The controversy arises over the construction of section 13 of the contract as follows:
"It is understood and agreed by me (appellee) that you (appellant) will sell and dispose of all or part of said bonds on the faith of this contract, and if for any reason I fail or refuse to carry out the conditions and obligations hereof, I agree to pay you the sum of $15,000 as liquidated damages and not as a penalty for the breach of this contract, which payment shall be made at the office of the Southern Mortgage Company at Abilene, Texas; that this contract is entered into by the borrowers on the assumption that a second lien of $60,000 shall be sold to certain parties of Corsicana, Texas, and that in the event said second lien is not subscribed and a valid commitment executed, as anticipated, the borrower shall be liable for actual expense incurred only by you, in the appraisal, etc., in connection with this application. In case I desire to cancel this contract because of failure to place said second lien, then I shall notify you to such effect on or before March 1, 1924."
The court filed conclusions of fact and law in substance: That paragraph 13 of said contract contemplated that same should include all of the terms and conditions of the agreement between McGregor and the hotel committee of said Chamber of Commerce, both as to securing the subscriptions of the $60,000 loan and the issuance of the commitment therefor, and the purchase of the Kerr lot for a building site. That said hotel committee was to secure subscription for $60,000 from the citizens of Corsicana, payable to said committee, for which said committee would issue a valid commitment to appellee. That said committee secured such subscriptions, amounting to $60,000 but never transferred or delivered same or a commitment for the amount thereof to appellee. That the Kerr lot was the lot contemplated in the *861 contract sued on and also by the citizens of Corsicana, and that the owner would have sold the same to the hotel committee or any other persons for the sum of $12,500. That said committee did not refuse to enter into a valid commitment for a $60,000 second lien, and that the negotiations between said appellee and committee did not reach that point. That it was contemplated by the parties to this suit, and paragraph 13 above quoted in effect provides that, in the event said second lien referred to was not subscribed and a valid commitment executed, that the contract between appellant and appellee automatically became canceled, and that appellee would not in such event be liable for any liquidated damages, but would be liable for the actual expense incurred in paragraph 13. That on March 8, 1924, appellee, by letter of said date to appellant, canceled the agreement here sued on with reference to the loan, stating as a reason therefor that he had failed to meet the requirements of the owner of the lot in order to procure title thereto. That the contract sued on was extended by the parties, made on February 28, 1924, to March 10, 1924. By said letter appellee canceled the contract under the terms thereof. That appellant was familiar with all the negotiations between appellee and said hotel committee, and that the original contract depended upon the condition that before said contract would be effective appellee and the hotel committee would acquire title to the Kerr lot in Corsicana. The court then concluded as a matter of law that appellee was not liable for the liquidated damages sued for.
It will be observed that the court found that the contract between the parties here included the terms of the agreement between appellee and the Chamber of Commerce. Appellant's position is, that under the facts as found by the court, appellee was in default in not securing a commitment for the loan of $60,000, and that he could not cancel the contract for the failure which he could have forestalled; and, further, that he did not attempt to cancel for the reason allowed in the contract.
Appellee's answer is that the execution of the commitment is a condition precedent, and having failed, the contract became automatically canceled, that the right to arbitrarily cancel the contract was reserved, and other matters not necessary to state.
The quoted provision of the writing does create a condition precedent, but that does not mean a condition qualifying the existence of the contract, but refers to conditions preceding liability thereunder. Williston, Contracts, §§ 666, 666A.
The questions upon which the decision of the instant case turns are whether appellee was bound to perform his part in securing the commitment provided for, and whether he was in default in the respect wherein the commitment was not given. That he was bound to do his part is clear. The rule has been stated to be:
"If conditions are used in a contract by the party to do the act, they plainly import he binds himself to do it." Williston, Contracts, § 672; Mathews v. Caldwell (Tex.Com.App.)
Words stating a thing shall be done or a certain thing happen must be taken prima facie to be the language of the party who is to do the act or in whose knowledge or power the event is supposed to be. Williston, Contracts, p. 1296. It is concluded, therefore, that the right of arbitrary cancellation was not in appellee, but that his liability rests on the answer to the question as to whether the failure to procure the commitment required is to be laid at his door.
Appellant's claim is that the court's findings are to the effect that the failure was due to appellee's dereliction.
There is no direct conclusion of fact on the point, but those above stated, when read in the light of the testimony, involve the necessary inference that the Chamber of Commerce breached its agreement with appellee.
Appellee testified without contradiction in substance that the hotel committee agreed to deliver to him the Kerr lot for $10,000, which was to be paid out of the $60,000 to be raised locally; that the owner of the lot asked $12,500 for it, and the hotel committee refused to pay the difference.
The commitment for the $60,000 to be loaned depending upon appellee's securing the Kerr lot and the Chamber of Commerce refusing to deliver the lot at the price agreed on, appellee could not be charged with the failure of the condition.
Appellant was, under the court's findings, charged with knowledge of the terms of the agreement between appellee and the hotel committee in regard to the lot, the letter written by the latter on March 8th was in effect notice that appellee's agreement to take the lot at $10,000 had not been complied with, and therefore the condition precedent as to liability on his part had failed. This was a substantial compliance with that part of appellee's agreement as to notice of cancellation.
It is concluded the other matters presented have in view of what has been said, become immaterial.
*862The judgment is affirmed.