OPINION
Two nuclear utilities seek damages for the failure of the United States Department of Energy (“DOE”) to commence performance of its contract to accept, transport and dispose of their spent nuclear fuel (“SNF”).
The court has jurisdiction over plaintiffs’ claims. PSEG Nuclear, L.L.C. v. United States,
The Federal Circuit held in Indiana Michigan, that while nuclear utilities could not recover their forecasted future costs of storing SNF that DOE contracted to remove, appropriately established and incurred mitigation expenses were recoverable. On September 15, 2005, the parties agreed that trial in this matter would be limited to costs incurred through December 31, 2004. On September 16, 2005, the court ordered that “[t]he scope of the trial proceedings in this matter will comprise damage evidence up to and including December 31, 2004.” (Order, Sept. 16, 2005, Dkt. 304, 2.) Plaintiffs’ Amended and Supplemental Complaint for damages through December 31, 2004 was deemed filed as of October 11, 2005. (Order, Oct. 26, 2005, Dkt. 315.) After a lengthy trial, the parties submitted post-trial briefs.
Introduction
Following the enactment of the NWPA, Pub.L. No. 97-425, 96 Stat. 2201 (Jan. 7, 1988) (codified at 42 U.S.C. §§ 10101-10270), plaintiffs, along with all domestic nuclear electrical utilities, signed Standard Contracts with DOE wherein, in return for the utilities’ payment of substantial fees, DOE would accept title to designated SNF at the reactor sites, and transport and dispose of the utilities’ SNF, starting on or before January 31, 1998. DOE did not commence performance by January 31, 1998 as required by the NWPA and the Standard Contracts. While DOE insists there will be performance, the forecasted inauguration continues to recede from 2003, to 2010, to 2017, and to 2018, the latest prognosis.
Standard Contracts were signed by plaintiffs Georgia Power Company (“GPC”) and Alabama Power Company (“APC”). APC owns Plant Farley. GPC holds a majority interest in Plants Hatch and Vogtle.
Plaintiffs seek reimbursement of their actual costs spent mitigating DOE’s delays. Rather than allow their spent fuel pools to completely fill with SNF, which would result in shutting down their reactors, replacing that source of electricity at a much higher cost, plaintiffs decided to incur the relatively lesser expense of additional on-site storage. Substantial costs (the amounts of which are mostly not disputed) were incurred to design, engineer, license, construct, install, load, operate and maintain this additional storage. As described in more detail hereinafter, at Plant Hatch, an Independent Spent Fuel Storage Installation (“ISFSI”), consisting of four highly-engineered concrete pads, each with a capacity to hold twelve dry SNF storage casks, was built. By December 31, 2004, twenty-two casks were purchased, loaded with SNF and placed on the pads. Construction of Plant Farley’s ISFSI began in 2000, and as of December 31, 2004, three dry SNF storage casks were purchased but had not been loaded. From 1998 to 2000, Plant Vogtle procured and installed racks to increase the capacity of its spent fuel pool. The actual costs of these mitigation measures are sought in this action.
Upon careful consideration of testimony, argument, documents and exhibits, the court concludes that plaintiffs incurred substantial costs in mitigating DOE’s acknowledged, continuing and substantial delay in commencement of performance—a partial breach of contract, which was a substantial causal factor in these mitigating storage decisions and of the reasonable costs thereof, and that but for the delay, these expenditures would not have been incurred. The court finds that, in the main, those mitigation decisions and costs were foreseeable and reasonable.
• A brief discussion of the generation of nuclear power provides background for the court’s findings and conclusions. Uranium oxide pellets (little finger-sized) are placed into 12-14 foot metal rods and bundled into assemblies, approximately nine inches square. Assemblies are placed in the reactor core, where fission produces heat, which is converted to steam, which drives turbines and generates electricity. (Tr. 142 (Long).) Nuclear-generated power constitutes 16 percent of the total electricity used by plaintiffs’ some four million customers
A. [T]he Southern system has a system that’s about 40,000 megawatts total. In that system, power is generated from basically four different sources. One is our coal plant. That’s our largest ... about 69 percent of the power that’s generated by the Southern Company comes from the coal plants. [Sixteen] percent, the second largest generator of electricity in the Southern system is out of our nuclear plants. And then we also have about 12 percent comes from gas and then about 3 percent comes from hydro. So nuclear is the second largest generator of electricity on the Southern system. The importance, though, is really relative to the cost of electricity out of those four sources. And the amount of time that each of these plants will run. Basically, nuclear is the cheapest production cost of any plant out of our system. They are the most valued from an economic viewpoint. We run our nuclear power plants 24 hours a day, seven days a week, as long as we can run them.
[O]ur nuclear plants, because they are the cheapest, run all the time.... The other additional benefit that nuclear has is there are no emissions associated with its generation, no SO2, no nitrous oxide, and no particulates, no mercury---- [N]uclear is quite candidly the ... best source of generation we have both in terms of cost and emission for our system.
(Tr. 135-38 (Long).)
After four to six years, the uranium in the reactor becomes somewhat depleted or “spent,” meaning it becomes relatively inefficient for producing electricity. The reactor is shutdown and assemblies (or rods) containing SNF are removed from the core, replaced with “fresh” fuel. The SNF is placed in basket-like racks in adjacent pools filled with treated water to protect against radioactivity. The pools are monitored with highly sophisticated devices to protect the workers and the environment. With rotational planning, generally about one-third of the core is removed during these scheduled refueling shutdowns.
Plaintiffs’ wet pools are about 30 by 40 feet and 40 feet deep, made of concrete and lined with stainless steel. When SNF is removed from the reactor core, it is still capable of attaining criticality. Transporting rods in or out of the reactor core, or in and out of the wet pool, is a complex, expensive and highly regulated process. See Twp. of Lower Alloways Creek v. Pub. Serv. Elec. & Gas Co.,
The two nuclear reactors at both Plants Hatch and Vogtle share one pool. Each of the two reactors at Farley have their own pool. The shared pool at Plant Hatch contains a rectangular section, referred to as the “bathtub” area, used for the operation and storage of neutron monitoring instruments and tools.
Historically, the disposal of SNF and high-level waste (“HLW”) from the commercial production of nuclear power has been a federal responsibility. See Florida Power & Light Co. v. Westinghouse Elec. Corp.,
The 1983 passage of the NWPA reaffirmed federal responsibility “to provide for the permanent disposal of high-level radioactive waste and such spent nuclear fuel as may be disposed of in order to protect the public health and safety and the environment.” 42 U.S.C. § 10131(a); Indiana Michigan,
The NWPA authorized DOE to enter into contracts with nuclear utilities for the acceptance, transportation and disposal of SNF. Indiana Michigan,
(A) following commencement of operation of a repository, the Secretary shall take title to high-level radioactive waste or spent nuclear fuel involved as expeditiously as practicable upon the request of the generator or owner of such waste or spent fuel; and
*402 (B) in return for the payment of fees established by this section, the Secretary, beginning not later than January 31, 1998, will dispose of the high-level radioactive waste or spent nuclear fuel involved as provided in this subehapter.
42 U.S.C. § 10222(a)(5).
Under the Standard Contract, fees paid by the utilities were deposited into the Nuclear Waste Fund (“NWF”).
Plaintiffs have paid approximately $850 million in fees into the NWF as of December 31, 2004 and payments continue. (Tr. 251 (Cocherell).) In the aggregate, nuclear utilities have paid over $20 billion into the NWF. Yankee Atomic Elec. Co. v. United States,
Notwithstanding the foregoing, the repository at Yucca Mountain remains unbuilt and commencement of contract performance is further out on the horizon. The “best-achievable” date is 2017. Statement of Edward P. Sproat III, Director, Office of Civilian Radioactive Waste Management (“OCRWM”), before the Subcommittee on Energy and Air Quality, Committee on Energy and Commerce, United States House of Representatives, July 19, 2006, available at www.ocrwm.doe/gov/infoJibrary/program_ does/testimonies/July_19_Sproat-testimony. pdf (last visited May 17, 2007). That date may slip to 2018. Sproat Statement before the Senate Appropriations Subcommittee on Energy and Water Development, March 7, 2007, available at www.ocrwm.doe.gov/ welcome/index.shtml (last visited May 17, 2007). See also Def.’s Ans. to Second Am. Compl. and Supplemental Compl. 11 in System Fuels, Inc. v. United States, No. 03-2624 (Fed.Cl.), Dkt. 125, filed Jan. 30, 2007 (citing Statement of OCRWM Director Sproat before Subcommittee Clean Air, Climate Change and Nuclear Safety, Committee on Environment and Public Works, United States Senate, September 14, 2006, that DOE planned to initiate repository operations in 2017).
Damages:
Faced with DOE’s impending delay in commencement of performance detailed hereinafter, and mindful of long lead times for approval and implementation of storage options required to continue operations, plaintiffs assert their decisions to increase storage, the implementation of those decisions and the reasonable costs thereof were necessary, foreseeable and caused by DOE’s partial breach, and are accordingly, recoverable. Plaintiffs also contend defendant did not meet its burden to establish either that these decisions, their implementation or cost, were unreasonable.
In addition to asserting plaintiffs did not meet their burden of establishing foreseeability, causation and reasonable certainty in amounts, defendant argues plaintiffs have another burden—to establish that their mitigation costs would not have been incurred if DOE had performed in the so-called non-
Plaintiffs urge the court to find that DOE would or should have performed in the non-breach world at an annual rate of 3000 MTU. At that level, there would not be a windfall— DOE would have removed more SNF than plaintiffs have actually placed in storage; accordingly, by reimbursing the costs as sought herein, plaintiffs would not be better off than if DOE had performed. Plaintiffs also contend they need not establish precisely how much SNF DOE would have removed and when. Rather, plaintiffs assert their decisions to construct dry storage at Plants Hatch and Farley, and rerack at Plant Vog-tle, were reasonably foreseeable, caused by DOE’s acknowledged breach and were reasonable mitigating reactions, the costs of which were shown with reasonable certainty.
“The remedy for breach of contract is damages sufficient to place the injured party in as good a position as it would have been had the breaching party fully performed.” Indiana Michigan,
Mitigation was required. As the Federal Circuit made clear in Indiana Michigan, by 1994 when DOE formally and publicly announced it was not going to initiate performance by January 31, 1998, nuclear utilities were obligated to mitigate.
In 1994, DOE announced that it would not begin SNF collection until 2010 because its planned storage repository would not be ready until then. Notice of Inquiry, Office of Civilian Radioactive Waste Management: Waste Acceptance Issues, 59 Fed. Reg. 27,007-27,008 (May 25, 1994). One year later, DOE asserted that it had neither a statutory nor contractual obligation to accept the utilities’ nuclear waste in the absence of such repository or temporary storage facility. Maine Yankee,225 F.3d at 1338 (citing Final Interpretation of Nuclear Waste Acceptance, 50 Fed.Reg. 21,-793 (1995)).
Generally mitigation, or more precisely, the failure to mitigate, reduces consequential damages awarded to a nonbreaching party. “The amount of loss that [the non-breaching party] could reasonably have avoided by ... making substitute arrangements or otherwise is simply subtracted from the amount that would otherwise have been recoverable as damages.” Restatement (Second) of Contracts § 350 cmt. b. Similarly, “ ‘mitigation damages’... are intended to reimburse a non-breaching party to a contract for the expenses it incurred in attempting to rectify the injury the breach caused it.” Citizens Fed. Bank v. United States,
Mitigation costs must have been “reasonably foreseeable by the breaching party at the time of contracting.” Indiana Michigan,
Since before the NWPA, or the formulation of the Standard Contract, DOE was aware that utilities faced enormous storage costs. Indeed, avoidance of these costs was an impetus for, and objective of, the NWPA. From the inception of the SNF program, DOE planning documents cited avoidance of these costs as a program goal. Whether aspirational objectives, goals or contractual requirements, the court relies on these statements for foreseeability as well as what would have been reasonable or unreasonable performance by DOE, discussed infra. Tennessee Valley Auth.,
Generally, foreseeability is determined at the time of contracting. Indiana Michigan,
While the general response to a breach must be foreseen, the particular way that a mitigating decision is implemented need not.
[A] breaching party should not be liable for damages that “it did not at the time of contracting have reason to foresee as a probable result of such a breach.” If it was foreseeable that the breach would cause the other party to obtain additional capital, there is no requirement that the particular method used to raise that capital or its consequences also be foreseeable. “What is required is merely that the injury actually suffered must be one of a kind that the defendant had reason to foresee and of an amount that is not beyond the bounds of reasonable prediction.”
Citizens Fed.,
Particularly here, where performance is delayed for decades during which technology advances, there may be tension between what may have been foreseeable consequences in the 1980s, vice what may be commercially reasonable mitigation measures when the upcoming delay(s) were announced and when mitigation measures were required, or at the time of the breach. “[M]iti-gation in a contract that spans the ages is not limited to decades-old technology____[Plain-tiffs] were required to mitigate and their selection of these containers was commercially reasonable and defendant did not establish that it was unreasonable.” Yankee Atomic,
The court notes that, to hold otherwise would be to provide a perverse incentive to non-breaching parties attempting to mitigate their foreseeable damages from a breach of contract through reasonable and appropriate methods. If the most reasonable and appropriate method of mitigating a non-breaching party’s foreseeable damages happens to be one that was not available at the time of contracting, and courts were to deny recovery because of this, non-breaching parties to contracts would have a significant disincentive to taking reasonable and appropriate steps to mitigate a breach of contract.
Pacific Gas & Elec., 73 Fed Cl. at 419 n. 71.
The breach must be a “substantial causal factor” in the mitigation decisions. In Citizens Federal Bank v. United States,
The Federal Circuit in Indiana Michigan upheld the trial court’s finding that DOE’s
Indiana Michigan’s pre-breach costs were not caused by any anticipated DOE delay in performance. It authorized the expenditure for its reracking projects in 1989, in the normal course of business, six years before the 1994 Notice of Inquiry announced DOE’s inability to begin timely SNF collection. In light of that fact, the trial court found that Indiana Michigan’s rerack schedule was not affected by 1987 and 1989 DOE announcements projecting delays in the scheduled January 1998 acceptance start date. And [Indiana Michigan’s] decision to perform a full instead of a partial, rerack in 1995 was purely a business judgment which it would have had to pursue irrespective of DOE’s partial breach.
Mitigating decisions are constrained by commercial reasonableness. Citizens Fed.,
The Federal Circuit in Indiana Michigan confirmed the application of these bedrock principles:
Section 350, comment b of the Restatement of Contracts advises that “[o]nce a party has reason to know that performance by the other party will not be forthcoming, ... he is expected to take such affirmative steps as are appropriate in the circumstances to avoid loss by making substitute arrangements or otherwise.” Indiana Michigan is “not precluded from recovery ... to the extent that [it] has made reasonable but unsuccessful efforts to avoid loss.”
“[T]he established standard for evaluating the reasonableness of mitigation efforts is ‘from the perspective of one viewing the situation at the time the problem was presented.’ ” Franconia Assocs. v. United States,
Generally, the breaching party may not complain that one of several reasonable courses of action were taken. “ ‘The rule of mitigation of damages may not be invoked by a contract breaker as a basis for hypercritical examination of the conduct of the injured party, or merely for the purpose of showing that the injured person might have taken steps which seemed wiser or would have been more advantageous to the defaulter.’ ” Sacramento Mun. Util.,
Although defendant disagrees, plaintiffs assert that defendant bears the burden of establishing that mitigating decisions or expenditures were unreasonable. Plaintiffs are correct. In Old Stone, the government breached its contract with the thrift by eliminating regulatory capital. The Federal Circuit rejected the government’s claimed error in the trial court’s award of the cost of replacement capital in excess of the required regulatory minimum, concluding the government did not prove that the thrift’s mitigation efforts were unreasonable.
In Home Savings, we recognized that “[w]hen mitigating damages from a breach, a party ‘must only make those efforts that are fair and reasonable under the circumstances.’ ”399 F.3d at 1353 (quoting Robinson v. United States,305 F.3d 1330 , 1333 (Fed.Cir.2002)); see also 11 Corbin on Contracts § 57.11, at 311 (2005 ed.) (“The doctrine of avoidable consequences merely requires reasonable efforts to mitigate damages.”); 3 Dobbs: Law of Remedies § 12.6(1), at 127 (2d ed. 1993) (“[T]he damage recovery is reduced to the extent that the plaintiff could reasonably have avoided damages he claims and is otherwise entitled to.”). The government has not shown that it was unreasonable for [the thrift] to replace the entire amount of regulatory capital that was eliminated by FIRREA ... so that the thrift had a cushion against future losses.
The court’s findings on reasonableness and substantial causation are also informed by Hughes Communications Galaxy, Inc. v. United States,
Another instructive case is Chain Belt Co. v. United States,
[P]laintiff was under an obligation to avoid by a reasonable effort any damages which it should have foreseen and, having done so, it may recover as damages the expense incurred in such reasonable effort to avoid harm.... It makes no difference whether the breach has already occurred, or where ... it is merely impending under circumstances such that it was not reasonable for plaintiff to expect defendant to prevent the harm.
Plaintiffs must establish the amount of their recoverable costs with reasonable certainty. Indiana Michigan,
Development of the Standard Contract
As background for the court’s findings herein, the development of the Standard Contract and the evolution of performance planning by DOE and monitoring by nuclear utilities is summarized.
The NWPA authorized DOE to enter into contracts for the acceptance, transportation and disposal of SNF.
On February 4, 1983, after receiving preliminary comments from nuclear industry groups, DOE published a proposed Standard Contract. 48 Fed.Reg. 5458-71 (Feb. 4, 1983). The Federal Register Notice stated that “[the NWPA] directs DOE to begin
[W]e would like to emphasize the importance of the annual receipt rate of the disposal facility being designed, to the extent practicable, to be commensurate with the levels of spent nuclear fuel being generated annually and the need to also reduce the back-log of spent fuel as expeditiously as possible. Consistent with section 302(a)(5) of the Act, the contract should express the intent of DOE to take title to spent nuclear fuel as expeditiously as practicable upon request of the generator or owner.
(PX 46, 47.) Industry groups and other utilities also complained of the lack of an acceptance rate in the proposed contract. (PX 48 (comments from Edison Electric Institute (“EEI”), an association of investor-owned utilities and the Utility Nuclear Waste Management Group (“UNWMG”), a consortium of 43 utilities).)
Bruce Hunt,
On April 18, 1983 DOE issued the final Standard Contract. 48 Fed.Reg. 16,590-01. The “expeditiously as practicable” phrase from plaintiffs’ (and others) comments was added as a preamble. “Whereas, the DOE has the responsibility, following commencement of operation of a repository, to take title to the spent nuclear fuel or high-level radioactive waste involved as expeditiously as practicable upon the request of the generator or owner of such waste or spent nuclear fuel....” 48 Fed.Reg. at 16600 (emphasis supplied). (PX 750 at SN059469; PX 751 at SN138239 and SN138176; PX 752 at SN0C01233.)
