134 Va. 503 | Va. | 1922
delivered the opinion of the court.
This action was brought by A. D. Watts against the Southern Railway Company to recover entire damages to a tract of land caused by changing the channel and retarding the flow of a natural stream of water which runs through the land. There was a verdict and judgment below in favor of the plaintiff, and the defendant assigns error. The parties to this writ of error will be designated as plaintiff and defendant, in accordance with their respective positions in the lower court.
The land here involved was formerly a part of a larger tract owned by A. L. Huntt. After his death a suit was brought to sell his real estate, and the land, in
As indicated above, commissioner Huntt sold the original Huntt tract in smaller parcels, and one of these, known in the record as the Leake land, lies below the Watts land, that is, between the Watts land and the point at which the creek was diverted in 1914, so that the creek runs through the Watts land, then through the Leake land, and thence into the new channel on the railroad right of way.
Section No. 2 referred to in the above mentioned report was the land sold by the commissioner to Mary O. Beard, and is now the Watts land. This report, which was dated September 10, 1915, was confirmed by a decree of September 24, 1915, and that decree contained this provision: “And it also appears that the Southern Railway Company has by the diversion of the waters of Rutledge creek * * * probably caused damage to sections 1, 2, 3 and 4, and that the purchasers should, upon compliance with the terms of their respective purchases, acquire any and all right of action the parties to this suit might have against said Southern Railway for such damage, the court doth adjudge, order and decree that Mary O. Beard, the purchaser of said section 2, shall as a part of her purchase acquire any and all right and claims of the parties to this suit against the said Southern Railway to institute an action for and to
The deed from Leake, commissioner, to Mary O. Beard, and the deed from Mary O. Beard to A. D. Watts, each purported to pass to the grantees therein such right of action against the railway company as was described in the above recited terms and provisions of the report and decree.
It will be observed that the report of commissioner Huntt stated that the diversion of the stream had already caused “some damage” to sections 1, 2, 3 and 4; that the decree confirming the sales recited that such diversion had “probably caused damage thereto;” and that the decree and the deeds above mentioned passed to Beard and Watts successively such right of action on that account as belonged to the former owners of the land at the time of the sale. None of these records, however, establishes as a fact any actual damage to the land, or any part thereof, before the division and sale. That question was not an issue in the suit in which the sales were made, and was open to inquiry in the trial of this case.
Whether any actual damage had resulted from the diversion of the stream to any part of the Huntt land prior to the sales is a question which the evidence leaves in doubt. One of the plaintiff’s witnesses said that within a month after the water was turned into the new channel, following a heavy rain, the whole of what is now the Watts bottom land was covered with water because the new outlet was too small to carry it off; but he added that no injury resulted therefrom, and that he never noticed any injury to any part of either the Leake or Watts land until two or three years later. Certain other witnesses for the plaintiff said that the creek bed
Without going into more detail as to the evidence, which we have examined most carefully, we are constrained to the conclusion that the question as to when the first actual damage resulted to any part of the original boundary was one for the jury to determine.
The question is important because this case turns upon the effect of the statute of limitations. The plaintiff is suing for permanent injury to the value of the land and concedes that the case is one for the recovery of entire damages. The defendant interposed a plea of the statute of limitations. The suit was brought in No
The defendant contends that, since the damage was unquestionably caused by a permanent work of railway construction, the right of action accrued as soon as the construction was completed. If this contention is sound, it ends the ease, for the construction was completed in 1914 and the action was brought more than five years thereafter.
The defendant contends further that even if the right of action did not accrue until some actual damage resulted, still the action is barred because the evidence shows that the actual injury to the land had begun in 1915 and more than five years before the institution of the suit. If this be true, and, further, if the actual damage started prior to the severance of the land into smaller parcels by the sale in 1915, then this alternative contention of the defendant is likewise the end of the case. If the injury to the land developed before the division, the right of action was entire, the statute began to run at once as to the whole boundary, and its running was not suspended or affected by a subsequent division of the land into parcels. We have already seen, however, that this latter contention of the defendant is concluded by the verdict of the jury. It is not questioned that the burden of proving the facts necessary to establish the application of the statute of limitations was on the defendant. Goodell’s Ex’rs v. Gibbons, 91 Va. 608, 22 S. E. 504; Va. Ry. & P. Co. v. Ferebee, 115 Va. 289, 78 S. E. 556; Va. L., etc., Co. v. O. D. McHenry, 122 Va. 111, 122, 94 S. E. 173.