This contract applies to the delivery by Purchaser11 to DOE of SNF and/or HLW of domestic origin from civilian nuclear power reactors, acceptance of title by DOE to such SNF and/or HLW, subsequent transportation, and disposal of such SNF and/or HLW and, with respect to such material, establishes the fees to be paid by the Purchaser for the services to be rendered hereunder by DOE. The SNF and/or HLW shall be specified in a delivery commitment schedule as provided in Article Y below. The services to be provided by DOE under this contract shall begin, after commencement of facility operations, not later than January 31, 1998 and shall continue until such time as all SNF and/or HLW from the civilian nuclear power reactors specified in Appendix A, annexed hereto and made a part hereof, has been disposed of.
10 C.F.R. § 961.11, Art. II. DOE’s obligation to commence performance was not conditioned on the existence of “a facility.”
GPC signed Standard Contracts for Plant Vogtle and Plant Hatch on June 10, 1983; APC signed for Plant Farley on June 13, 1983.
While the Standard Contract did not contain a rate or schedule for the acceptance of SNF either on an industry-wide basis or by specific utility, it included a process by which a schedule and quantities would be established. Pacific Gas & Elec.,
As an initial matter, under the Standard Contract, priority of acceptance is generally based on the age of the SNF, calculated from the date the material was discharged from the reactor core. Standard Contract, Art. VI.B.1(a); see also Art. IV.B.5(a) (“[Pjriority ranking shall be based on the age of SNF and/or HLW as calculated from the date of discharge of such material from the civilian nuclear power reactor. The oldest fuel or waste will have the highest priority for acceptance, ----”). This priority is referred to as Oldest Fuel First (“OFF”). Beginning annually starting on January 1, 1992, utilities were required to submit for DOE’s approval, a proposed Delivery Commitment Schedule (“DCS”), specifying the amount of SNF it “wishes to deliver to DOE beginning sixty-three (63) months thereafter.” Art. V.B.1. The amount of SNF in a proposed DCS was to be based on OFF allocations from two types of DOE documents—Annual Capacity Reports (“ACRs”) and Annual Priority Rankings (“APRs”). DOE would accept or reject the submitted DCSs. Any disagreement would be negotiated. To the extent a DCS was approved, the utility would then submit a Final Delivery Schedule (“FDS”) some four years later, one year prior to scheduled acceptance, describing in more detail the SNF to be relinquished. The utility could adjust the quantity of SNF by plus or minus twenty percent and the delivery date by two months. Art. V.B.
DOE’s ACRs
Mindful that DCSs were many years hence, beginning in June of 1987, DOE would
The first ACR issued in June of 1987 listed all SNF assemblies by date of discharge from the reactor, starting with the oldest (fuel discharged in 1959), cumulating a total of over 18,000 MTU, ending the listing with fuel removed in 1989. The assemblies were grouped into annual capacity segments based on the total amount DOE then-projected accepting. In “Years 1-5,” specific allocations of 1200 MTU annually are charted. For example, Year 1 listed the location of the oldest 1200 MTU of SNF. The next four years continued with the next oldest 1200 MTU. After five years at 1200 MTU annually (for a total of 6000 MTU), the allocations for subsequent years were: Year 6—2000 MTU; Year 7—2650 MTU; Year 8—2650 MTU; Year 9—2650 MTU; Year 10—2650 MTU. The ACR also noted whether transportation would be by rail or truck. The 1987 ACR contemplated initial acceptance at a monitored retrievable storage system (“MRS”) beginning in 1998, if Congressional approved DOE’s MRS proposal. In that event, repository operations would then begin in 2003. Acceptance of a total of 6000 MTU at an MRS prior to commencement of repository operations was contemplated (1200 MTU annually for the first five years). Future acceptance rates “may differ.” (PX 4.) The 1988 ACR (along with the 1988 Draft Mission Plan) delayed receipt at either an MRS or a repository until 2003, reaching an annual combined acceptance rate, using both an MRS and a repository, of 3000 MTU within five years. (Tr. 526-29 (Hunt).)
In its draft 1989 ACR, DOE recognized that delay in the repository and conditions imposed on the siting and construction of an MRS facility by the NWPA amendments (further discussed later) made it unlikely that DOE would be able to start accepting SNF significantly before 2003. Recognizing that a delay would increase utilities’ need for additional at-reactor storage, DOE was evaluating the costs and impacts of this delay and exploring whether the NWF could be used to cover costs. (PX 6.)
DOE’s December 1990 ACR utilized two waste acceptance schedules for the first ten years of operation, upper and lower bounding rates for DOE’s Waste Management System CWMS”), including an MRS if statutory conditions were removed and an early site was found. While the 1989 ACR presumed delay in commencement until 2003, the December 1989 ACR projected acceptance starting in 1998 with a ten-year cumulative rate of 24,-100 MTU (1200, 1200, 2000, 2000, 2700, then 3000) in the upper bounding case and 7375 MTU (300, 400, 550, then 875) for the lower bounding case. The upper bounding rates assumed that the linkages in the 1987 Amendments to the NWPA would be lifted by Congress. (Tr. 1773-74 (Kouts).) Similar to the 1987 ACR, individual utilities allocations for ten years under both the upper and lower bounding rates were charted, and all SNF was listed through 1992 by date of discharge from the reactor. Under the Standard Contract, it was to be the last in the series of DOE’s ACRs. Beginning in April of 1991, DOE would publish its first APR. Under the Standard Contract, the APR would
Under OFF,
DCSs, which would identify “all SNF and/or HLW the Purchaser wished to deliver to DOE”
DOE’s December 1991 ACR contained only one acceptance rate rather than the prior upper and lower bounding rates in the previous ACR. Commencement could begin in 1998 only if the NWPA was amended. “If the current [statutory] linkages between [an] MRS facility construction and repository construction authorization are maintained, it is estimated that commencement of facility operations and initial acceptance of SNF by DOE could not start until at least 2007.” (PX.8.) The annual rates (400, 600, 900 thereafter until 2007) reflected the 10,000 MTU statutory storage capacity limit placed on an MRS, and the rates were “representative” of a WMS that included an MRS.
Plaintiffs cite DOE’s ACRs as support for their growing anxiety over DOE’s inability to commence performance by January 31, 1998. In that regard, in making its findings herein, particularly on causation, foreseeability and reasonableness, the court relies on, and compares, evidence at the time of contracting and DOE’s subsequent equivocations.
Shortly after the Standard Contracts were executed, at a conference of nuclear utilities and other program participants, Robert Morgan, Acting Director of the NWPA Project Office,
The fundamental objective of the Federal Waste Management System (“FWMS”) in OCRWM’s draft Mission Plan,
In February 1984 (eight months after plaintiffs signed the Standard Contracts), OCRWM’s Acting Director Michael Lawrence (Robert Morgan’s successor) testified before the Energy Conservation and Power Subcommittee of the House Committee on Energy and Commerce, presenting the FY 1985 budget. “The $327.7 million requested will be used to fund the activities under the NWPA of which the fundamental objective is for the [DOE] to accept high-level radioactive waste for safe management, storage and permanent disposal on a firm schedule, beginning not later than January 31, 1998.” (PX 54 at PNL-173-0226.) “By achieving this fundamental objective and implementing an appropriate waste acceptance schedule, this will initially preclude the need for additional at-reactor storage by nuclear utilities after January 31, 1998, and ultimately, remove all eligible waste from at-reactor storage.” (Id. at PNL-173-0228.)
OCRWM’s April 1984 draft Mission Plan, stated that “[i]n the event of a delay in repository operation, [DOE] could take the waste materials in accordance with the Waste Acceptance Schedule and arrange for either continued storage at the utilities in Federal storage casks, or for storage elsewhere pending transfer to the repository.” (PX 37.) The Waste Acceptance Schedule in the draft Mission Plan listed aggregate annual generation of spent fuel and discharge from decommissioned reactors, comprising the cumulative SNF inventory (43,800 MTU in 1998). Two repositories
While the April 1984 draft plan addressed reduction of backlog, it did not mention prevention of additional at-reactor storage. Plaintiffs expressed concern to DOE that the draft did not reflect the “clear understanding” reached with DOE in December of 1983 that “sufficient spent fuel would be shipped to federal facilities beginning in January 1998 so that no additional construction of storage capacity at utility plant sites would be required after 1998 [which] is a fair, reasonable, and proper interpretation of NWPA requirements.” (PX 267 at 2.)
Interdepartmental comments at that time were consistent with a program goal of eliminating the need for additional at-reactor storage. Michael Lawrence, who was then at DOE’s Richland Operations Office, wrote to Ben C. Rusche, Director of OCRWM on July 23, 1984, that (1) to eliminate the need for additional at-reactor storage after January 31, 1998, the initial acceptance rate would have to be at least 2800 MTU; (2) assuming DOE would be responsible for post-1997 additional storage, that cost would approximate one billion in 1983 dollars. (PX 506 at 783.) “Based upon our interpretation of the NWPA, the minimum acceptance rate should be based upon the rate at which spent fuel is generated by civilian nuclear power reactors. This would be consistent with NWPA intent that no power reactor would require additional spent fuel storage after January 31, 1998.” (Id.)
The Final Mission Plan in June of 1985, with acceptance starting in 1998, contained a 3000 MTU acceptance rate for the first repository after a ramp-up (400, 400, 400, 1800 and then 3000). The second repository would be added in 2006 starting at 900 MTU, then 1800 for 2007 through 2010, 2400 in 2011, and 3000 thereafter through 2030. (PX 38 at 26.)
Plaintiffs cite to witness testimony that DOE’s objective and planning was to avoid additional at-reactor storage; that 3000 MTU a year would achieve that goal; that DOE understood Congress did not intend for utilities to have paid billions into the NWF and have to bear the cost of additional at-reactor storage after 1998; that before a utility would run out of storage space, DOE would pickup. (Pis.’ Posh-Trial Br. 35-37.) The intent of the DOE at the time of the execution of the Standard Contracts was “to get a facility operating in '98, to take the stuff away fast enough so that utilities would not have to add additional storage. That was the intent.” (Id. at 37, citing Cole Dep. 80-81, Mar. 12, 2002 (PDD 11).) To meet that goal and to reduce the backlog of accumulated SNF, the DOE initially planned a 3000 MTU rate. (Id.) DOE’s RCFC 30(b)(6) witness testified that DOE’s goal in the mid-1980s was to “alleviate the purchasers’ need to have storage outside of their [spent fuel] pools.” As calculated by DOE, the rate that would achieve that objective was 3000 MTU annually. (Pollog Rule 30(b)(6) Dep. 96-97, Apr. 11, 2002 (PDD 26).)
DOE also used a 3000 MTU annual rate for operational and financial planning, particularly in assessing program costs and the adequacy of the 1 mil per kilowatt hour fee charged to the utilities under the Standard Contract. (Pis.’ Br., 40-45.) OCRWM’s more recent WMS requirements documents have acceptance rates of 400, 600,1200, 2000, and 3000 MTU annually with performance commencing in 2010. (PX 98 (Jan.2002); PX 170 (May 2002); PX 180 (Sept.2004).)
The 1987 Amendments to the NWPA
In March 1987, DOE sought Congressional authority to construct an MRS as an integral part of the WMS, both for storage and as a central receiving station, to prepare fuel for emplacement in the repository. (PX 59.) The proposal was that acceptance at an MRS could not occur until construction authorization for the first repository was received. The MRS could accept no more than 15,000
In its 1987 Mission Plan, DOE formally announced a five-year delay in the commencement of repository operations from 1998 to 2003, and its proposal to accept SNF during this five-year period at an MRS. (PX 39, 40.) DOE also reported thirty-five pending lawsuits, any one of which could affect the repository schedule. (PX 40 at 5.) The MRS was planned as a stand-alone facility from 1998 to 2003 when SNF would then be gradually transferred from the MRS to the repository. (PX 40 at 12, 61.) DOE’s Chief Operating Officer, Ron Milner, testified the MRS could have operated at an annual acceptance rate approaching 3000 MTU consistent with prior planning.
MRS—Spent MRS—Spent Shipped from fuel fuel in MRS to Year received storage repository
1998 1200 1200
1999 1200 2400
2000 1200 3600
2001 1200 4800
2002 1200 6000
2003 2000 7600 400
2004 2650 9850 400
2005 _2650_12100_400
2006 2650 13850 900
2007 2650 14700 1800
2008 2650 14700 2650
2009 2650 14700 2650
2010 2650 14700 2650
2011 _2650_14700_2650
2012 _2650_14700_2650
(PX 40 at 61.) At these rates, with shipment from the MRS to a repository starting in 2003, the MRS inventory would not exceed its 15,000 MTU capacity under DOE’s proposal. DOE’s objective with these acceptance rates was to prevent additional at-reactor storage and reduce SNF backlog. (Pollog RCFC 30(b)(6) Dep. 202-03, Apr. 11, 2002 (PDD 29).) This is how DOE planned on “performing” before the intervention of the 1987 Amendment to the NWPA in which Congress, not the Standard Contract, constrained capacity and timing.
In December 1987 amendments to the NWPA, Congress authorized an MRS, but with more stringent conditions than DOE had proposed. While DOE had proposed no waste acceptance at an MRS until construction of a repository had been authorized, Congress precluded construction of an MRS until construction of the repository had been authorized. 42 U.S.C. § 10168(d)(1). This condition would delay commencement by five years. (DX 71.) Congress also limited acceptance at an MRS to 10,000 MTU until a repository started accepting SNF, and then the capacity was limited to 15,000 MTU. 42 U.S.C. § 10168(d)(3) and (4). And, in any event, an appropriate MRS site had to be located. No site was located. The conditions for the construction of an MRS were never met. These statutory conditions were never amended or rescinded and there is no MRS. The Standard Contract does not contain these constraints.
In June 1988, DOE issued another draft amendment to the Mission Plan. Acceptance at a repository was again predicted to start in 2003, assuming construction authorization in 1998. (PX 42 at 15; Tr. 1987 (Zabransky); Tr. 1819-23 (Kouts).) Also in June 1988,
The delay in the repository schedule first noted in the OCRWM Mission Plan Amendment published in June 1987 and the conditions imposed on the siting and construction of an MRS facility by the [1987 NWPA amendments] make it unlikely that DOE will be able to start accepting SNF significantly before 2003. As recognized in the draft Mission Plan Amendment, earlier waste acceptance would require additional Congressional action or an acceleration of the system development schedule by some other means. Under current conditions, the owners and generators of SNF will continue to be responsible for storing their spent fuel until acceptance by DOE. The DOE will continue working with the Purchasers to expedite the effective use of available storage and the development of additional storage at reactor sites.
(DX 71 at 4 (footnote omitted).) Assuming repository construction would be authorized in 1998, commencement in 2003 was thought to be achievable. It was assumed the MRS and repository would commence acceptance simultaneously, accepting at total of 1200 MTU in 2003; 1200 MTU in 2004; 2000 MTU in 2005 and 2006; 2700 MTU in 2007; and 3000 MTU in 2008 through 2012, for a total of 24,100 MTU in the first ten years. (Id. at 5.) The 1988 ACR also explained that, because of limitations in the 1987 Amendments to the NWPA, should the repository be delayed, an MRS could only accept 10,000 MTU. (Id. at 7.) Accordingly, by 1988, performance at an MRS was contingent on construction authorization for a repository (which never has occurred) and successful siting of an MRS (which also never occurred). Even under the best-case scenario, performance at any rate, at anyplace, would not commence by January 31,1998.
Plaintiffs were aware of, and complained about, DOE’s then five-year delay. On September 23, 1988, Hunt wrote: “[t]he DOE’s assertions in the ACR and [Draft Mission Plan Amendment] that it will not accept any SNF until 2003 is contrary to the disposal contract and the expressed will of Congress.” (PX 64, 65.)
This departure from the [NWPA’s] requirements is completely unacceptable. [APC and GPC] do not agree with the DOE’s assertion that the owners and generators of spent nuclear fuel will continue to be responsible for the waste material after 1998. The DOE’s obligations under the disposal contract begin January 31, 1998 and the DOE is responsible for the SNF, or spent nuclear fuel, after that date. The DOE’s assertions in the ACR and the Draft Mission Plan that it will not accept any [SNF] until 2003 is contrary to the disposal contract and the expressed will of Congress.
(Tr. 531-32 (addressing the June 1988 ACR).) The letter also complained that the acceptance level was too low. DOE responded indicating those concerns were expressed by others. (Tr. 523.)
DOE published a “Report to Congress on Reassessment of the Civilian Radioactive Waste Management Program” in November of 1989. (PX 67.) While DOE had already announced a delay in commencement of repository operations until 2003, in the Report, DOE stated that unless the conditions or linkages in the 1987 Amendments to the NWPA were lifted, SNF acceptance at an MRS would not, and could not, commence in
At this point, DOE conceded that commencement of performance could not start until 2010 absent Congressional action. While the 1988 ACR initiated performance in 2003 (the then predicted start-up date for the repository—a date that fell back another seven years to 2010 in DOE’s 1989 Reassessment Report to Congress), despite these pri- or admissions, DOE projected commencement of performance in the 1990 ACR in 1998 with initial acceptance at an MRS at upper and lower bounding rates.
Defendant’s response to plaintiffs’ claimed damages relies on rates DOE projected in the December 1991 ACR. (DX 97, PX 8.) These are the rates that define the non-breach world according to defendant, and damages for any higher level of performance than this—what DOE was agreeing to or projecting at that time—would either not be caused by DOE’s delay, or be a windfall. This position is discussed in further detail hereinafter. At this point, it is appropriate to note this document, in the context of DOE’s prior and subsequent statements.
DOE’s performance starting in 1998 with an MRS under the 1991 ACR, was conditioned and constrained by legislation enacted subsequent to the signing of the Standard Contracts, including a 10,000 MTU capacity and delay in construction of an MRS until repository construction was authorized. DOE’s pre-1987 amendment performance plans in the previous ACR, the March 1987 proposal to Congress, and the 1987 Mission Plan, were not conditional and had higher rates of acceptance. (PX 517, 39, 40.) For example, the 1987 ACR contemplated acceptance at an MRS starting in 1998, accepting 1200 MTU annually for the first five years when the repository would come on board, reaching an annual combined acceptance rate of 3000 MTU within five years. (PX 4; PX 40.)
The 1991 ACR, like the earlier planning documents, was estimated, but unlike earlier projections, was contingent on legislative changes.
2.0 WASTE ACCEPTANCE PROJECTIONS
The waste acceptance projections used in this ACR are representative of a FWMS configuration authorized by the NWPA, which includes a[n][MRS] facility. Article II of the Standard Contract specifies that “[t]he services to be provided by DOE under this contract shall begin, after the commencement of facility operations, not later than January 31, 1998.... ” DOE recognized that, under current conditions, waste acceptance at a DOE facility can begin in 1998 only if the Federal Government is able to consummate a timely agreement, which is enacted into Federal law, with a host State or Indian Tribe for the siting of an MRS facility. The Office of Nuclear Waste Negotiator, the head of which is a representative of the Federal Government appointed by the President, is actively seeking a State or Indian Tribe willing to host an MRS facility or a geologic repository.
The acceptance rates in Table 2.1 do not reflect the MRS facility schedule linkages with the repository development that were imposed by the NWPA, but are consistent with the 10,000 MTU storage capacity limit contained in the NWPA for an MRS facility before a repository starts operation. These acceptance rates assume commencement of facility operations in 1998. If the*418 current linkages between MRS facility construction and repository construction authorization are maintained, it is estimated that commencement of facility operations and initial acceptance of SNF by DOE could not start until at least 2007.
(PX 8 at HQR-001-2365 (emphasis added).) Thus, absent Congressional action, given the delay in repository operations until 2010, the aggregate acceptance rate for the years 1998 through 2007 would be zero. David Zabran-sky, DOE’s contracting officer, admitted the rates in the 1991 ACR assumed there was an approved MRS and that the statutory linkages were removed, neither of which ever occurred. (Tr. 1990 (Zabransky).)
Mr. Zabransky also testified that DOE’s position was that utilities, but not DOE, would be bound by either the ACRs or the DCSs, a position with which he disagreed.
A. (quoting from the 1991 ACR) As specified in the [SJtandard [Contract, the ACR’s [sic] for planning purposes only. It is thus not contractually binding on either DOE or the purchaser.
Q. So DOE didn’t think the 1991 was— ACR was contractually binding, right?
A. Well, again, as I’ve explained, DOE didn’t think the DCSs were, they thought they were conditional commitments. The ACR in itself is a planning document. It’s when it was used by the contracting officer as the basis for the DCSs that it started the contractual process.
Q. Okay. And that was—you skipped to my next question. DOE didn’t consider the DCSs binding, is that your testimony?
A. I think DOE erroneously considered them to be deconditional [sic] commitments.
Q. Erroneously, in your judgment?
A. I always thought that was erroneous. I just work there.
(Tr. 1990-91.)
Under the Standard Contract and DCS instructions (PX 74), utilities could submit DCSs beginning January 1, 1992. A DCS had to be submitted at least 63 months (five years and three months) prior to an allocation. Putting aside the DOE’s equivocations prior to the 1991 ACR, it is not clear whether DOE’s conditional and contingent commitments in the 1991 ACR would have started the 63-month clock. In the absence of a firm commitment to take delivery within 63 months of a date certain, the DCS process is/was largely academic for plaintiffs. At the 1991 ACR rates, plaintiffs’ allocations never came within 63 months of pickup before DOE repudiated its obligation to unconditionally commence performance by January 31, 1998 and suspended the DCS process. Under the December 1991 APR, plaintiffs’ first allocation was for Hatch Unit 1—.749 MTU when cumulative total acceptance reached 2,383.22 MTU. (PX 9 at 1398; PX 13 at Table B.4 (annual allocations for ‘Year 4”—listing .8 MTU for Hatch 1).) At the 1991 ACR rates (400, 600 and then 900), cumulative total acceptance would reach 2800 MTU in 2001— the year in which Hatch Unit l’s initial allocation under defendant’s theory was slated for pickup. (PX 8 at 5.) The DCS instructions suggest a calendar year with 63 months measured from January of the pickup year. Sixty-three months prior to January, 2001 is September 30, 1995 which is when plaintiffs’ first DCS would have been due. Before that due date, DOE had already announced it would not begin SNF collection until 2010, 59 Fed.Reg. 27,007-27,008 (May 25, 1994), and stated in its 1995 Notice of Inquiry that it had no obligation to commence performance absent a repository, and had no authority to build an MRS. 60 Fed.Reg. 21,793, 21,794 (May 3, 1995) (announcing it “does not have an unconditional statutory or contractual obligation to accept [HLW and SNF] beginning January 31,1998 in the absence of a repository or interim storage facility constructed under the [NWPA]”).
Interim storage by DOE was contemplated by the Act in only two situations, neither of which currently applies. Under the Act, DOE had authority to offer a limited interim storage option. See 42 U.S.C. [§ ] 10156. However, that authority has, by its express terms, expired. Under the Act, DOE also has authority to provide for interim storage in an MRS. That authority also is inapplicable, however, because the Act ties construction of an MRS to the*419 schedule for development of a repository. See 42 U.S.C. [§§ ] 10165,10168.
60 Fed.Reg. 21,797. The March 1995 ACR had no specific years of acceptance; rather listed “Year 1,” “Year 2,” etc. (PX 13.) Eliminating specific years effectively precluded utilities from determining the due date of DCS forms, 63 months before that unknown. Thus, it was impossible for plaintiff to hold an approved DCS. (Tr. at 1826 (Kouts).) Also, the DCS instructions refer the utility to its allocations in the 1991 ACR “or subsequent ACRs, as appropriate.” (PX 74 at 1 (emphasis added).) As allocations for the other plants came later, the same “overcome-by-events” would have applied and defendant’s reliance on the 1991 ACRs unravels.
DOE will not resume the DCS process until it has a reasonably firm date for the beginning of repository operations. At that time utilities would comply with the required 63-month lead time for DCS submittals. (Tr. 2002-04 (Zabransky); id. at 1853-54 (Kouts).) Nevertheless, on September 30, 1996, SNC submitted DCS forms for a 2001 allocation for Plant Hatch. “The attached meets the notice obligations under the spent fuel disposal services contracts, but does not indicate [SNC’s] acceptance of the removal rates contained in the current ACR. [SNC] believes the ACR rates are too low and are therefore inadequate.” (PX 82; see also PX 83 dated October 21, 1996.) In reply, DOE informed that it was “not able at this time to approve your DCS submittal. Consequently, the Department hereby waives until further notice the contract requirement that you provide a revised schedule within 30 days.” (PX 86 (received March 13, 1997).) DCSs were not approved because the DOE suspended the DCS process. (Tr. 1966-68 (Zabran-sky).) Cf. Pacific Gas & Elec.,
While the Standard Contract does not limit acceptance to a repository (so performance at an MRS would not necessarily have been foreclosed), the conditional and contingent nature of the 1991 ACR did not comport with the DOE’s unconditional statutory and contractual obligations. Defendant’s position is that plaintiffs’ acceptance rights in the 1991 ACR define the nonbreach world and any mitigation damages cannot exceed what that nonbreach world would have been. However, even if plaintiffs consented to this level (which by their objections, they did not), DOE’s inability to implement the 1991 ACR rates would nullify their use as equivalent to an “accord,” to define nonbreach world performance.
(1) An accord is a contract under which an obligee promises to accept a stated performance in satisfaction of the obligors existing duty.
(2) Until performance of the accord, the original duty is suspended unless there is such a breach of the accord by the obligor as discharges the new duty of the obligee to accept the performance in satisfaction. If there is such a breach, the obligor may enforce either the original duty or any duty under the accord.
Restatement (Second) Contracts § 281. A valid accord and satisfaction requires: (1) proper subject matter; (2) competent parties; (3) a meeting of the minds; and (4) consideration. O’Connor v. United States,
The 1992 ACRs
By 1994, MRS siting efforts “effectively ceased.” (Tr. 1773 (Kouts); Tr. 1978-79 (Za-bransky).) By 1998, no MRS was included in DOE’s program planning; efforts to construct an MRS terminated. (Tr. 1833-35, 1839-40 (Kouts); PX 78 at 3,13-15.) Nevertheless, the projected nominal acceptance rates in DOE’s 1994 combined ACR/APR were the same as in the 1991 and 1992 ACRs. (PX 13 at 4 (dated March 1995).) Unlike prior ACRs, however, quantities were not tied to specific calendar years. Instead, the initial projected rate of 400 MTU was for ‘Tear 1,” 600 MTU for ‘Tear 2” and so on. “In the previous ACR, the projected nominal acceptance rate was based on the assumption of SNF acceptance beginning in 1998 at a[n][MRS] facility prior to repository operations. Due to the uncertainty associated with the date of commencement of operation of the waste management system, the annual nominal waste acceptance rates are presented by year(s) of operation of the system rather than by specific calendar year(s).” (PX 13 at 3-4; Tr. 1969-70 (Zabransky) (language added because of uncertainty regarding the first year of operations).) Once again, the 1994 ACR/APR cautioned that, “[a]s specified in the Standard Contract, the ACR is for planning purposes only and, thus, is not contractually binding on either DOE or the Purchasers.” (PX 13 at 1.) However, it also provided that “[tjhese capacity allocations, as listed in the ACR, form the basis for the Purchasers’ submittal of [DCSs].” ([Id.)
DOE’s most-recent (at the time of trial) ACR/APR issued in July 2004 has an acceptance rate of 3000 MTU within five years of the predicted 2010 repository opening, starting with 400 MTU, then 600 in 2011, 1200 MTU in 2012, 2000 MTU in 2013 and then 3000 MTU annually from 2014 to 2019. (PX 14 at 2.) Again, “[a]s specified in the Standard Contract, the ACR is for planning purposes only and, thus, is not contractually binding on either DOE or the Purchasers.” {Id. at 1.) In July of 2004, DOE, predicting that the Yucca Mountain repository would begin operation in 2010, resumed the DCS process. (PX 179.) Utilities were directed to use the 2004 ACR as the basis for their DCS submittals and encouraged to submit DCSs for all allocation years “to assist us in our planning efforts.” (PX 179 at 1.) However, new DCS submissions were required, replacing any previously approved.
To date, the DCS process of the Standard Contract has not been completed. Maine Yankee Atomic Power Co.,
Plaintiffs’ mitigation
Plant Hatch ISFSI
As previously noted, utilities needed empty space in their spent fuel pools to operate—to unload and load fuel, and for inspections and repair of the reactor. Up until the early 1990s, loss of room did not appear to be an issue. Company documents did, however, note when pools would lose one FCR. (DX 38, 39, 101, 104, 106, 312, 313, 324.) Loss of two FCRs was noted for Plant Hatch. (PX 789, 800; DX 208.) Plaintiffs monitored DOE’s planning and positions. Uncertainty ripened into reality. When it became apparent that DOE was not going to commence performance by January 31, 1998, plaintiffs had two options: (1) allow their spent fuel pools to completely fill which would force a shutdown and loss of the most cost-efficient and emission-free source of electricity, or (2) obtain additional storage.
There was concern in Plant Hatch’s 1994 fuel storage task force study about DOE delays and its position that it had no obligation to commence performance. A repository would not be available until 2010 and perhaps much later. Loss of two FCRs was projected for the Fall of 1998, with loss of a single FCR in 2001. Pool capacity would be exceeded in the Fall of 2003. (DX 154, 158.)
A Strategic Plan was prepared each year to advise owners of the overall status of the plants. (Tr. 152; PX 789 (Long).) Hatch’s 1997 Strategic Plan stated that because of DOE’s partial breach, additional SNF storage was needed. “The capacity of the spent fuel pools [will] be exceeded with discharges scheduled to occur in 2003. Because of [DOE’s] continuing delays or the lack of a feasible alternative offsite storage option, Hatch intends to add dry cask storage capacity by as early as 1999.” (PX 856 (Hatch Strategic Plan, May 1997) at 10.) Dry storage was classified as a “mandatory” and “major” project with capital expenditures of nearly 25 million dollars through 2002 expected. (Id.) “This mandatory project is needed to support normal operations in accordance with prudent utility prac-tice____ Future expenditure beyond 2002, could include additional dry cask storage capacity based on U.S. DOE actions.” (Id.)
[DOE] has contracted to dispose of Plant Hatch’s spent fuel in a permanent repository, which is not expected to be available before 2010. Following a lengthy period of increasing uncertainty regarding when DOE would begin spent fuel pickup, DOE formally announced in December 1996 that it would not commence spent fuel pickup in 1998, as originally committed. This announcement followed DOE’s decision not to further appeal the ruling by the U.S. Court of Appeals in July 1996 that DOE indeed had an obligation to commence spent fuel pickup in 1998. Industry efforts continue to compel DOE to commence spent fuel pickup starting as close to 1998*422 as feasible, including more industry dialogue and work groups, new legislation, and additional legal action. Southern Nuclear is also part of a joint utility corporation effort to develop a private spent fuel storage facility for operation as early as the year 2002.
(PX 789.)
Dry cask storage, as opposed to wet pool storage, is the containment and storage of SNF in giant casks on large concrete pads adjacent to the reactor buildings. Dry cask storage facilities, also known as independent spent fuel storage installations (“ISFSIs”), were constructed at Plants Hatch and Farley to store huge, highly-engineered storage casks containing shielded SNF. As detailed at trial, ISFSI construction is a massive project, requiring licensing and inspection by the NRC. Planning and decision-making preceded ground-breaking by years. Demonstratives, numerous photographs and witness testimony are credited in the court’s consideration of the magnitude of these endeavors and the time to plan, license, test, train and then commence and complete construction.
The ISFSI at Plant Hatch includes four pads, roughly adjacent to the plant site, each approximately 31 by 96 feet, made primarily of steel and specialty concrete. (Tr. 1195-96 (Bland); Tr. 2387 (Johnson).) Three ISFSI pads were built at Plant Parley; each pad can hold up to twelve casks in a two-by-six array. (Tr. 1318-19 (McCallum).) The Plant Farley ISFSI was constructed in 2004; cask loading costs began in 2005—beyond the December 31, 2004 current cost-incurred damage period. Plant Vogtle procured and installed additional racks for its wet pool from 1998 through 2000 which increased its storage capacity. (Tr. 167-68 (Long); Tr. 278-83 (Cocherell).) This additional wet storage capacity postponed the building of dry storage at this plant until 2015. (Tr. 1613-14 (Metcalfe).)
Because of long lead times, planning for Plant Hatch began in the late-1990s. (Tr. 1153-54 (Bland).) Mr. Bland, project manager for the Plant Hatch dry storage project beginning in August of 1997, testified about the decision-making process and implementation. The number of assemblies in the spent fuel pool was a given, as were additions to the pool from future core off-loads, although increased efficiencies in fuel-burnup in the reactor core extended the time between discharges. Bland also had a mandate that he “shall not allow single-core offload capability to disappear. We need that to ensure availability of these assets to make electricity.” (Tr. 1163 (Bland).) It was assumed that plant would remain operational at least until the end of its plant life—2013 when its NRC license expired. A license extension would, however, add an additional twenty years of operation and attendant production of SNF. Based on feedback from those dealing with DOE, he assumed storage needs would exist throughout that time. His analysis would have changed with confidence that DOE
Q. Would it have changed your analysis about what kind of system you needed to design or develop if you had assumed DOE would appear at a fairly certain date and pick up a fairly certain quantity of fuel?
A. Oh, sure. The realities of an engineering job are that you start with a set of input parameters and those needed outcome and you create a solution that’s cast around them. If you change the desired outcome or change the input parameters, it can change your entire solution. Let me give you a specific example of that. Say today you were asking me to build a boat that I was going to personally live on. Now, if you tell me that I’m going to need to be on this boat for the next six hours, I’m going to create probably a raft, because I don’t have a lot of time and I’m not going to be on it that long. If you tell me I’m going to live on this boat for the next six years, if I could afford it, I’m going to build a very large yacht, because I have to live on it.
(Tr. 1165 (Bland).)
Mr. Bland discounted utilizing unused areas of the spent fuel pool where operational tools were stored. At best, this small area would only be a stop-gap measure. (Tr. 1159-60 (Bland).) Also, additional reracking, handling all the assemblies and placing them in denser arrays with the acquisition of more compact racks, was rejected because of risk to the plant and the public. (Tr. 1160 (Bland).)
Dry storage, the chosen option, was reasoned and reasonable, although it was a complex, time-consuming and expensive endeavor fraught with many unknowns. Constructing and implementing a dry storage system is not unlike licensing and building a new nuclear power plant.
The container or cask system in which the SNF assemblies are placed and stored is another major component of a dry storage system. There was also unpredictability in this relatively new and evolving technology. During the planning and initial acquisition period here, there were only six cask vendors. Two were shutdown by the NRC; one recently emerged from an NRC-issued shutdown for quality issues and one was in bankruptcy. Two of the then six existing reactors with ISFSIs had been shutdown for over a year due to problems with their selected cask vendors. Some nuclear utilities had failed in them attempts to implement dry storage systems. (Tr. 956-57 (Wade); Tr. 1164-67 (Bland).) Accordingly, planning included a two-year buffer for unexpected contingencies.
A cask vendor proposal request was issued in August of 1997 for Plant Hatch; offers were received in October 1997; Holtec International was selected to provide the dry-cask storage system and a contract was signed in January of 1998.
At this time Holtec was developing two types of casks—the HI-STAR and the HI-STORM. Defendant alleges that the selection of the HI-STAR at Plant Hatch was unreasonable and the costs attendant that system and its implementation should not be included in damages. The difference in cost of the HI-STAR versus the HI-STORM is considerable. HI-STAR casks cost approximately $1.15 million each. (Tr. 2294 (Johnson).) HI-STORMs cost about $620,000. (PX 414 at SNC002615; Tr. 2329-30 (Johnson).)
Mr. Bland testified the decision to initially purchase and load three HI-STAR casks was because the HI-STAR was further along in the NRC review process, principally because Dresden, a nuclear power plant in Illinois owned by Commonwealth Edison, had selected the HI-STAR for its decommissioning.
The court credits the testimony of Mr. Long and Mr. Bland concerning the selection of the HI-STAR:
To create a facility—again remember our end date, which was the summer of 2000, we needed to have loaded three systems to maintain single-core offload. To be able to achieve that requires a long line of successful activities. We’ve got to build these pieces of equipment that can take as much as a year to do. We’ve got to construct the facilities on which they’re doing it, which again can take as much as a year to do. We have to—before we can do either of those, we have to produce the designs under which we’ll do that work, which takes from six months—six to nine months to do. So in reality, for a load to occur in the summer of 2000, we’re back in mid '98, late '98, no later than early '99 making decisions about what we’re going to load or we’re not going to make it.
Q. All right, sir. And this is in early '98,
A. That’s correct.
Q. Okay. And do you recall in early '99 where HI-STAR was in that process.
A. In early '99, we had gotten the NRC to agree that it was safe. I don’t think we had yet the certificate done, not even sure we were very far through the rule-making process. It’s a little bit fuzzy, but we really got a lot of that stuff towards the end of '99, early 2000.
Q. And where was HI-STORM?
A. HI-STORM was lagging____ [W]hat the review for the HI-STORM was focusing on was the other two overpack components that are unique to the HI-STORM. But they still required review because they did provide safety functions and they still required evaluation. And even once that was complete, they had to go through this rule-making process as well because they were unique components with regard to that work too. And so to my memory, at least in the '99 time frame that—well frankly, that process is hard to predict, you know? Because as long as there’s one more question on a technical reviewer’s mind, even if there’s only one question, it could be three years before you get a final answer. So you can’t very well predict ruling making and evaluation process, you can only try your best to manage it.
(Tr. 1180-83 (Bland).)
Mr. Long also testified that the HI-STAR was selected initially because it would likely be licensed first:
Q. [A]t the time you had to make a decision about what kind of overpack you were going to use, where was the HI-STORM compared to the HI-STAR in terms of regulatory approval.