The final question then is, did the statute begin to run as soon as the construction of the railway company’s new work was completed, or did it only begin to run
There have been a number of cases in this State, and very many more in other jurisdictions, dealing with the limitation of actions for damage to real estate caused by permanent structures. In the majority of such cases, the precise and sharply defined question here under consideration has not arisen. In most cases of permanent works resulting in such an injury to land as that the owner may recover in one action all damages, past, present and future, the completion of the work and the commencement of the damage are practically simultaneous. This, either expressly or inferentially, appears to have been true in Virginia Hot Springs Co. v. McCray, 106 Va. 461, 56 S. E. 216, 10 L. R. A. (N. S.) 465, 10 Ann. Cas. 179; Southern Ry. Co. v McMenamin, 113 Va. 121, 73 S. E. 980; Worley v. Mathieson Alkali Works, 119 Va. 862, 89 S. E. 880; Magruder v. Va. Car. Chem. Co., 120 Va. 352, 91 S. E. 121; and Southern Ry. Co. v. Fitzpatrick, 129 Va. 246, 105 S. E. 663.
The case of McKinney v. Trustees of E. & H. College, 117 Va. 763, 86 S. E. 115, was an injunction suit, and did not determine whether the injury was to be regarded as permanent or intermittent, or whether an action for entire damages would lie, but it does hold that no cause of action accrued until some actual damage was done, quoting with approval the following from 1 Farnham on Waters and Water Rights, sec. 139b: “And the injury must be present and not prospective. The consequence of this is that the right of action accrues at the time the injury is done, regardless of the time when the works were completed.”
The case of Southern Ry. Co. v. White, 128 Va. 551, 104 S. E. 865, did not involve the statute of limitations, but the opinion shows that the court (1) treated the injury to the land as permanent, and (2) regarded the cause of action as having arisen, not when the work of construction was completed, but when the first damage caused.thereby was suffered. If this is the true import of the decision, and we think it undoubtedly is, then this White Case is directly in point as authority for the proposition that, in actions for entire damages resulting from railway structures, the limitation begins with the damage and not with the completion of the work.
In Southside R. R. Co. v. Daniel, 20 Gratt. (61 Va.) 344, 367, the damage complained of resulted from an insufficient waterway. The railway company had the right to construct the waterway, but did the work in such a manner as not to allow the flood waters of a creek to escape as they had formerly done. No question of the statute of limitation arose, and the case was not classed as one for the recovery of entire damages, but the following language of the opinion by Judge Staples is in point: “Where, however, the act is lawful in itself, but negligently and improperly performed, the gist of the action is the damage, without which there can be no recovery.” In the instant case, the work of Ailing the
So, too, in Virginian Ry. Co. v. Jeffries’ Adm’r, 110 Va. 471, 66 S. E. 731, which was held by this court to be controlled by the Daniel Case, supra, it was said by Judge Cardwell, in delivering the opinion, that “no injury having occurred to the sand bank directly from the erection of the embankment by the railway company, which was a lawful act, no suit could have been maintained until some actual injury was caused to the plaintiff’s intestate by the action of the water in the river.”
In Freeman’s note to Eells v. C. & O. Ry. Co., 87 Am. St. Rep. at p. 791, it is said: “The statute of limitations does not begin to run against a landowner’s right of action for the unlawful flowage of his land until he has been injured, and his action has accrued, notwithstanding' the negligent structure and other acts causing the overflow may have been growing and working for a length of time beyond the period of limitation. If a structure, when completed, is permanent in character, but not necessarily a nuisance, and afterwards becomes one, the statute begins to run from the time an injury is received, and not from the time the structure is erected,” citing numerous cases.