A. [The HI-STORM] was behind [the HI-STAR], Because all—the HI-STORM didn’t get licensed until like 2000, at the time we loaded our cask for the HI-STAR. So it’s licensing was behind____We would have been—well, we picked the system that was going through the licensing process first, that was due to get out first, so it could be licensed on our site where we could use it. And we were in a rush for time. So that’s why we chose to do what we did.
(Tr. 180 (Long); see also DX 217.)
That the HI-STAR was further in the NRC licensing process was a reasonable factor in the mitigating decisions for Plant Hatch. NRC licensing is time-consuming and the outcome can be uncertain. There is a technical review by NRC staff for health and safety concerns. A safety evaluation report is produced which can take three to six months. There is an opportunity for public input—a Part 72 rule-making process, after which a certificate of compliance may be issued.
An additional factor in selecting the HI-STAR was its transportability. (Tr. 185 (Long).) The HI-STAR cask is dual-purpose, licensed for both transportation and storage. A HI-STORM cask is licensed only for storage. (Tr. 173-74 (Long); Tr. 907
HI-STARs each weigh about 125 tons and are about 7}£ feet in diameter. They arrive on-site by specialized railcar in a horizontal position and are “upended” to vertical. The tremendous weight and size of the casks required modifications to the plant and construction of a rail spur. Suitable cranes and other equipment, including an upender pad, were needed. This required additional design and engineering work. (Tr. 891 (Wade).) Three HI-STARs were purchased and loaded at Plant Hatch.
To load a HI-STAR, assemblies filled with SNF are taken from racks in the pool and loaded into a metal canister in the pool that is then welded shut, dried and filled with helium. A HI-STAR cask is lowered into the SNF pool for loading of the filled canisters. (Tr. 1202-03 (Wade).) The HI-STAR is transferred out of the fuel building in a horizontal position and then upended on an upender pad at the ISFSI. (Tr. 1237 (Bland).)
The HI-STORM was licensed in June 2000. (Tr. 180, 184 (Long).) HI-STORMs each weigh 175 tons and have roughly a 10-foot diameter footprint. (PX 414 at SNC002615; Tr. 2329-30 (Johnson).) Anticipating its eventual licensing, the ISFSI was designed to accommodate the heavier HI-STORM.
Prior to December 31, 2004, nineteen HI-STORMs were purchased and loaded at Plant Hatch. The first four HI-STORM casks were loaded in June 2001, prior to the September 2001 discharge from Unit 2. (Tr. 983 (Wade).) Unlike the HI-STAR, the HI-STORM is not lowered into the pool. A HI-TRAC transfer cask is lowered into the pool and the loaded canister is inserted. The HI-TRAC is removed from the pool and the canister is welded shut, dried and filled with helium. The HI-TRAC transfer cask is then placed on the top of the HI-STORM cask; the bottom of the HITRAC is opened and the canister is lowered into the cask. The HI-STORM is then transferred to and placed on the ISFSI. In connection with the loading of the HI-STORM casks, significant costs associated with equipment, plant modifications, and NRC dry runs and inspections were incurred. (Tr. 1118-19 (Wade).)
Defendant argues plaintiff should not have ordered and loaded the three HI-STARs but should have waited and used the less-expensive HI-STORMs. Based on defendant’s economist Dr. Neuberger’s simulations and conclusion that Plant Hatch could have waited longer before it selected the initial three HI-STAR casks, defendant’s accountant Mr. Johnson, calculated the costs attributable to the HI-STAR that would not have been incurred if only HI-STORM had been selected. Neither Dr. Neuberger nor Mr. Johnson have any particular nuclear experience and did not opine on the reasonableness of these expenditures. Rather, Mr. Johnson parsed costs associated with the HI-STAR that, in his opinion, would not have been incurred with the HI-STORM. HI-STAR specific costs include: (i) cask procurement costs ($3,458,904) (Tr. 2294-95 (Johnson)); (ii) Southern Company HI-STAR-specific engineering work ($50,362) (Tr. 2277-78 (Johnson)); (iii) Williams labor related to HI-STAR ($135,696) (Tr. 1010 (Bland)); (Tr. 992-93 (Wade)); (iv) construction of HI-STAR upender pad ($803,404) (Tr. 1235-36 (Bland)); (v) gantry crane rails for upender pad ($105,697) (Tr. 1094 (Wade); see also DX 308); (vi) Holtec NRC demonstration costs
When initial decisions to acquire the HI-STARs were made, Plant Hatch had enough room in the pool to maintain one FCR through the next scheduled refueling outage and discharge in 2001. Engineering and licensing work for the Plant Hatch ISFSI began in 1998; construction was complete in mid-2000. (Tr. 159 (Long).) Three HI-STARs were purchased in late 1998 and loaded with 204 SNF assemblies and placed on the ISFSI through the summer of 2000. (PX 657 at KRG00697, 701.) By December 31, 2004, a total of twenty-two casks had been purchased, loaded with a total of 1496 assemblies, and installed on the ISFSI pad. (Tr. 1508-10 (Metcalfe).) Because Plant Hatch did not lose one FCR until September of 2001, and because the less expensive HI-STORMs became available in June of 2000,
Defendant’s hindsight does not negate plaintiffs’ reasonable mitigating decisions.
It is a bedrock principle of mitigation of damages, however, that even where the plaintiff bears the burden of mitigation, such Monday-morning quarterbacking is irrelevant to an award of mitigation costs. See, e.g., E. Allan Farnsworth, Contracts § 12.12 (3d ed. 1999) (“[A] party that takes steps that seemed reasonable at the time will not be judged by hindsight.”) As the Third Circuit explained in In re Kellett Aircraft Corp.:
Whether or not the buyer’s obligation to mitigate damages has been discharged depends on the reasonableness of its conduct. In this connection, reasonable conduct is to be determined from all the facts and circumstances of each case, and must be judged in the light of one viewing the situation at the time the problem was presented. Where a choice has been required between two reasonable courses, the person whose wrong forced the choice can not complain that one rather than the other was chosen.
186 F.2d 197 , 198 (3d Cir.1950) (footnotes omitted).
Citizens Fed. Bank v. United States,
Mr. Bland presented the foregoing analysis of options leading to the initial selection of the HI-STAR to the NRC. (PX 238.) That defendant does not point to any objection by NRC speaks to the reasonableness of these decisions and their implementation. Crediting the testimony of the decision-makers, the court concludes that the decisions to build dry storage, and implementation with HI-STARs and then HI-STORMs, was reasonable. While defendant asserts the three HI-STARs, or a number of the subsequently-acquired and loaded HI-STORMs, and their accompanying charges, were either not caused by DOE’s partial breach, or an award of these costs would be a windfall, defendant does not disagree that these costs were incurred.
Dry cask storage was new and complex. Long lead-times were planned to accommodate ISFSI engineering, licensing and construction as well as the design, implementation and execution of SNF-loading—a host of unknowns. Application had been made to license and install a bathtub rack which would have increased storage capacity in the wet pool by 167 spaces. However, at the time the initial decision to acquire the three HI-STARs was made, that process was not completed. NRC license approval for those additional racks was finalized in March of 2000. By adding 167 additional spaces with the approval and then installation of the bathtub rack, Plant Hatch then anticipated loss of a FCR with the next-scheduled refueling discharge in early 2001. This rerack postponed the loss of full core reserve from Fall of 2000 to the end of the Fall 2001 “an important achievement.” (PX 363.) A second bathtub rack, which was approved, was not used, in part to preserve operational flexibility. (Tr. 157 (Long).) Also, by this time, cask loading had begun. (Tr. 160 (Long); 1180 (Bland).)
The court concludes that the decision to build the ISFSI at Plant Hatch was caused in substantial part by DOE’s delay, and that but for the partial breach—in the nonbreach world, plaintiff would not have built it. In this regard, the court credits Mr. Long’s testimony that the dry storage decisions would not have been made if DOE’s commencement of performance had not been delayed. If DOE had timely commenced performance, a second bathtub rack would have been installed to accommodate discharges for the relatively short time until DOE’s accepted SNF from this plant. The cost of the second bathtub rack was deducted from damages. Rather than build expensive dry storage, any loss of FCR would have been tolerated because DOE’s continuing performance in the nonbreach world would have restored FCR in a relatively short time. The court credits Mr. Long’s testimony:
This whole business of ISFSI and having to store these casks out in rods, or out in the yard is not part of our core business. It is something we’re being made to have to do because [DOE] did not come and pick up our fuel and we would not be in*428 that business but for that. And if there was a choice where I didn’t have to build an ISFSI and I had to put in, you know, a second set of racks for a while, in the unit 1 pool, I probably would have selected to do that rather than go out and build this thing out there.
(Tr. 160-61(Long).) Upon consideration of the testimony and evidence, the court concludes defendant did not establish the decision to acquire the three HI-STARs was unreasonable. The decisions at Plant Hatch in this regard were foreseeable, substantially caused by DOE’s partial breaches, were reasonable, and the costs were established with reasonable certainty.
Cask loading schedule at Plant Hatch
Once its ISFSI was constructed, Plant Hatch made an operational decision to load more than simply enough to reach one FCR—at a schedule approaching two FCR. Defendant argues this level of loading was an independent business decision, and as in Indiana Michigan, not caused by DOE’s partial breach. Defendant asserts that only nine casks were necessary or caused by the breach at the acceptance rate DOE argues it would have performed. Defendant also calls Plant Hatch’s positions inconsistent or disingenuous, by arguing loss of one FCR as the “floor” for ISFSI causation purposes, yet ordering and loading casks at a more aggressive schedule.
Witnesses testified about operational loading decisions. First, because both units at Plant Hatch have the same reactor model, an NRC directive or other requirement to inspect both reactors at the same time, would require the offloading of both reactor cores simultaneously, utilizing two FCRs. (Tr. 955 (Wade).) The economic cost of any such simultaneous shutdown would be significant. (Tr. 145-49 (Long).) At the time of trial however, Plant Hatch was operating at less than two FCR, evidence defendant uses as support for its position the loading schedule was excessive and not caused by DOE’s partial breach. Southern contends that its actual loading of twenty-two casks (holding a total of 1496 assemblies) was reasonable (and not unreasonable) in light of its long-term goal of dual-reactor off-load capability. (Tr. 309 (Cocherell), 1531, 1508-10 (Metcalf); PX 657 at KRG00697, 101.) Mr. Long testified that there is a difference between operating at one FCR reserve in the short-term, versus planning for a higher reserve in the long-run, particularly as plants age.
Q. Well, if it is so important to have dual core off-load capability, why haven’t you recovered it already [at Plant Hatch]?
A. Because it is a risk management kind of decision that you make. Not all decisions are black and white. There is a probability of having to off-load one core at a time. There is a less probability to have to off-load two simultaneously.
But as our plants grow older, get older, I think that the probability increases, and, therefore, we made a short-term judgment that we can live with something happening and us being able to kind of manage through that problem by doing this, and this, but we would really like to have dual core off-load capacity. So we’re working as a matter of policy to try and, for our system, to have the capability.
(Tr. 148^9 (Long).)
Another asserted reason for working toward a FCR per reactor is to guard against contingencies in the cask loading process that could impact operational reliability, such as late arrival or defect in casks or canisters, unavailability of internal or contract labor, malfunctioning of cranes, helium evaporators or other equipment or NRC stop-work orders. The NRC stopped cask loading for over a year at another plant. (Tr. 1163 (Bland).) Also, Southern’s managers balanced the cost of paying earlier, rather than later, for casks and loading. (Tr. 147 (Long); Tr. 956-57 (Wade).)
During each refueling outage, Plant Hatch loads approximately three and one-half casks. Therefore, if Plant Hatch maintained an operating reserve of only one FCR total for its shared pool, an unexpected delay in a single
Defendant did not present any witness from the nuclear industry to testify what a reasonable cask loading schedule would be or would have been. Defendant points to a 1992 document indicating that the need for a two core reserve, one for each reactor, was not credible. Mr. Long testified that “as time goes on, the industry is finding things that are unexpected. There is a possibility that some issue might be found that a TVA Browns Ferry reactor, that Nuclear Regulatory could say, hey, look, this thing could be a generic problem facing all BWRs [boiling water reactors] of that vintage, like our Plant Hatch, you all need to go fix this thing.” (Tr. 146 (Long).)
Q. [I] f you don’t have that [two FCR] now, what would you have to do if you needed to shut down both reactors at the same time and remove the cores?
A. What I would have to do is off-load one core, fix the problem on that unit, and reload that core and then go the next unit, off-load that core and fix that unit. And then, you know, that’s just time and money, just takes additional time to do that.
(Tr. 149 (Long).)
Mr. Wade, the Southern engineer who managed the loading at Hatch, testified: [A] single core off-load would take about three years to use up during normal refueling operations. About that amount of time is what we estimate to qualify and select and test a cask from a new vendor. So the second full core off-load, not only does it give us the capability to off-load both reactors at the same time, it also gives us some margin for some contingency in case Holtee goes out of business or if they are required—or if they can’t supply casks to use any longer.
[To change cask vendors], you would have to redo the entire operational evaluation. You would have to do a licensing evaluation, go through planning. You would have to go through evaluation of the building of the structure. You would have to do [an] evaluation of the concrete pads at the ISFSI itself. Particularly [if] the ISFSI is designed for a single cask vendor’s casks. So all of those evaluations would have to be redone as a prerequisite to being able to load a cask from another vendor.
(Tr. 956-57 (Wade).) These concerns are not unreasonable. Several nuclear utilities have had to change cask vendors. (Tr. 956 (Wade); Tr. 1166-67 (Bland).)
The trial court opinion in Indiana Michigan,
Regardless, the court concludes that with DOE’s admitted commencement of performance delayed until 2017 (and perhaps 2018), there is no question the casks that were loaded would have to be acquired and loaded in any event; accordingly, there is no windfall. Loading was caused by DOE’s delays and the costs were incurred. Indiana Michigan limits damages to costs incurred. If recovery is not obtained now, there may be statute of limitations issues if the incurred costs were claimed later. The Federal Circuit foresaw this possibility and counseled: “subsequent claims for future damages are considered to accrue for the purposes of the statute of limitations at the time such damages are incurred. Accordingly, Indiana Michigan must bring any future actions for damages related to DOE’s breach of the Standard Contract within six years of incurring such damages.”
Even at the 900 MTU annual rate defendant advocates, the amount of SNF at issue would have been loaded to the ISFSI at some time prior to commencement of DOE’s now-projected performance in 2017-2018. Plant Hatch loaded 22 casks containing 1496 assemblies. (Tr. 309 (Cocherell); Tr. 2122, 2152 (Neuberger).) Plant Hatch’s allocations reach 1496 with the 181 assemblies allocated to Hatch when DOE’s cumulative total acceptance reaches 12,050.50 MTU. (PX 9 at 1412.) Assuming for ease in calculation, a steady 900 MTU rate, it would (or will) be approximately 13.4 years after commencement of performance before that total tonnage is accumulated. DOE’s projected start date of 2017 is a 19-year delay; 2018 is a 20-year delay. There is no possible windfall. This is more evident when it is recognized that the 1991 ACR rate was impossible to implement and cannot be used to define DOE’s performance had there been no partial breach.
Plant Farley ISFSI
Like the Strategic Plan for Plant Hatch, the May 1997 Strategic Plan for Plant Farley reported:
Based on projected Plant Farley spent fuel discharges to current onsite storage, the last cycle at which full-core offload capability is maintained begins in 2004 for Unit 1 and 2008 for Unit 2. The capacity of the spent fuel pools would be exceeded with discharges scheduled to occur in 2010 for Unit 1 and 2013 for Unit 2. If necessary, because of the [DOE’s] continuing delays or the lack of a feasible alternative offsite storage option, additional onsite storage could be obtained, most likely using transportable dry cask storage technology. Planning for additional onsite spent fuel storage capacity at Plant Farley is expected to begin as early as 1997, with the intent to place additional spent fuel storage capacity in operation by as early as 2004.
The DOE has contracted to dispose of Plant Farley’s spent fuel in a permanent repository, which is not expected to be available before 2010. Following a lengthy period of increasing uncertainty as to when the DOE would begin spent fuel pickup, the DOE formally announced in December 1996 that it would not commence spent fuel pickup in 1998, as originally committed. This announcement followed the DOE’s decision not to further appeal the ruling by the U.S. Court of Appeals in July 1996 that DOE indeed had an obligation to commence spent fuel pickup in 1998. Industry*431 efforts continue to compel the DOE to commence spent fuel pickup starting as close to 1998 as feasible, including more industry dialogue and work groups, new legislation, and additional legal action. SNC is also part of a joint utility corporation effort to develop a private spent fuel storage facility for operation as early as the year 2002.
(PX 865 at 15.) Substantially the same statements are” in a draft dated April 23, 1997, reflecting edits made on March 27, 1997. (PX 795.)
Tom MeCallum, Project Manager, was assigned to the Farley dry storage project in the summer of 2001. (Tr. 1269 (MeCallum).) At that point, the decision had been made to construct dry storage and bids had been received from three cask vendors. In January of 2002, Farley selected Holtec’s HI-STORM. (Tr. 1270-71 (MeCallum).)
Plant Farley has two reactors, each with a separate dedicated pool. (Tr. 134 (Long).) Unit 1 pool holds 1358 assemblies; Unit 2 holds 1386 assemblies. (PX 594 (Neuberger expert report, Ex. 3-Model Assumptions-Ae-tual Scenario).) Each reactor core holds 157 assemblies. (Id.) Unlike at Plant Hatch where only the fuel to be replaced is removed, at each refueling, the entire Plant Farley reactor core is removed and placed in the pool. (Tr. 1365-71 (MeCallum)
Tom MeCallum testified that Farley’s ISFSI was completed in 2004 and the first cask was loaded in 2005. The only costs claimed at this time are the costs of ISFSI construction and of the three casks purchased as of December 31, 2004. (Tr. 165 (Long).) The same type of engineering design, licensing, procurement, fabrication, construction, testing and implementation activities were undertaken at Plant Farley as at Plant Hatch. (Tr. 1195-96 (Bland); Tr. 1297-1325 (MeCallum).) The three ISFSI pads are constructed out of highly-engineered steel and concrete, are approximately two feet thick and can hold up to twelve casks each. (Tr. 1312-19 (MeCallum).)
Damages sought for Plant Farley total $21,355,367. At or prior to trial, plaintiffs removed-several claimed costs. Mr. Johnson, defendant’s economic, expert asserted further adjustments/deductions of $7,723,886 including $4,045,589 in what defendant claims is “prejudgment interest” (referred to by plaintiffs as cost of capital); $2,822,224 for investment in Private Fuel Storage and $821,103 • for internal labor, all discussed hereinafter.
Plant Vogtle reracking
Plant Vogtle, the newest plant, has the least amount of SNF. Its spent fuel pool capacity was increased with the installation of an additional rack purchased and installed for several million dollars.
Vogtle’s Strategic Plan Update dated April 23, 1997, reported DOE’s announcement not to commence SNF pickup in January of 1998
Plaintiffs’ storage mitigation decisions and expenditures were reasonable
The court concludes plaintiffs’ reracking and ISFSI decisions were reasonable mitigation given the utilities’ rational belief that DOE was not going to commence performance in January of 1998, or at any reasonably foreseeable time thereafter. Indeed, the Federal Circuit in Indiana Michigan held that at least by 1995, nuclear utility/contraet holders had an obligation to mitigate.
In addition to proving that their mitigation decisions were foreseeable and caused by DOE’s partial breach and establishing their costs with reasonable certainty, defendant also asserts plaintiffs have a concomitant burden to prove that those costs would not have been incurred if DOE had performed—that the expenditures would not have been made in the nonbreach world. Absent such proof, plaintiffs would enjoy a windfall, defendant posits. Defendant acknowledges delays resulted in at least some mitigating efforts, but only to the extent of storage needed for the quantity of SNF that would have been picked-up under the 1991 ACR. Defendant asserts causation is limited by the level of performance DOE was espousing in the 1991 ACR-400, 600, 900 MTU. “Plaintiffs’ Burden Includes Their Obligation To Establish A Reasonable ‘But For’ World Against Which To Measure Whether DOE’s Delay ‘Caused’ Them to Incur Incremental Costs.” (Def.’s Br. 95.) Defendant reasons that because of the limitations on the total amount of SNF that could be accepted at an MRS prior to the commencement of repository operations, DOE planned to accept SNF at the rates set forth in the 1991 ACR. Accordingly, only appropriate expenses to load the amount of SNF DOE would have picked-up under the 1991 ACR were caused by the breach. (Def.’s Br. 41, 154-57.)
In many respects, the parties here quarrel over hypotheticals—about what would have happened if there had been no breach. Although “effort is made to put the injured party in as good a position as that in which he would have been put by full performance of the contract,” that effort must be “at the least cost to the defendant and without charging him with harms that he had no sufficient reason to foresee when he made the contract.” Northern Helex Co. v. United States,
The parties present alternative views on whether this nonbreach or “but-for” world is an appropriate inquiry and even if it is, they differ on what that world would have looked like, and how, or if, it applies in this case. Much effort is expended in urging the court to adopt a rate at which DOE would have performed starting in 1998. Defendant insists the conditional 1991 ACR is the yardstick that limits mitigation, and because plaintiffs have removed more SNF from their wet pools than DOE would have at that rate, awarding mitigation costs at the higher level would place plaintiffs in a better position than if there had been no partial breach. However, even at those rates, defendant’s economic expert admitted that over sixteen million dollars of plaintiffs’ dry storage costs would have been incurred. (Tr. 2348 (Johnson); Def.’s Br. 6 (at the 1991 rate, plaintiffs’ damages are no more than $16,707,845).) Plaintiffs insist that in the nonbreach world, DOE would have been performing at a 3000 MTU annual rate after a short rampup, and at that rate, would have removed more SNF from their pools than plaintiffs have; accordingly, plaintiffs are not in a better position than if DOE had commenced performance and there is no windfall.
Defendant conflates mitigation and causation, a position the Federal Circuit rejected in similar circumstances in First Heights Bank v. United States,
The clear import of the government characterizing its argument as one of causation is to avoid the reasonability element of the mitigation doctrine. We disagree, however, with the causation label that the government assigns to its argument. The sole allegation underlying the government’s argument is that plaintiffs failed to take actions that would have eliminated some of the damages from the breach. Such an allegation is covered by the mitigation doctrine and its reasonability element. We thus conclude that the government’s so-called causation argument is identical to the government’s mitigation argument and reject it.
To reiterate, generally, the remedy for breach of contract is “damages sufficient to place the injured party in as good a position as it would have been had the breaching party fully performed.” Indiana Michigan,
Once plaintiff has established, to a reasonable certainty, its expenditures were the foreseeable result of, and caused by, DOE’s partial breach, the burden shifts to defendant to prove that such damages “could have [been] avoided by reasonable efforts.” Pa-
In asserting plaintiffs’ burdens include establishing a “but-for world,” defendant cites Winstar cases concerning expectancy damages. (Def.’s Br. 97.) Seeking expeetancy/lost profits, the nonbreaching party attempts to prove what would have happened—how many widgets would have been sold, etc. and what profits would have been made. Glendale Fed. Bank v. United States,
Analogously, in awarding foreseeable costs incurred in reliance on a contract, the breaching party has the burden of establishing any loss that would have been incurred in the nonbreach or “but-for” world—if the contract had been performed. Damages for the nonbreaching party’s reliance on a contract are recoverable less “ ‘any loss that the party in breach can prove with reasonable certainty the injured party would have suffered had the contract been performed.’ ” American Capital Corp. v. Fed. Deposit Ins. Corp.,
In American Capital Corp., the Federal Circuit explained the shifting burden of proof, upholding an award equal to the cash infusion made in reliance on the government’s promises. Not unlike here, the government argued that TransCapital Financial Corporation (“TFC”) the nonbreaching party, had the burden of proving what its expenditures would have been had the government not breached. The Federal Circuit rejected that approach. If the nonbreaching party established foreseeable loss (and in American Capital, the government had reason to know the loss would occur and it did), the burden shifts to the breaching party to establish with reasonable certainty any costs would have been incurred in the absence of the breach.
Essentially, the injured party may not be able to prove with reasonable certainty what it would have made if the contract was performed; however, it may be able to prove what expenditures it made in relying on the contract. Here TFC demonstrated that its $42.2 million loss in reliance on the contract was foreseeable. At that point,*435 we shift the burden to the breaching party and allow it to prove what expenditures would have been lost despite the breach. If the government can show with reasonable certainty that TFC would have lost the $42.2 million regardless of its breach, then TFC could not recover.
These Winstar cases for the most part involve reliance damages. Granted, reliance and mitigation differ. Reliance damages are actual expenditures made in preparation or in performance; here mitigation damages are actual expenditures addressed to an admitted future partial breach. In both instances, however, the costs must be proven by the nonbreaching party. What would have happened had the breach not occurred, is in both instances based at least in part on conjecture and the burden in both should be born by the breaching party. In contrast, in seeking consequential damages for breach—such as lost profits—assuming the contract had been performed, the burden is on the nonbreaching party to establish its cost of performance in the nonbreach world, in order to determine net profits. Defendant’s position that the nonbreaching party has the burden of establishing what DOE would have done and would have performed in a process in which DOE, for the most part, controls that process, is further reason not to place the burden of establishing any offset for this world on the plaintiffs. The very breach for which plaintiffs seek recompense would deny plaintiffs the ability to meet the burden defendant advocates. To the extent that this inquiry is appropriate, DOE’s failures to establish a firm comparison doom its burden in this regard. “The government contends that TVA’s damages should be constrained to the difference between the costs of building the dry storage facilities in the present (breach) world versus the costs of building the facilities later in the but-for, non-breach world. Because the government seeks to limit the non-breaching party’s recovery for mitigation, the government bears the burden of proof.” Tennessee Valley Auth.,
The court also rejects defendant’s assertion that the Standard Contract is too indefinite to be enforced if the court does not accept the DCS process with the 1991 ACR. (Def.’s Br. 153,160.) Embedded in the Standard Contract is a process for honing the rate as the system was to be (and is) developing. The Contract is not too indefinite to be enforced. The mechanism is there. It is DOE’s delays and partial breaches that have thwarted or stunted the process. Even if the mechanism under the Standard Contract was left to future defining, an obligation to proceed in good faith is imposed. In North Star Steel Co. v. United States,
*436 This court has recognized that a provision which calls upon the parties to a contract to agree in the future on a specified point or contract term, often referred to as an ‘agreement to agree,’ imposes an obligation on the parties to negotiate in good faith. See Aviation Contractor Employees, Inc. v. United States,945 F.2d 1568 , 1572 (Fed. Cir.1991); see also Gardiner, Kamya & Assocs. v. United States[Jackson],369 F.3d 1318 , 1322 (Fed.Cir.2004); City of Tacoma v. United States,31 F.3d 1130 , 1132 (Fed.Cir.1994).
See also Chapman Law Firm Co. v. United States,
The contingent and conditional 1991 ACR was discussed previously and the court declines to find that DOE would have performed at that level. Indeed DOE could not have performed at that level without Congressional action. The court does not accept either defendant’s proffered 1991 ACR rate or the 3000 MTU rate advocated by plaintiffs. Prior SNF cases have found specific rates, others have not. Indiana Michigan Power Co. v. United States,
Perhaps any “would have been world” is more appropriately determined, not seven years before the time for performance was to begin, but at subsequently acknowledged levels, or as envisioned as of the date of the damages cut-off, or as of the date of judgment(s). The fundamental purpose of limiting mitigation damages is to prevent a windfall— that is, to not award costs that would have been incurred anyway. While the Standard Contract has not changed, conditions and the level of DOE’s performance have. If plaintiffs’ foreseeable mitigation measures and expenses were substantially caused by DOE’s admitted delays in commencing performance, which is and was a partial breach in and of itself, and those expenses would not have been incurred if DOE had commenced performance at the level it recently has proposed as its performance obligation (which is also the level contemplated at the time of the enactment of the NWPA and the contract formation), or at any reasonable level, there
La Salle Talman v. United States,
Adopting in part the reasoning of Commonwealth Edison Co. v. United States,
Both parties presented expert testimony which, in great detail, calculated reactor core discharges, spent fuel pool inventory and one or two full core reserves under various hypothetical, as support for their respective non-breach worlds. Plaintiffs’ expert Eileen Supko,
Four ramp-up and acceptance rates scenarios were used: Scenario 1 reached 3000 MTU by 2002 and remained at that rate; Scenario 2 (based on the 1991 ACR) reached 900 MTU by 2000 and remained at that rate; Scenario 3 (based on the 1992 ACR) reached 900 MTU by 2000 and increased to 3000 MTU by 2015; Scenario 4 reached 6000 MTU by 2001. (PX624.)
Using strictly OFF (Oldest Fuel First) and applying these four scenarios, Ms. Supko charted the following:
Comparison of Factors Important to Spent Fuel Acceptance
(Id. at 14.) Of these four rates, only Scenario 1, 3000 MTU, met the goals of generally preventing additional at-reactor storage after 1998 and reducing backlogs of SNF inventory to allow timely decommissioning. Additional dry storage of 1030 MTU (less than the cumulative amount of industry-wide SNF discharge in one year) was projected. On the other hand, under Scenarios 2 and 3, additional dry storage of 13,130 and 6200 MTU, respectively, was projected. Also, Scenario 1 would result in a relatively short average time for post-shutdown fuel storage—nine years vice sixty-four years under Scenario 2 and 16.5 under Scenario 3. Also, under Scenario 1, DOE’s waste management system would operate at maximum capacity for twenty-eight years (after a five-year start-up), which was fairly consistent with the planned forty-year period of acceptance operation. In contrast, under Scenario 2, the program would operate for over 100 years. In concluding Scenario 1 was the most efficient and best met her identified goals, based on the greater volume of SNF that would have to be stored on-site under Scenario 3, Ms. Supko rejected Scenario 3 rates even though there were fewer years of both post-shutdown storage and system operation. Ms. Supko’s sensitivity analysis, assuming intra-company swaps of acceptance allocations between plaintiffs’ plants, also concluded that Scenario 1, the 3000 MTU rate, minimized the need for additional on-site storage and reduced industry backlog to allow timely decommissioning.
Accordingly, as discussed previously, the trial court in Indiana Michigan concluded DOE would have performed at the 3000 MTU rate.
From her spent fuel management expertise, Ms. Supko also described alternatives utilities had for dealing with small quantities of SNF to avoid building expensive dry storage facilities for a small quantity of SNF, if DOE had performed and there was industry confidence in continued performance.
Having heard the testimony concerning time, effort and expense involved in building and maintaining dry storage, without contemplating the decommissioning efforts that will be required for the eventual shutdown, dismantling and decontamination of these football field-sized mega-pads filled with 100-plus-ton concrete containers of radioactive waste, the court concurs with the logic expressed in Tennessee Valley Authority v. United States, that “[g]iven the proportionately large cost of building and operating dry storage facilities, TVA would have had several options available in the but-for scenario to deal with its spent fuel while still avoiding dry storage.”
Regardless of whether the burden is on the plaintiffs to establish lack of windfall, or on the defendant to prove windfall, the court credits witness testimony that the reracking at Plant Vogtle and the dry storage at Plants Hatch and Farley would not have occurred if DOE had been performing at any reasonable rate.
In the main, analysis comes full circle. The court’s conclusion that there will not be a windfall is further support for the court’s findings on causation. At DOE’s projected commencement dates and levels of performance, at the time the mitigating decisions were made, at the time DOE was required to commence performance, at the time the expenses were incurred, and at the time of trial (as well as the date of this opinion), plaintiffs will not be better off by an award of mitigating expenses, than if DOE performed at any of these levels. “[Pjlaintiffs claim to have been forced to absorb unnecessary interim storage costs. If the government reimburses such costs, it hardly puts plaintiffs in a better position.” Dominion Resources, Inc. v. United States,
Plaintiffs’ claimed mitigation costs include employee and management time spent on these endeavors. This includes the dry cask storage and related projects at Plants Hatch and Farley, and the rerack at Plant Vogtle— efforts consequential from DOE’s partial breach. These internal labor costs total $6,466,016, and are supported by books and records. (Def.’s Br. 82 n. 4; Pis.’ Br. 117.) Any time spent on a mitigation-related project was so “booked” on plaintiffs’ records. These time-allocations were consistent with generally accepted accounting principles required by the Alabama and Georgia Public Service Commissions. (Tr. 1565-69 (Met-calfe).) Internal labor was used where feasible because these employees were more reliable, better trained and less expensive than outside contractors. (Tr. 168-72 (Long); Tr. 1125-28 (Wade) (describing use of internal labor at half the cost of outside contractors).) For the operations portion of the projects, plaintiffs used unionized, hourly-rate employees. (Tr. 169 (Long); Tr. 1020-21 (Wade).) Management personnel, generally salaried, also booked specific time to mitigating projects.
Construction of the dry cask storage facilities and the loading, welding, transportation and placement of the casks on the pad are extremely dangerous activities, planned months in advance. Use of internal employees simplified planning. Also, but for these projects, the employees would have been doing other work which is what they were hired and paid to do. “[I]f the people are off working on dry cask storage, they are not working on the backlog of maintenance activities that we—that they are normally charged to do” and “they would be working on maintenance backlogs that we have.” (Tr. 170 (Long).) Mr. Wade, agreed that there was “other plant maintenance work that could have been done” by these employees. (Tr. 1128 (Wade).) Mr. McCallum testified that the use of internal employees on SNF storage projects meant that “there’s work that gets deferred—gets sent outside of the company, or the backlog____” (Tr. 1287 (McCallum).) “The maintenance departments have backlogs of activities that they are working on to try and work down to get fixed so that the plant runs as it is supposed to.” (Tr. 170 (Long).) However, Mr. Wade did not identify any operational maintenance activity delayed because of effort diverted to dry storage. (Tr. 1138-39 (Wade).) Identified deferred projects included the design and construction of tornado barriers and security enhancements that were outsourced because in-house personnel were tasked to mitigating work. (Tr. 1389-91 (McCallum).)
Labor-intensive cask loading was scheduled around planned outages when labor needs for plant activities were reduced. About 150 employees at Plant Hatch were trained to assist in loading activities. More than half of those employees booked less than $5,000 annually to mitigation efforts.
Plaintiffs’ economic expert opined these internal labor charges were appropriate components of the actual costs of mitigating DOE’s partial breach. (Tr. 1565-69 (Met-calfe).) As a regulated, investor-owned public utility, there is a high level of cost consciousness. While safety is paramount, idle employee time is minimal. These projects were massive and labor intensive and the use of these employees was a true cost because they were not doing the work they were hired to do.
That these people are working on these, again, major projects, complex, and the fact that you use an internal person as opposed to a third party contractor doesn’t mean that the internal person is not incremental to the utility. They need those people to work on their normal projects and to dedicate them to the size and complexity of the projects that we’re talking about here, and it makes sense that those*441 people are incremental and should be reimbursed.
(Tr. 1553 (Metcalfe).) “[J]ust because a person is being used as internal labor doesn’t mean that their costs are not reflected or their replacement costs are not reflected somewhere in the company.” (Tr. 1554 (Metcalfe).) “[T]he utility is using that individual in a way that they were not intending to use that person____And, a fair and reasonable method of compensating for that is to use the person’s salary.” (Tr. 1554-55 (Metcalfe).) In regulated industries, “internal labor has to be recovered or the utility would never be made whole in the rate process ...,” and while the costs of the employee would already be included in the rate base, “they are not doing the work that the ratepayer expected them to do. Instead they are doing the work that the government has necessitated to be done.”
Defendant’s position is not that internal labor costs can never be recovered; rather, that the evidence here did not show any deferred work or incremental costs, and “a contractor is not entitled to recover ‘expenses which would properly have been incurred regardless of the [breach].’ ” (Def.’s Br. 162, citing Boyajian v. United States, 191 Ct.Cl. 233,
Our position is not that, as a matter of law, these costs are not recoverable. Rather, had the plaintiffs established that employees were retained based upon work being performed upon incremental projects, that overtime was paid in connection with those projects, such costs likely would be recoverable. However, instead of establishing that specific employees were incremental, the plaintiffs relied upon eonclusory and unsupported statements concerning the asserted incremental nature of their internal labor as a whole. Plaintiffs’ litigation strategy, however, failed to meet their burden of proof.
(Defi’s Br. 166.)
As mitigation efforts must be reasonable, the lesser cost of using internal labor (highly trained, trusted and available), vice more expensive contract labor, is compelling. “If ... [utilities are told] we are not going to reimburse you for the efficiency factor of using your internal labor, the message ... is utilities for the next cases are going to say ... I want to recover this money, I’m going to go out and get third-party contractors and the third-party contractors, again, are by default a more expensive resource.” (Tr. 1557 (Metcalfe).) Internal labor charges sought here were subject to rigorous proof.
The court finds that plaintiffs’ accounting for and booking costs in this regard was reliable and accurate. Defendant agreed that plaintiffs’ claims (as adjusted) were adequately supported from a books and records perspective.
[T]he fact that TVA used its own internal resources to support its mitigation is not fatal to its claim for damages in mitigating a breach of contract. Rather, the test for recovery is a targeted one: whether use of the internal resources by TVA deprived it of the ability to employ those resources on other projects. That TVA would have paid its employees in all events is not material to this inquiry.