The case of Ridley v. Seaboard, etc., R. R. Co., 118 N. C. 996, 24 S. E. 730, 32 L. R. A. 708, was, by reason of the pleadings, treated as one for entire damages, and the court held that the statute of limitations against the ac
In Powers v. Council Bluffs, 45 Iowa 652, 24 Am. St. Rep. 792, it appeared that the city cut a ditch in 1859 along the end of the plaintiff’s lots, and turned into this ditch a stream of water flowing from the lots. No injury resulted to the plaintiff until 1866, when a cavity in the ditch, which began to form earlier and at a point remote from the plaintiff’s lots, had gradually cut back up the stream and reached his property. The suit was not brought until, counting from the year 1866, the statutory period of limitation to actions in Iowa for entire damage had elapsed. The city pleaded the limitation, and the trial court, holding that the injury was permanent and the plaintiff’s remedy therefor was complete when the damage first intervened, directed a verdict for the defendant, which was sustained on appeal. The case is in point here because, although a recovery was denied, the court held that the cause of action arose, not when the ditch was constructed, but when its construction first caused damage to the plaintiff. The court, on this point, said: “No suit could have been maintained until some actual injury was caused to the plaintiff by the action of the water, resulting from the improper construction of the ditch. Washburn on Easements and Servitudes, 591. But in 1866, if not earlier, the plaintiff’s premises began to be injured, and then, of course, he had a right of action.”
The decision in the case last cited is criticised in a note to Wood on Limitations (3rd ed.), p. 411, 412, but not upon the proposition for which it is here cited. That criticism is directed to the holding therein that the case was one for entire damages. We are not concerned with
The several specific assignments of error will now be briefly discussed.
1. It is urged that the court erred in granting and refusing instructions, and'in declining to set aside the verdict and enter a final judgment for the defendant. This contention is rested upon the theory that the cause of action accrued when the construction work by the defendant was completed, and also, upon the theory that some actual damage was conclusively shown to have resulted to the plaintiff’s land more than five years before the suit was brought. In granting and refusing instructions, and in ruling upon the motion to set aside the verdict, the trial court acted in conformity with the views which we have hereinabove expressed. It could not, in view of the evidence, properly set aside the verdict upon the question as to when the first damage was done to the plaintiff’s land. As to the instructions, the court told
“The court instructs the jury that even though they may believe that the plaintiff or his predecessor in title, could not, at the time of the completion of the construction work by the defendant, which is complained of, have discovered or been able to tell that his land would be damaged by the said diversion of the said stream and the construction work; yet, if they believe from the evidence that the property was damaged to any extent, more than five years prior to the institution of this action, they must find for the defendant, as the action should have been brought within five years from the date on which the property was first damaged to any extent.”
There was no error in the instructions, or in the refusal to set aside the verdict as contrary to the evidence.
2. Another ground on which the court below was asked to set aside the verdict was that the damages awarded were excessive; and we are now asked to reverse the judgment on that ground. The amount fixed by the verdict was $1,430.00. Watts paid only $1,600.00 in September, 1920, for the, whole tract of twenty-eight acres purchased by him from Beard. This same tract, being section 2 of the Huntt land, was bought by Beard at the sale in July, 1915, for $1,230.00, at which time it had suffered no material damage from the diversion of
3. We have not overlooked the two remaining assignments, but have given them careful consideration with the result that we do not find anything in them which would justify a reversal of the judgment. One of them complains of leading questions and the other of the introduction of so-called hearsay evidence. The questions complained of as leading were objectionable on that ground, but the objection was not made until after a number of them had been answered, and, moreover, the answers thereto were merely cumulative of other evidence in the case to which there was and could have been no objection. The so-called hearsay evidence, if it was hearsay, could not have prejudiced the defendant. It was in answer to the statements in the commissioner’s report of sale, introduced by the defendant over the plaintiff’s objection, and its purpose was to minimize the effect of that report. We have already held that the report had no probative value as to the damage, and the attack upon it in this respect was harmless.
We find no error in the judgment complained of, and the same must be affirmed.
Affirmed.