Tennessee Valley Auth.,
Use of internal labor is less expensive than hiring contractors which reduces costs to ratepayers and ultimately to the federal taxpayers who bear the burden of judgments entered by this court. As damages continue, not only in this case, but also in the some fifty cases pending in this court, to not allow recovery of appropriately established costs of internal labor (assuming causation and foreseeability is established) may lead to the use of contractors to perform future mitigation
Private Fuel Storage
Since 1993-94, plaintiffs’ parent corporation, Southern Nuclear, has contributed over $8 million to Private Fuel Storage, LLC (“PFS”), a consortium of private entities, to finance the development of an off-site SNF storage site proposed on the Goshute Indian Reservation in Utah. Tr. 186-87, 205-06 (Long); (Tr. 385 (Cocherell); PX 715 at J-178). The PFS project would be a private ISFSI. (Tr. 186 (Long).) SNF would be shipped from reactor sites to the PFS facility. (Id.) Similar to DOE’s ill-fated proposed MRS, the PFS facility would store SNF until a repository became operational. (Id. at 186-87.) Southern Nuclear is an equity member of PFS. (Tr. 384 (Cocherell).) Approximately $4.4 million was contributed after ISFSI loading at Plant Hatch began. (Tr. 385-86 (Cocherell); PX 715 at J-178). Southern Nuclear made a total of $8,466,674 in payments to PFS between 1995 and 2004, and seeks to include those amounts in mitigation damages. (PX 715 at KRG00230.)
Mr. Long testified that Southern Nuclear’s managers decided that a private, off-site ISFSI was reasonable given the uncertainties of whether storage restrictions or expensive taxes or other uncertainties would prohibit, restrict or delay on-site storage options at plaintiffs’ sites. (Tr. 205 (Long).) Private storage was an insurance policy in case any of a host of possible obstacles to dry storage rendered that option unusable. For example, during the mid-90s, the State of Minnesota limited the amount of SNF that a nuclear power plant could store on-site. There was concern that similar local political opposition to on-site storage could occur. Possible increased taxation, uncertainties over untested NRC licensing of dry storage and the acquisition of a host of new technologies needed to build and load an ISFSI, made contingency planning necessary. Plaintiffs assert these contributions were reasonable decisions, made prior to the completion of the ISFSIs at Plants Hatch and Farley, accomplishments that were not foregone conclusions. The decision to stop contributions came only after the completion and successful operation of those ISFSIs. After five years of operating its Hatch ISFSI and one year of operating its Farley ISFSI without any tax increases or restrictions by the Georgia or Alabama Public Service Commissions, no further contributions to PFS were made. (Tr. 205 (Long); DX 338.)
Defendant argues that PFS was not reasonable mitigation because (1) it would be more expensive than dry storage; (2) it faced many licensing and financing hurdles; (3) even if it were ever built, it would not solve plaintiffs’ storage dilemmas. Mr. Cocherell, who was Southern Nuclear’s representative on the PFS Board of Managers and was against participation in the venture, felt the project was speculative and had no real chance of solving plaintiffs’ storage needs, and may never be licensed. (Tr. 339, 388-98 (Cocherell).) He also testified to substantial hurdles to the project including potential opposition from the State of Utah and problems with financing the estimated $100 million in construction costs. (Tr. 393; DX 161 at SN014291, DX 162 at SN014248.)
That there were (and are) questions whether the PFS would ultimately be built does not make it unreasonable and outside the realm of possible mitigation. Guaranteed success is not a prerequisite to recovery of mitigation expenses. Plaintiffs are “ ‘not precluded from recovery ... to the extent that [it] has made reasonable but unsuccessful efforts to avoid loss.’ ” Indiana Michigan,
One of the purposes of the NWPA and the FWMS was to address dwindling on-site storage. That off-site private storage might be needed absent a federal solution was likely contemplated. Robert Morgan, DOE’s director of SNF storage, stated in the 1983 that “[d]uring the first year of operation of the repository in 1998, we should be receiving fuel at a rate so that no utility would have to add any further storage facilities either on site or at another location.” (PX
A possible PFS was contemplated and included in DOE’s contingency plans in its February 2002, draft Environmental Impact Statement (“EIS”) for Yucca Mountain:
• There are a number of possibilities that DOE could pursue____ One such centralized storage possibility, the proposed [PFS] Facility for commercial spent nuclear fuel in Utah, is currently in the Nuclear Regulatory Commission licensing process.
• There are a number of possibilities that the Nation could pursue____One such centralized storage possibility, the proposed [PFS] Facility....
• DOE recognizes interim storage at the [PFS] facility in Utah to be a reasonably foreseeable future action and has included this proposed action____
(Pls.’ Br. 102.) Southern Nuclear made payments to the PFS in 2002, 2003 and 2004 totaling $1,152,600 after DOE made these public statements. (PX 428 at SNOC007755, 7758, 7761, 7764; PX 715 at 3178.) The NRC approved a license for the PFS facility on September 9, 2005. (Tr. 339-40 (Cocherell).) Ironically, the PFS is further along in the approval process than the Yucca repository or the ill-fated MRS ever was.
In 1994, before Southern Nuclear made any contributions to the PFS, the Hatch Spent Fuel Task Force reported that “[a] private MRS could be implemented, but the date for commercial operation and pick-up is not certain.” (DX 158 at 19.) Included in that report was a legal opinion that there was no legal impediment to on-site storage. That report also noted that while there may have then been no legal impediment at that time, the State of Georgia had a moratorium on the disposal of radioactive waste, the Georgia Department of Natural Resources had previously questioned the adequacy of interim storage of radioactive waste and the Georgia Public Service Commission could question chosen technology if the issue became political. While more costly, a private MRS was noted as a back-up option. (DX 158.)
Private off-site storage would likely be more expensive than on-site. Financial analysis done by the Mescalero Apache Tribe and Northern States Power in March of 1994, estimated costs of private SNF storage at $96 per kilogram and ISFSI cost of between $62 and $83 per kilogram. (DX 143.)
Thereafter, in March 1996, after contributions began, Plant Hatch was predicted to lose FCR by 2000. At that time, the projected start-up date for PFS was 2002—two years too late for Plant Hatch. (DX 180; DX 182; Tr. 212-13 (Long).) Accordingly, additional on-site storage was the “only solution to Hatch’s storage problem.”
Plaintiffs respond that the State of Georgia could have prohibited on-site SNF storage or taxed it prohibitively. In either of those events, PFS would have been utilized. Also, use of PFS by 2002 could have avoided the dry storage expenditures at Plant Farley and Plant Vogtle, and a shutdown of any of those plants may have required the backup storage PFS could provide. In March of 1996, use of private fuel storage was not assumed, at least for decommissioning purposes, although impact of possible PFS on a permanent shutdown some decades hence would have been speculative. (Tr. 396-97 (Cocherell); DX 178.)
While plaintiffs knew as early as 1995 that PFS would probably not be licensed and constructed in time to alleviate Plant Hatch’s storage needs, there was uncertainty in all of the limited storage options plaintiffs had. However, contributions to PFS continued after ISFSI loading at Plant Hatch began, with a final $1.5 million contribution in 2004 after loading 22 casks to the ISFSI at Plant Hatch, after ISFSI construction at Plant Farley and the rack addition at Plant Vogtle. (Tr. 385-86 (Cocherell); PX 715 at J-178; DX 338.) Defendant also argues that, of the approximately $8.5 million contributed, about $4.4 million was after ISFSI loading at Plant
Plaintiffs argue that their nuclear plant management made reasonable decisions to contribute to PFS prior to the completion of ISFSIs and made the reasonable decision to stop contributing after the completion and successful operation of those ISFSIs. Accordingly, plaintiffs urge those contributions be included in recoverable mitigation expenses.
Defendant asserts recovery is foreclosed by Indiana Michigan’s conclusion that the investment in PFS was “too speculative” and not foreseeable.
The Federal Circuit limited its findings in Indiana Michigan to that factual record.
While upholding the trial court’s findings based on credited evidence that Indiana Michigan’s investment in PFS was speculative and its high cost unforeseeable, the Federal Circuit also addressed PFS from DOE’s perspective. “While DOE should have foreseen that its breach would force Indiana Michigan to find alternative storage for its SNF, it is not liable for such a speculative venture and unforeseeable costs.” The venture and costs are the same in this ease. The court in Pacific Gas and Electric, faced with this same issue, concluded that “[t]he preponderance of the credible evidence adduced at trial does not persuade the court to rule differently than the Federal Circuit under substantially similar circumstances.”
In addition, it is noted that payments and capital contributions were made by Southern Nuclear with costs allocated to APC and GPC. (PX 715 at SNOC01839-42.) An equity interest in PFS is apparently retained along with any subsequent profits or losses.
Accordingly, for the reasons stated, the investments in PFS are not included in mitigation damages awarded herein.
Cost of capital
The cost of capital claimed was presented by plaintiffs’ economic expert Kenneth Met-calfe.
Based on discussions with finance and rate-making departments at public utilities, Mr. Metcalfe used blended rates of debt, common and preferred equity which varied from year to year, and deducted expenses to determine after-tax weighted average costs of capital. (Tr. 1545^7.) He explained that the Federal Energy Regulatory Commission (“FERC”) recognizes equity and debt costs:
FERC rules allow public utilities to essentially book what’s called allowance for funds used during construction, and an allowance for funds used during construction is a weighted average cost of capital. It looks at their short-term debt, long-term-debt, preferred stock equity and it allows those to be recorded to the asset that’s being constructed to be recovered ultimately from the ratepayers.
(Tr. 1550.) Mr. Metcalfe testified as to his understanding of the difference between prejudgment interest and, what he opined was a separate, distinguishable component of damages in this case. “[Pjrejudgment interest ... is a simple application of interest to whatever costs are being incurred ... from the time of the claim until the time of the award____[Tjhe cost of capital is a separate component of Southern’s damages that I am putting forth in their claim.” (Tr. 1549 (Met-calfe).) His expert report, PX 651, p. 20, opines:
An additional element of past damages is the increased financing costs associated with the money spent by Southern to address the impacts of DOE’s failure to begin picking up spent fuel from the nuclear industry in 1998. Southern has had to finance the costs it has incurred related to DOE’s failure to perform in accordance with its contractual obligations from the time those costs were incurred (as have the co-owners of Hatch and Vogtle). Appropriate after-tax weighted average cost of capital rates were used to calculate these increased financing costs. The applicable annual rates were applied to the total nominal damages incurred each year*447 from the middle of that year through August 31, 2005.
Disagreeing, defendant’s expert, Dr. Neu-berger testified that plaintiffs’ cost of capital was disguised interest.
Q. Now, if Plaintiff had actually incurred financing costs, would you—what would your opinion be concerning whether those financing costs could be claimed in damages?
A. I might have a slightly different opinion. And I guess to make that distinction, I would distinguish between interest on damages and interest as damages.
If Plaintiffs could show, for example, that it actually did pay interest to fund an ISFSI, for example, or if there was—if Plaintiff could show, for example, that it had to issue a new bond or take out a bank loan and could document that it actually incurred higher interest costs, then what I would expect to see on this chart would be another line, so we have on-site storage, we have alternative storage facilities and we have financing costs and presumably some documentary support for the actual costs incurred.
In the absence of such evidence, however, computing the present value of damages is interest on damages, and in all material respects, that’s prejudgment interest.
(Tr. 2087-88 (Neuberger).)
Plaintiffs do not point to any actual costs they incurred; rather they assert that “Southern’s claim for the cost of capital incurred represents an actual expense incurred during the construction and operation of additional storage facilities as a result of the Government’s partial breach.” (Pis.’ Br. 164 (emphasis supplied).) Plaintiffs argue that compensation is appropriate because these large amounts of capital were not available for other purposes. “While Southern did not borrow money specifically to finance the dry storage projects, Mr. Metcalfe testified that the cost of funds committed to the SNF storage expenses is a real economic cost to Southern ... [and] accounts for the impact of inflation on dollars and the cost of money in the credit and equity markets.” (Pis.’ Br. 104-05 (citing Tr. 1542-51 (Met-calfe)).)
Prejudgment interest on contract claims against the United States is precluded by 28 U.S.C. § 2516(a).
[T]he force of the no-interest rule cannot be avoided simply by devising a new name for an old institution: “[T]he character or nature of ‘interest’ cannot be changed by calling it ‘damages,’ doss,’ ‘earned increment,’ ‘just compensation,’ ‘discount,’ ‘offset,’ or ‘penalty,’ or any other term, because it is still interest and the no-interest rule applies to it.” United States Court of Federal Claims only under a contract or Act of Congress expressly providing for payment thereof.
*447 (a) interest on a claim against the United States shall be allowed in a judgment of the
To recover debt costs such as interest, “changed work either must be directly traced to a specific loan or a necessity for increased borrowing must be shown to have been required by extra work or delay caused by the government.” Gevyn Constr. Corp. v. United States,
Plaintiffs’ expert Mr. Metcalfe testified generally about capital having a theoretical cost, an assertion not in serious dispute. He acknowledged that his calculations of “cost of capital” was the time value of money to attempt to make plaintiffs whole, in order to account for inflation and the time value of money. (Tr. 1542-43.) He also noted that cost of capital is a factor in rate-making; utilities have to pay interest on unpaid amounts under the Standard Contract; so reciprocity is not unfair; and without some consideration of the time value of money, the utilities would not be made whole. (Id.) Plaintiffs make conclusory statements that capital was used and capital is not costless, but must be adjusted by inflation, etc. to account for the time value of money—a million dollars spent in 2001 is not the same as a million dollars awarded in a judgment in 2007, which will not be paid until it is final. However, plaintiffs do not point to any consideration by Mr. Metcalfe of either a specific or general debt from which any allocation to plaintiffs was made. It is not clear that any money was borrowed. Similarly, while cost of funds may be de rigueur in regulatory or other proceedings, something more is re
In Tennessee Valley Authority there was discussion concerning the utility practice for rate-making purposes of adding to the amount of capital used on construction projects, a cost of and for those funds—-Allowance for Funds Used During Construction (“AFUDC”).
The parent company, Southern Company, provides capital to plaintiffs and it is the rates applicable to Southern Company that were calculated. (Tr. 1685-86 (Metcalfe); Def.’s Br. 92.) As evidence that Southern Company “incurred” costs of capital, then passed cost through to APC and GPC under Operating Agreements, plaintiffs rely on Metcalfe’s testimony and his underlying workpapers. (Pis.’ Reply Br. 60.) In their Reply Brief, plaintiffs cite to Mr. Metcalfe’s testimony and demonstratives. (Tr. 1547-48, 1584-86; PX 668 SNOC01645-46.
Hurdle rates are the minimum return on investment needed to attract capital investment. How these hurdle rates translate into actual debt cost attributable to capital used for these projects was not sufficiently established for the court to make a determination that a concrete, identifiable cost, as opposed to a time-value, inflation-related adjustment, was incurred.
A hurdle rate is typically a rate used for— an interest rate used for internal computations to determine if an investment project is potentially profitable____ You have a certain amount of outlays, cash outlays today, and you’re going to get a stream of revenue sometime in the future. Companies often want to determine whether that’s a—that stream of revenues is going to be a profitable enterprise is that the*450 present value of that stream of future revenues, greater than today’s cost, and the interest rate that they often use to do that analysis is what’s called a hurdle rate. So when you compute present value or, more specifically, net present value, what you do is you take the present value of all of those future streams of income and you subtract from that the cost of the project and that gets you a net number. If that number is zero or greater at the hurdle rate, then the company will approve the project. If you can’t achieve that rate of return on the project, then oftentimes, it’s not funded. So that’s my understanding of a hurdle rate.
(Tr. 2082-83 (Neuberger).) See also Dock-ery v. C.I.R.,
Apparently, projected profit level required to attract investment income was calculated before a capital investment project was approved. A new power plant or other capital expenditure would have to have a projected income flow sufficient to generate return of investment at the hurdle rate. It does not appear that dry-storage is such a revenue producer. Plaintiffs’ reliance on hurdle rates is another reason to deny recovery.
Deductions for costs to load to DOE casks and for second bathtub rack
Defendant asserts an offset of the cost that would have been spent at Plant Hatch and Plant Farley to load SNF to DOE’s casks if DOE had performed. Defendant also seeks an offset of the cost of installing a second bathtub rack at Plant Hatch— which would have been done even if DOE had commenced performance at any level in order to preserve a minimum of one FOR. The court agrees with plaintiffs that when DOE does perform, cask loading costs will be incurred then. If deducted now, and incurred later, plaintiff would bear the cost twice. Moreover, what those discrete loading costs might have been in a hypothetical, nonbreach world is speculative. The court adopts the reasoning and conclusion on this issue in Tennessee Valley Authority.
[T]he government claims that in the non-breach, but-for world, TVA would have had to incur costs in loading casks with SNF for delivery to DOE. As a result of DOE’s breach, the government claims that TVA has temporarily avoided these costs, that TVA has received a benefit as a result, and that the government should be credited with an offset to TVA’s damages to reflect this benefit.
The alleged benefit stems purely from timing; both DOE and TVA contemplate that DOE will still perform under the contract at some future date. As matters now stand, any benefit inhering in TVA because of delayed loading costs would be entirely speculative. It is not possible to ascertain the method DOE will ultimately use for SNF acceptance. The size and type of casks to be used to transport the SNF are not known; no casks have been approved for the purpose. The mode of transport has not been determined. Additionally, the date at which DOE will begin to perform in the future cannot even be estimated, let alone determined with reasonable certainty.
Tennessee Valley Auth.,
The court concludes that the costs of installing the second bathtub rack at Plant Hatch that would have been incurred if DOE had performed should be offset from mitigation damages. The claimed offset for DOE cask loading is rejected and mitigation damages are awarded accordingly.
Other offsets to damages
Defendant’s expert, Mr. Johnson, proposed numerous adjustments, parsed primarily into categories of costs incurred but attributable to the HI-STARs and associated expenses, loading beyond one FOR at Plant Hatch, cost of capital, internal labor and PFS. (Tr. 2212 (Johnson).) In rejecting costs incurred that were deemed not reasonable, Mr. Johnson did so not based on any technical knowledge of the operation of a nuclear power plant, but relied upon testimony of others. He monetized and categorized evidence and testimony of others. (Tr. 2214 (Johnson).) Due to continuing cooperation of counsel in providing evidentiary support for the voluminous invoices and other documents listing the costs incurred, the amount of costs Mr. Johnson originally considered not adequately supported was reduced considerably. Also, plaintiffs unilaterally removed certain other costs from those claimed. Adjustments continued during trial proceedings. Except for the two following items, remaining proposed monetized adjustments were resolved.
Stand-by welding time
Defendant proposes deduction of costs paid by plaintiffs to welders who were on stand-by on-site. Briefly, to weld the casks shut, contract welders were used for the first loading campaigns at Plant Hatch. Charges were incurred for “standby time,” while they waited to weld the next cask, a standard industry practice. Mr. Wade testified:
Q. I want to ask you a question or two about welding. I believe Mr. Ekman had asked you a few questions about downtime for welders. Do you know if that’s industry practice for companies to pay downtime for welding?
A. That is my normal understanding. I mean, you know, we went to Welding Services to hire welders that were prequali-fied, precertified to make these welds. And my understanding is that they get normally a 40-hour week and we reserve those welders for that. Best of my understanding is it is not an uncommon practice to do that throughout the industry.
(Tr. 1129-30 (Wade).) Welders were specially trained to weld dry storage casks and worked on a plant site miles from other possible job sites. It was reasonable to pay for their on-site down time and defendant did not establish these charges were unreasonable.
Work platform for cask loading
Mr. Johnson also questioned the $48,284 cost of a 228-foot platform used at Plant Hatch to support workers while they welded or bolted the top of the HI-STORM cask before transport to the ISFSI pad, asserting that amount should not be included in damages. (Tr. 2363-64 (Johnson).) Mr. Wade testified that DOE would have supplied this equipment under the contract and the cost was appropriate cover or mitigation:
Q. But you would agree Southern Nuclear would need the 228 foot platform to load to a DOE cask, is that right?
A. I don’t—well, we would have assumed that the DOE would have provided access to the top of their casks, but since we have it, you [DOE] can use it.
(Tr. 1063-64 (Wade Test).) Mr. Wade’s assumption is supported by the language in the Standard Contract that DOE will supply equipment necessary to load the cask:
(a) Written procedures for cask handling and loading, including specifications on Purchaser-furnished cannisters for containment of failed fuel;
(b) Training for Purchaser’s personnel in cask handling and loading, as may be necessary;
(c) Technical information, special tools, equipment, lifting trunnions, spare parts and consumables needed to use and perform incidental maintenance on the casks(s); and
(d) Sufficient documentation on the equipment supplied by DOE.
Standard Contract, Art. IV.B.2.
There is no dispute that the platform was required to load—incident to mitigation otherwise recoverable under the court’s findings herein. This cost was incurred. To the extent at the time DOE does perform, if this platform is not needed or not used, any appropriate adjustments can be made at that time.
Is Southern Nuclear a proper party?
Defendant renews its request that SNC should be dismissed for lack of contractual privity because it is not a party to the Standard Contracts. (Def.’s Br. 92-93.) SNC was incorporated on December 17, 1990 for the express purpose of acting as operating agent and licensee of APC and GPC. (Pis.’ Resp. to Def.’s Motion to Dismiss, filed January 24, 2002, at 3.) “Because APC and GPC bear the costs claimed as damages in this action, damages should be awarded to APC and GPC only.” (Pis.’ Reply Br. 1 n. 1.) “[SNC] has not asserted any right to recovery in its own right; rather, [SNC’s] claims are asserted solely in its role as operating agent and attorney-in-fact for APC and GPC.” (Pis.’ Resp. to Def.’s Motion to Dismiss, Jan. 24, 2002 at 2.) And, “[SNC’s] elimination as a plaintiff would neither divest this [c]ourt of jurisdiction over APC and GPC’s claims nor affect the merits of the plaintiffs’ Complaint or the quantum of damages recoverable by APC and GPC in any way.” (Id. at 4 n. 3.) Plaintiffs assert SNC is a proper party because Operating Agreements with APC and GPC designate SNC as their “attorney-in-fact and agent” and SNC has administered the contracts with DOE. (PX 806, 807.). Plaintiffs contend that Southern Nuclear should remain in the litigation as attorney-in-fact and agent for APC and GPC, and indeed, trial evidence included documents authored by Southern and testimony included reference to Southern, as the managing company. In the end, however, APC and GPC, both in contractual privity, incurred most of the costs sought herein and defendant does not assert to the contrary.
This court previously ruled that it “lacks jurisdiction to consider or resolve any issues between APC, GPC, and SNC concerning their operating agreements ...” and no such issues were presented. “Absent contractual privity between SNC and the United States, no judgment can be rendered in favor of SNC.” (Order, Apr. 7, 2004, Dkt. 234, 4.) Nevertheless, the court allowed SNC to continue to participate as a plaintiff in this case because its “voluntary participation in this litigation could facilitate discovery and trial proceedings.” (Id.) No purpose is seen in dismissing SNC at this stage of the proceedings.
Waiver
The D.C. Circuit Court of Appeals issued a writ of mandamus prohibiting DOE from asserting its delay in commencing performance of the Standard Contract was unavoidable. Northern States Power Co. v. DOE,
The so-called unavoidable delays clause, as well as the avoidable delays clause, are contained in Article IX of the Standard Contract entitled “Delays”:
A. Unavoidable Delays by Purchaser or DOE
Neither the Government nor the Purchaser shall be liable under this contract for damages caused by failure to perform its obligations hereunder, if such failure arises out of causes beyond the control and without the fault or negligence of the party fading to perform. In the event circumstances beyond the reasonable control of the Purchaser or DOE—such as acts of God, or of the public enemy, acts of Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes and unusually severe weather—cause delay in the scheduled delivery, acceptance or transport of SNF and/or HLW, the party experiencing the delay will notify the other party as soon as possible after such delay is ascertained and the parties will readjust their schedules, as appropriate, to accommodate such delay.
B. Avoidable Delays by Purchaser or DOE
In the event of any delay in the delivery, acceptance or transport of SNF and/or HLW to or by DOE caused by circumstances within the reasonable control of either the Purchaser or DOE or them respective contractors or suppliers, the charges and schedules specified by this contract will be equitably adjusted to re-fleet any estimated additional costs incurred by the party not responsible for or contributing to the delay.
Standard Contract, Art. IX.A.
After the trial in this matter, Nebraska Public Power District v. United States,
In view of defendant’s post-trial brief reference to its intention to assert an unavoidable delays defense, if not restricted by the D.C. Circuit’s mandamus, the undersigned, sua sponte ordered the parties, after the Nebraska decision, to address whether the validity of the D.C. Circuit’s writ of mandamus could be raised for consideration at this time in this case, or whether the issue has been waived. These matters were not previously addressed in the briefs.
Defendant’s position is that it did not, and could not have waived that defense. Plaintiffs counter that defendant could have asserted the D.C. Circuit lacked jurisdiction and/or could have preserved this possible defense with a statement similar to that made in other SNF cases pending in this court that but/for the writ of mandamus, the defense would be raised.
Litigation leading up to the D.C. Circuit’s prohibitory writ commenced in 1995. DOE formally announced, pursuant to Article IX of the Standard Contract (the Delays clause), it was “not obligated to provide a financial remedy for the delay [in commencement of performance] because the delay was ‘unavoidable.’ ”
DOE’s duty under [under the NWPA] to dispose of the SNF is conditioned on the payment of fees by the owner and is triggered, at the latest, by the arrival of January 31, 1998. Nowhere, however, does the statute indicate that the obligation established in subsection (B) is somehow tied to the commencement of repository operations referred to in subsection (A).
In conclusion, ... we hold that section 302(a)(5)(B) creates an obligation in DOE, reciprocal to the utilities’ obligation to pay, to start disposing of the SNF no later than January 31,1998.
Thereafter, several utilities and others filed petitions for a writ of mandamus in the D.C. Circuit to compel DOE to commence performance by January 31, 1998. While those petitions were pending, and according to defendant, in response to comments received from utilities regarding the delay, DOE announced that, pursuant to Article IX of the Standard Contract, DOE was “not obligated to provide a financial remedy for the delay,” because the delay was “unavoidable.” DOE’s contracting officer wrote that “regulatory delays; roadblocks to implementation of interim or monitored retrievable storage; funding restrictions, litigation delays” were “unavoidable delays” that would exempt DOE from liability for damages for failure to commence performance by January 31, 1998.
We hold that the Standard Contract between DOE and the utilities provides a potentially adequate remedy if DOE fails to fulfill its obligations by the deadline, and thus do not grant in full the writ requested by petitioners. We do agree, however, that DOE’s current approach toward contractual remedies is inconsistent with the NWPA and with our prior decision in Indiana Michigan. We thus grant the petition in part, and issue a writ of mandamus precluding DOE from advancing any construction of the Standard Contract that would excuse its delinquency on the ground that it has not yet established a permanent repository or an interim storage program.
This necessarily means, of course, that DOE not implement any interpretation of the Standard Contract that excuses its failure to perform on the grounds of “acts of Government in either its sovereign or contractual capacity.”
The D.C. Circuit reiterated its holding in Indiana Michigan that DOE’s obligation under the NWPA to commence performance by January 31, 1998 was conditioned only on payment of fees by the utilities. That conclusion did not change under the Standard Contract.
*455 Accordingly, we order DOE to proceed with contractual remedies in a manner consistent with NWPA’s command that it undertake an unconditional obligation to begin disposal of the SNF by January 31, 1998. More specifically, we preclude DOE from concluding that its delay is unavoidable on the ground that it has not yet prepared a permanent repository or that it has no authority to provide storage in the interim____We therefore issue a writ of mandamus precluding DOE from excusing its own delay on the grounds that it has not yet prepared a permanent repository or interim storage facility.
Northern States,
DOE filed a petition for rehearing, contending the D.C. Circuit lacked jurisdiction to construe the unavoidable delays clause of the Standard Contract which, DOE contended, was a matter for the Court of Federal Claims. The D.C. Circuit denied DOE’s motion for rehearing, stating it was not adjudicating a contract dispute, rather, it was enforcing a statutory duty—a function clearly within its jurisdiction.
[t]he DOE ... suggests] that this Court has erroneously designated itself as the proper forum for adjudication of disputes arising under the Standard Contract. As the above should make clear, we did not; we merely prohibited the DOE from implementing an interpretation that would place it in violation of its duty under the NWPA to assume an unconditional obligation to begin disposal by January 31, 1998. The statutory duty to include an unconditional obligation in the contract is independent of any rights under the contract. The Tucker Act does not prevent us from exercising jurisdiction over an action to enforce compliance with the NWPA.
Northern States Power Co. v. United States,
Defendant, in its December 6, 2006 post-trial supplemental briefing cites one trial exhibit, a June 3, 1997 letter from Beth Toma-soni, former DOE contracting officer for the Standard Contract, to utilities, informing of her preliminary determination that DOE s delay in commencing performance was excusable under the unavoidable delays clause because of technical and regulatory issues, roadblocks to implementation of an MRS, funding short-falls and litigation delays. (PX 88.) This exhibit, while setting forth her preliminary determination, recognized utilities disagreed and alleged any delay was avoidable. Recognizing delay would result in increased on-site storage costs, Ms. Tomaso-ni’s letter invited suggested amendments to the contract under Article XV, including compensation for storage costs. (PX 88 at 2.) This post-trial mention in an exhibit is not sufficient to preserve this possible defense— and if defendant wishes to rely on one part of that letter as binding, then the other part of the letter suggesting possible amendments could include compensation for on-site storage—the goal of plaintiffs’ complaint—is part of the package.
Defendant also cites testimony of Christopher Kouts, a senior official at OCRWM. While defendant does not specify the portion of Mr. Kouts testimony which assertedly raised and preserved these issues, presumably the reference is to the following colloquy concerning funding issues and staff reduction.
A. [Kouts] [W]e did not always receive what we had requested of Congress, and there were certain years that had substantial impact on the program---- [E]very year ... we get less than we typically ask for____[W]hat that caused to the program at that time was a substantial reduction in our contractor structure, and subsequently, we actually underwent, about a year or two after that, a reduction in federal staff.
Q. And have these funding shortfalls affected DOE’s ability to perform the standard contract is a timely manner?
Mr. Blanton: I’m sorry to interrupt. But we object. Liability has been found in this case. The Court’s [sic] issued an order. The DC Circuit has ordered the Justice Department not to raise excusable delay as a defense. I can’t think of any other reason this testimony would be relevant other than that, and we object to it.
*456 Ms. Sullivan: As we noted in our pretrial brief, Your Honor, we are seeking to preserve the record by having Mr. Kouts present this evidence.51 What arguments we may make in the future is still a matter to be decided, but while Mr. Kouts is here, we would ask he be allowed to testify about this so that the information is in the record.
Judge Merow: Well, I can see some possible relevance, not necessarily on the liability aspect of this, but just to complete the historical part of the matter, may not be directly related to the Southern case, but I think it gives a full picture of the program involved. And to that extent, I’ll overrule the objection. You can present the evidence, but of course, you can object to any findings—
Mr. Blanton: Thank you, sir.
Judge Merow:—that are proposed based on it in the nature of any limitation of liability or something like that that is attempted.
(Tr. 1794-96.)
Defendant did not raise the unavoidable delays clause of the Standard Contract and did not raise the question whether the D.C. Circuit had jurisdiction to issue the writ of mandamus prohibiting the government from asserting this provision in defense of its failure to meet the statutory and contractual obligation to commence performance by January 31, 1998. Questions of the validity or applicability of the D.C. Circuit’s mandamus in this court in this breach of contract suit could have been raised but were not. Defendant raised the absence of a repository as a defense in other SNF cases. Boston Edison Co. v. United States,
Recently, defendant asserted unavoidable delays as an affirmative defense:
To the extent that the defense is not barred by the United States Court of Appeals for the District of Columbia Circuit’s writ of mandamus in Northern States Power Co. v. United States Department of Energy,128 F.3d 754 (D.C.Cir.1997), plaintiffs’ damages would be affected by the “unavoidable delays” clause of the standard contract.
Def.’s Answer to Second Am. Compl. and Supplemental Compl., in System Fuels, Inc. v. United States, No. 03-2624 (Fed.Cl.), Dkt. 125, filed Jan. 30, 2007, p. 7, H 37.
The initial Complaint in the instant action was filed on July 29,1998; the First Amended Complaint was filed on October 8, 2002; the Amended and Supplemental Complaint was deemed filed on October 11, 2005. (Dkts. 1, 175, 308.) Defendant’s responses did not raise the unavoidable delays clause as an affirmative defense, nor contend that but for the mandamus order, the unavoidable delays clause would be raised. (Dkt. 239 (Answer to Am. Compl.), Dkt. 318 (Answer to Am. and Supplemental Compl.).) Defendant’s motion for partial summary judgment filed on November 28, 2001, Dkt. 100, did not raise this issue either, nor was it raised in a pretrial hearing on September 15, 2005. During trial in October 2005 and January 2006, there was brief reference to the writ of mandamus, but defendant did not reserve any right to assert that if the writ were lifted or found to be invalid, the unavoidable delays clause defense would have been presented. With the exception of certain deposition designations, evidence was closed on January 31, 2006. (Tr. 2416-18.) While defendant’s post-trial footnote states that if the writ were lifted or found to be ineffective, unavoidable delays arguments would be made in this case, defendant does not point to any part of the record in this case wherein it asserted that the D.C. Circuit’s writ was invalid. There was no request to hold the record open.
Defendant argues it did not, and could not, waive these matters and that the cases cited in this court’s request for supplemental briefing on the issue of waiver, B-E-C-K Constructors v. United States,
While challenges to this court’s subject matter jurisdiction may be raised at any time, even sua sponte by the court or initially on appeal, see Rutledge v. United States,
Plaintiffs would be seriously prejudiced if the record were reopened to litigate what is or was unavoidable or beyond the control and without the fault or negligence of the government. “It is always possible to imagine more evidence which could- have been offered, but at some point litigation must come to an end.” Hazelwood School Dist. v. United States,
In Maine Yankee Atomic Power Co. v. United States,
Both Maine Yankee and Northern States were decided on the same day, by the same panel. Both opinions were authored by Senior Circuit Judge Friedman. Maine Yankee affirmed the undersigned’s: (1) denial of the government’s motion to dismiss for failure to exhaust remedies under the contract’s disputes provision;
a more limited one dealing with specified kinds of delays, namely, those “in the delivery, acceptance or transport” of nuclear waste [such as] delays that routinely may arise during the performance of the contract. For them to arise, however, the parties must have begun performance of their obligations relating to disposal of the nuclear waste.
Yankee’s claim against the government is far broader than one for improper delays by the [DOE] in performing its contractual obligations. Yankee contends that the government breached a critical and central obligation of the contract—that it begin disposal of nuclear waste by January 1, 1998. Congress found this objective so important when it promulgated the Act that it took the unusual action of specifying that all the contracts must contain this explicit requirement. The breach involved all the utilities that had signed the contract—the entire nuclear electric industry. The language of the avoidable delays provision of the contract cannot properly be read to cover Yankee’s claim.
that the unavoidable delays provision deals with delays arising after performance of the contract has begun, and does not bar a suit seeking damages for the government’s failure to begin performance at all by the statutory and contractual deadline of January 31,1998.
Both the avoidable and unavoidable delays clauses mention adjustment of schedules. The unavoidable delays clause provision provides that “the parties will readjust their schedules, as appropriate, to accommodate such delay.” Standard Contract, Art. IX.A. The avoidable delays clause also provides for adjustment of schedules as well as adjustment of charges. “[T]he charges and schedules specified by this contract will be equitably adjusted to reflect any estimated additional costs incurred by the party not responsible for or contributing to the delay.” Standard Contract, Art. IX.B.
In our Maine Yankee opinion we pointed out that it was unclear whether the amount the company had paid for electricity generated before April 17, 1983 could be equitably adjusted at all under the unavoidable delays clause. The same problem does not arise with respect to the charges Northern States paid after that date, which presumably are subject to equitable adjustment. For the reasons set forth in our Maine Yankee opinion, however, that factual difference between the two cases does not warrant a different outcome in them.
CONCLUSION
Historically, for reasons of public health and safety, the federal government has long assumed responsibility for disposal of highly radioactive waste such as that involved in this litigation. As provided by the NWPA in 1983, the United States, represented by DOE, entered into contracts with plaintiffs under which DOE, in return for plaintiffs’ payment of fees calculated to cover DOE’s costs of developing and implementing the waste disposal system required by that contract, was to start accepting and removing plaintiffs’ SNF no later than January 31, 1998. The contracts have been breached by a series of delays that now continue into 2017 and perhaps 2018. As a result, plaintiffs have built dry storage and reracked, as detailed herein, mitigating efforts that would not have been necessary if DOE had commenced performance at any reasonable pickup rate. In these circumstances, it is concluded that plaintiffs are entitled to recover the following expenses incurred through December 31, 2004, in reasonably mitigating DOE’s acknowledged delays in initiating performance of the Standard Contract.
As the court in Pacific Gas and Electric observed:
The sole reason plaintiff is being awarded damages in this case is the government’s delay in providing storage facilities for spent fuel after having contracted to do so. The United States, with the vast resources*460 of the most powerful nation on Earth, has failed, after nearly a quarter century, to accomplish a task that plaintiff, with limited resources, has accomplished in less than a decade.
Accordingly, upon consideration of the evidence, testimony and argument in this regard, damages are awarded as follows:
(1) Final judgment shall be issued in favor of plaintiffs for the following total sums:
ALABAMA POWER COMPANY
Plant Farley
$14,821,000.00 ISFSI
Dry Casks 2,191,000.00
Loading to ISFSI 266,000.00
APC TOTAL $17,278,000.00
GEORGIA POWER COMPANY
Plant Hatch
ISFSI $25,871,000.00
Dry Casks $18,978,000.00
Loading to ISFSI $10,570,000.00
Bathtub Racks $ 3,186,000.00
Less cost to install ($ 419,800.00)
bathtub rack (offset for
nonbreach world)
Adjustments57 ($ 982,120.00)
Hatch Subtotal $57,203,080.00
Plant Vogtle
SpentFuel Rerack $ 2,716,000.00
Vogtle Subtotal $ 2,716,000.00
Hatch Subtotal $57,203,080.00
Vogtle Subtotal $ 2,716,000.00
GPC TOTAL $59,919,080.00
(2) In accord with Restatement (Second) of Judgments § 26(b)(1) and (e), plaintiffs may bring a subsequent action(s) for damages incurred after December 31, 2004. Indiana Michigan,
Notes
. Spent nuclear fuel “has been withdrawn from a nuclear reactor following irradiation, the constituent elements of which have not been separated by reprocessing.” 42 U.S.C. § 10101(23) (2005).
. Briefing was extensive. Plaintiffs’ Post-Trial Brief was 167 pages; defendant's was 186; plaintiffs’ Reply was 63 pages.
. GPC owns 50.1% of Plant Hatch and 45.7% of Plant Vogtle. Other owners of Plant Hatch are Oglethorpe Power Company (30%), Municipal Electric Authority of Georgia (17.7%) and the City of Dalton (2.2%). Plant Vogtle is also owned by Oglethorpe Power Corporation (30%), Municipal Electric Authority of Georgia (22.7%) and the City of Dalton (1.6%). (PX 6 (Kenrich Report) at 1.)
. APC has about 1.3 million customers consisting of businesses, families and government agencies; GPC serves around 2 million. (Tr. 26-27.)
. Mr. Long received a bachelor’s degree in physics from the Georgia Institute of Technology in 1966, a master’s degree in nuclear engineering from that institution in 1969 and an MBA from the University of Alabama in Birmingham in 1979. He attended Harvard Advanced Business Management School in 1995. During his senior year and into his first year of graduate school, he calculated fuel burn-up rates at the Savannah River Plant which produced plutonium for weapons. He was in the Army as a weapons analyst, assessing foreign tactical nuclear weapons, for a year and a half before serving in Vietnam. (Tr. 115-16.) After analyzing Soviet and Chinese nuclear weapons for the United States Army in the 1960s, in 1970, he started as a licensing engineer at Plant Hatch, Unit 2, responsible for obtaining the construction permit from the Nuclear Regulatory Commission (“NRC”). Since then, he has managed hundreds of engineers responsible for the operation and modification of Southern Company's three nuclear plants. In 1979, he became manager of procurement for both nuclear and fossil fuel plants for Southern Company Services, a corporate subsidiary. In 1981, he headed the Nuclear Safety and Licensing Group at Southern Company Services which had licensing and support responsibilities. Responsibility for nuclear fuel was added in 1985. In 1987, he was a member of a task force to consolidate operations at all three nuclear plants. In 1988, he was appointed Vice President of Technical Support of Southern Company Services, where he was responsible for in-service inspections, quality assurance, nuclear fuel and regulatory environmental services. In 1990, SNC was formed and he was appointed Vice President of Technical Support. In the conclusions reached herein, the court credits Mr. Long’s extensive experience in the nuclear industry.
. The NWF was established to cover DOE’s costs. The Fund is "composed of payments made by the generators and owners of such waste and spent fuel, that will ensure that the costs of carrying out activities relating to the disposal of such waste and spent fuel will be borne by the persons responsible for generating such waste and spent fuel.” 42 U.S.C. § 10131(b)(4). Utility breach of contract claims cannot be settled by offsets to future payment obligations. Alabama Power Co. v. DOE,
. Hughes launched the five satellites in question, from 1985 to 1994, thus “covering” NASA’s pre-deadline announcement. Hughes Commons Galaxy, Inc. v. United States,
. San Carlos Irrigation & Drainage was cited by the Federal Circuit in Indiana Michigan,
. Congress intended that under the contract, beginning no later than January of 1998, DOE would accept, transport and dispose of SNF and the utilities would pay for these services. H.R.Rep. No. 97-491, Pt. 1, at 59 (1982), U.S.Code Cong. & Admin.News 1982, pp. 3792, 3825 (DOE "is responsible for disposing of [HLW or SNF] ... in permanent disposal facilities, beginning not later than January 1998, in return for the payment of fees established by this section.”); Standard Contract, 10 C.F.R. pt. 961, pmbl. & Art. VII; Indiana Michigan Power Co. v. DOE,
. Bruce Hunt is the nuclear fuel manager for Southern Company, a position he has held since 1989. He has a bachelor’s of science degree in engineering physics from Cornell University and a master of science degree in nuclear engineering from the Georgia Institute of Technology. (Tr. 439-40.) He joined Southern Company Services (which later became Southern Company) in 1972. One of his responsibilities starting in 1979 was the development of the contract with DOE. He was aware of pre-contracting activities and, on behalf of GPC and APC, participated in early meetings with DOE. (Tr. 446.)
. The Standard Contract defines the signing utility as the “Purchaser.” 10 C.F.R. § 961.11 (Preamble).
. The final Standard Contract defined “DOE facility” as "a facility operated by or on behalf of DOE for the purpose of disposing of spent nuclear fuel and/or high-level radioactive waste, or
. If there was any doubt that the contract was with the United States, explanatory comments prefatory to the published final contract reported that twelve commentors requested the definition of DOE include successor agencies. That suggestion was declined in part because “the Purchaser is not contracting, as such, with DOE, but rather with 'the United States of America ... represented by the U.S. Department of Energy.' " 48 Fed.Reg. at 16,591, Supplementary Information, Art. I (alteration in original).
. Discharge date came from RW-859 data forms submitted to DOE periodically by the utilities. The longer SNF has been out of the reactor the cooler it is.
. If the aggregate requests for acceptance exceeded the annual capacity of the disposal facility, acceptance would generally be based on OFF. 1. Acceptance Priority Ranking.
Delivery commitment schedules for SNF and/or HLW may require the disposal or [sic] more material than the annual capacity of the DOE disposal facility (or facilities) can accommodate. The following acceptance priority ranking will be utilized:
(a) Except as may be provided for in paragraph (b) below and Article V.D. of this contract, acceptance priority shall be based upon the age of the SNF and/or HLW as calculated from the date of discharge of such material from the civilian nuclear power reactor. DOE will first accept from Purchaser the oldest SNF and/or HLW for disposal in the DOE facility, except as otherwise provided for in paragraphs B and D of Article V.
10 C.F.R. § 961.11, Art. VI.B.1(a).
. The “commitment” was that of the utilities, not DOE. From the history, the reason could relate to the potential value of recoverables in the waste. SNF is not truly “spent,” but can, through processes beyond the pale of this Opinion, be reprocessed. With transfer of title, DOE will be entitled to any proceeds of reprocessing.
. DOE established the Nuclear Waste Policy Act Project Office to begin implementation of its responsibilities under the NWPA and later formed "OCRWM.” 42 U.S.C. § 10224. (Lawrence Dep. 24-25, May 20, 2002 (PDD 18); PX 45.)
. Despite its "draft” moniker, the NWPA required "a draft mission plan” to be published in the Federal Register. See 42 U.S.C. § 10221(b).
. The Standard Contract requires the SNF to be cooled for five years before acceptance disposal by DOE. 10 C.F.R. § 961.11, App. E.B.3.
. The NWPA authorized the DOE to conduct siting activities for a second repository. Until a second repository was in operation, the first repository could accept only 70,000 MTU. Projections at that time were for a total of 130,000 MTU industry-wide. Accordingly, a second repository was contemplated. (PX 38 at 22.) On May 28, 1986, the Secretary of Energy postponed site-specific activities for a second repository. (PX 40 at 13.)
. Five years of operation divided by a 15,000 MTU capacity is 3000 MTU annually.
. When DOE issued the Standard Contract as a final rule, 48 Fed.Reg. 16590 (April 18, 1983), several modifications were made from the proposed rule, following industry input. The final Standard Contract eliminated any requirement for DOE to begin SNF “disposal” in a permanent repository by January 31, 1998. The final rule required DOE to begin SNF acceptance after "the commencement of facility operations, not later than January 31, 1998.” "Facility" was defined as either a permanent repository to be constructed pursuant to the NWPA or such other facility to which SNF might be shipped by DOE prior to shipment to a permanent repository. 10 C.F.R. § 961.11, Art. 1.10, Art. II; 48 Fed.Reg. 16590, 16591 (April 18, 1983). Defendant does not point to any provision of the NWPA or the Standard Contract that permits contingent performance.
. No 1989 ACR was issued because, at the request of the Secretary of Energy, an assessment of the program schedule to Congress concluded there was a "significant slip for the expected start of repository operations—from the year 2003 to approximately 2010.” (PX 70.) Until a revised schedule was developed, an ACR would not be useful for planning. (Id.)
. “Upper bounding” and "lower bounding” denoted generally maximum and minimum. (Tr. 1174 (Bland).)
. The 1992 ACR, Revision 1, dated May 1993 (PX 11 at 4), differs from the 1992 ACR dated March 1993 (PX 10 at 4), in that the former adds the word "nominal" to the description of the projected annual rates.
. That all DCSs solicited under the 1991 ACR were disregarded by DOE is another reason for rejecting defendant’s reliance thereon.
. This statement was also in the 1997 Strategic Plans of Plant Hatch and Plant Vogtle.
. Building an ISFSI required specialized soils engineering including earthquake-protected concrete pad design. Engineering work was handled primarily by Southern Company. The concrete was designed to assume a 175-ton loaded cask would fall; accordingly, the concrete had to be relatively "soft” to absorb such a load—a very difficult engineering task. Analysis of the reactor plant also included floor loading capacity to handle the tremendous weights involved, as well as the dangers associated with moving nuclear material. About 100 pieces of equipment were required, including vacuum pumps, gantry cranes, railcar pushers and lifting slings. The fabrication of many of these items was inspected by the NRC. Dry-run testing was done internally and then for the NRC, including demonstrations of loading, lifting and moving these 175-ton containers. Demonstrations of loading and moving required specialized weights to replicate the cask systems.
. A Holtec dry storage system was used by other nuclear utilities during this time. Pacific Gas & Elec.,
. Decommissioning is the process of permanently shutting-down a nuclear power plant.
. Southern's licensing efforts on the HI-STAR benefltted the HI-STORM, leading to its licensing in 2000. (Tr. 1178-80 (Bland).)
. To the extent that the HI-STARs may have a residual value, and/or whether further costs or offsets may be significant in this regard, await future events when such matters may become relevant.
. Thomas MeCallum is a Project Manager for Southern Nuclear and managed the construction of Plant Farley’s ISFSI. He has over 20 years of nuclear-related engineering and management experience and received his bachelor’s and master’s degrees in mechanical engineering from Mississippi State University. (Tr. 1258-71(McCallum).)
. Other relatively minor adjustments as detailed in defendant’s Brief were also made. (Def.’s Br. 86.)
. Eileen Supko is a Senior Consultant with Energy Resources International, Inc., consultants on nuclear fuel cycle matters, including spent fuel management. The court accepted Ms. Sup-ko as an expert in nuclear engineering, DOE’s waste management program, storage and disposal of SNF and modeling of SNF acceptance and allocation rates. (Tr. 878-81.)
. The court in Tennessee Valley Authority rejected the government’s challenge to the "viability of the 'plus or minus 20%’ provision” of the Standard Contract, citing testimony of David Zabran-sky, DOE’s contracting officer, that "expressed an understanding that the Standard Contract would require DOE to accommodate a request by a utility” under this provision.
. Tennessee Valley Authority also rejected as “unavailing” the government’s argument that an inter-utility exchange "market" was speculative.
. The record evidence demonstrates that a reasonable annual removal rate in most circumstances would fall between the 2000 MTU annual industry SNF discharge as the floor and the annual 3000 MTU design capacity of the planned repository as the ceiling.
. Tennessee Valley Authority rejected the government’s suggestion that an employee’s time be included in mitigation only if that employee spent more than fifty percent of his or her time on mitigating efforts.
. The court inquired as to whether recovery in this litigation would result in a rebate to ratepayers. In response, Mr. Metcalfe testified that in his experience, "the [state regulatory] commission works with the utilities to decide how that money will be distributed. Generally, the proposition is that a substantial if not ... total amount of the moneys will go back to the ratepayers in some fashion with adjusted rates going forward.” (Tr. 1563-64 (Metcalfe).)
. Larry Johnson, President and CEO of Veris Consulting in Reston, Virginia, graduated from the University of Maryland with a degree in accounting. He attended graduate school at George Washington University where he completed all the course work for a master’s in finance, but did not write a thesis, so does not have the designation. He is a certified public accountant. He spent 18 years as an accountant at Ernst and Ernst, one of the big eight accounting firms. He left that firm in 1986 to open up his own firm with another individual, that grew from those two founders to over 100 professionals. The firm focused primarily in accounting and auditing. In 2000, he formed Veris Consulting which concentrates on forensic-litigation matters in addition to providing outsourcing of audit and accounting and surveying services. Veris Consulting has approximately 100 professionals with offices in Virginia, New Jersey and Ohio. (Tr. 2178-84 (Johnson).) His experience includes damage analysis involving "but-for worlds” and analysis of damage models. He has been qualified as a expert witness in several courts, including this court in Winstar-related cases and other SNF cases. (Tr. 2184—88 (Johnson).) The court qualified Mr. Johnson as an expert witness in the areas of financial analysis, cost accounting, auditing and analysis of economic damages. (Tr. 2190, 2196.) Mr. Johnson admitted he had no experience in the operation of nuclear power plants. {Id.) He applied data from plaintiffs' claim. In reaching his expert opinions, he relied on conclusions of Dr. Neuber-ger as to the number of casks loaded and room in the spent fuel pool, although Dr. Neuberger also did not claim any nuclear operational experience. (Tr. 2193-95.)
. For internal, regulatory and other purposes, employees would record their time to certain projects or tasks.
. Q. Southern Nuclear is an investor in PFS right?
A. That’s correct.
Q. So if PFS were to earn a profit, Southern Nuclear would be entitled to a share of that?
A. I believe that’s correct.
(Tr. 211 (Long).)
. Mr. Blanton (plaintiffs’ counsel): But other than that [certain maintenance work orders for Plants Hatch and Farley], I think everything else in this—in the claim as expressed by the Ken-ric[h] group, the government has agreed is supported from a books and records standpoint. Is that right?
*446 Mr. Ekman (defendant’s counsel): That's correct.
(Tr. 6.)
. Kenneth Metcalfe is the President of The Ken-rich Group LLC, a business and litigation consulting firm. He is a Certified Public Accountant and a Certified Valuation Analyst and has computed accounting, financial, and economic damages in matters involving the construction and operation of over forty nuclear plants during the past twenty years. (Tr. 1406 (Metcalfe).) The court accepted Mr. Metcalfe as an expert in accounting, finance and economics related to damages and other related issues with respect to regulated utilities, nuclear power plants and government contracts. (Id. at 1446, 1449.)
. 28 U.S.C. § 2516(a) provides:
. Metcalfe’s demonstrative slide 69 referenced in his testimony is from these two pages of PX 668.
. Also, a cost of capital accelerator was added by plaintiffs' expert to all damages components, not just capital expenditures. While the cost of internal labor has been allowed as a reasonable mitigation expense, since no additional capital expense is involved in this cost, the addition of a capital accelerator to internal labor is not supportable in any event. If cost of capital were to be awarded, the amount associated with any claim item rejected, such as the investment in PFS, must also be deducted.
. DOE's Final Interpretation of Nuclear Waste Acceptance Issues, 60 Fed.Reg. 21,793, 21,797 stated that the lack of a operational repository on January 31, 1998 would exempt it from liability for breach of contract under the delays clauses.
. The unavoidable delays clause addresses liability for damages if the delay "arises out of causes beyond the control and without the fault or negligence of the party failing to perform.” The contracting party with the utilities is the government. See Yankee Atomic Co. v. United States,
. A footnote in the defendant’s Memorandum of Contentions of Fact and Law, states "as part of the Government's evidence at trial, we anticipate that Mr. Kouts and perhaps other witnesses will testify regarding the reasons for DOE's delay in beginning SNF acceptance and its excusabilily. The [c]ourt may find it necessary to resolve these issues at trial.” (Dkt. 309-2, 34 n. 7, filed Sept. 28, 2005.)
. “[T]he government has persisted in urging in this court that it has an obligation to accept and dispose of SNF and HLW only if an appropriate repository is available, notwithstanding the D.C. Circuit’s grant of a writ of mandamus in November 1997 precluding DOE from excusing its own delay on the grounds that it has not prepared a permanent repository or interim storage facility-”'
. That Response (signed by government trial counsel who was also trial counsel in the instant action) included a section, titled in part:
WE BELIEVE THAT THE D.C. CIRCUIT OVERSTEPPED ITS JURISDICTION IN RULING UPON THE SCOPE OF THE 'UNAVOIDABLE DELAYS' CLAUSE IN THE STANDARD CONTRACT
[T]he Government consistently has taken the position that the Court of Federal Claims has the exclusive jurisdiction to resolve issues concerning the construction and administration of the Standard Contract.... [T]he United States courts of appeals do not possess jurisdiction under section 119 of the NWPA to review performance-related matters arising under the Standard Contract. Yet, in Northern States, the United States Court of Appeals for the District of Columbia Circuit expressly asserted jurisdiction to interpret and rule upon the "unavoidable delays” clause contained in the Standard Contract and to determine whether the delay at issue in these cases is encompassed within that contract provision. The D.C. Circuit then purported to bar the [DOE] from asserting any interpretation of the "unavoidable delays” clause that would excuse its delay based upon that contract clause. Because the D.C. Circuit lacked jurisdiction to resolve that issue, the Government should not be barred from revisiting that issue in this Court. See Christopher Village, L.P. v. United States,360 F.3d 1319 , 1329-30 (Fed.Cir.2004), cert. denied,543 U.S. 1146 ,125 S.Ct. 1296 ,161 L.Ed.2d 106 (2005). It is for this very reason that this [c]ourt can, and should, notwithstanding the United States Court of Appeals for the District of Columbia Circuit's decision in Northern States Power, resolve the issue of whether DOE may properly invoke the "unavoidable delay” provision of the Standard Contract.
Nebraska Public Power Dist., Dkt. 168, 5-6.
. Defendant did not raise this defense in its recent Amended Answer in Wisconsin Electric Power Co. v. United. States, another pending SNF case. Def.'s Answer to Second Am. Compl. and Supplemental Compl., No. 00-697 (Fed.Cl.), Dkt. 248, June 25, 2007.
. Under the disputes provision of the Standard Contract: "any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer....” Standard Contract, Art. XVI. Appeals are to the DOE Board of Contract Appeals. Id.
. The unavoidable delays clause was addressed in briefing in Northern States. Br. for Def.Appel-lee, Northern States Power v. United States, No. 99-5096,
. Defendant proposed "Other Adjustments” of $1,080,404, to which plaintiffs responded in part. (Pis.' Br. 117.) With the exception of stand-by welding labor costs ($50,000) and the expenses of the work-platform for loading Hi-STORMs ($48,284), this adjustment is accepted.
