71 Fla. 128 | Fla. | 1916
The Southern Menhaden Company exhibited its bill in the Circuit Court for Duval County against Harlan W. How and Edward S. How, Co-partners doing business under the names of Southern Engineering Company or Harlan W. How Company; Morris Engineering-Company, a Corporation; Webster Manufacturing Company, a Corporation, and Orr and Sembower, a Corporation.
The purpose of the bill seems to have been to obtain an adjudication in this proceeding as to complainants’ liability to the How Company on a certain building contract ; to ascertain the amount due if any; to restrain the How Company from prosecuting its bill in chancery against the complainants to enforce a builders’ lien'and to restrain the prosecution at law of suits by Morris Engineering Company; Webster Manufacturing Company and Orr and Sembower, material men, against the complainants to enforce liens for materials, and thus determine in. the one proceeding all the issues presented in the other causes.
The cause proceeded through the various stages of original bill, answers, cross-bills, answers thereto, and replications to the taking of testimony and a decree against the complainant, to which it objects and takes this appeal.
Every answer to the original bill contained a demur
No question of pleading or practice is involved, and there is little dispute as to the facts. The claims of the material men for materials furnished to the How Company which were used in the construction of complainant’s manufactory seem to have been agreed upon by all parties as to amount, the complainant denying that they held liens for such materials upon any part of its'plant, because at the time they served notices upon it of their intention to declare liens upon the plant the complainant owed How Company, the contractors, nothing.
The appellant contends that the decree was erroneous because the chancellor construed a clause in the building contract for liquidated damages as a penalty; that the chancellor failed to allow certain indebtedness of the How Company to complainant to be set off by complainant against How Company’s claim, and that the chancellor erred in holding that the How Company had substantially complied with their contract.
These questions are presented by the record, and we will discuss them, or so many of them as may be necessary to a determination of this cause. We will not undertake to copy the pleadings nor any part of the testimony, nor the final decree, but will give in substance so much of the proceedings as we deem essential to a clear understanding of the case.
The Southern Menhaden Company is a Florida Corporation which was organized for the purpose of engag
The Menhaden Company and Harlan W. and Edward S. How on January 15, 1912, entered into- a contract whereby the How Company agreed to fhrnish to the owner the Menhaden Company, certain machinery specified in the contract, of certain capacity and efficiency, to install the same, and have the plant completely equipped and in running order and in condition to receive fish on or before the nth day of March, 1912.
The payments were to have been made as follows: $5,000.00 when the contractors furnished a bond for the faithful performance of the contract; $3,100.00 within days after the furnishing of the bond; $4,860.00 upon the receipt of bills of lading showing shipment of the machinery; $3,240.00 when the factory was in running order to receive fish for the manufacture of them into oil and scrap; at the same time of the last payment in cash to deilver to the contractors, six promissory notes of the owner as follows: $4,000.00 payable in four months; $2,000.00 payable in five months; $2,000.00 payable in six months; $2,000 payable in seven omnths; $2,200.00 payable in eight months; and $4,000.00 payable in nine months. The four thousand dollars for the erection and superintendence and engineering work in connection with the mechanical equipment to be paid in cash from time to time as the work progressed. The factory was to have been built at a place about the distance of Fulton on the St. Johns River from. Jacksonville. The contract contained the following clause concerning which some trouble between the parties has arisen: “That for each and every day after the said nth day of March, 1912, the said plant is not in running order in accordance with the terms and, conditions of this agreement,
The statement condensed was as follows:
Cash payments to be made under contract------------------$20,200.00
10% Com:, on materials, etc____ 2,547.05
10% “ “ Generator______ 50.00
“Statements 8th inst.”________ 390.42
Total ------------------ $23,187.47
Payments made by Menhaden Company since Jan. 29, I9i2_$i7,710.00
Paid Bank on order_________ 1,500.00
Cash paid July 6th____________ 200.00
*137 Amt. clue from How Company as per statement July 1st------ 463.43
Deduction from How Company “Statements of 8'th inst.” 150.00
Total ------------------ 20,023.43
Balance due____________ $ 3,164.04
Notes to be delivered but not mentioned in statement____ 16,200.00
Total------------------ $19,364.04
On the same day, July 10, 1912, The Southern Menhaden Company wrote the How Company: “In confirmation of our verbal understanding with you that there will be no objection on your part to our deducting from the final notes due you in accordance with the terms of our contract with you for furnishing machinery and equipment for our factory the liquidated damages of $75.00 per day for 50 days, making a total of $3,750.00.” The request was made to confirm this by the endorsement of How Company, which was done.
On July 11, 1912, The How Company submitted to the Menhaden Company the affidavit of H. W. How showing amount due for machinery and equipment by the How Company, and a list of firms by whom the machinery was furnished. This affidavit showed an aggregate amount due of $10,116.53, and included the claims of Orr and Sembower, Morris Engineering Company and, Webster Manufacturing Company substantially in the amounts named by them in their cross-bills.
On August 8th, 1912, Mr. Pennington as President
On September 20th the How Company wrote to the Southern Menhaden Company that the How Company had consented to the deduction of $3,750.00 damages claimed by the Menhaden Company in consideration that the latter company would, assume responsibility for the obligations of the How Company as stated in the list and that as the Menhaden Company had refused to carry out its part of the agreement the matter of the $3,750.00 alleged damages'was left open.
The Webster Manufacturing Company, Orr and Sembower and Morris Engineering Company not having been paid the amounts due to them notified the Men
Upon final hearing, the testimony having been taken before the Chancellor and preserved in writing, a decree was entered adjudging the Menhaden Company to be indebted to the How Company in the sum of $12,200.00 for labor performed and materials furnished in the construction of the manufactory; that the Menhaden Company was entitled to set-off against that sum the amount of $4,939.15'on “account of the failure of the plant to comply in certain respects with the contract under which it was constructed;” that the judgment which the Menhaden Company had obtained against the How Company in March, 1913, for $2,064.15 was included in and satisfied by the decree, and that all questions raised by the pleadings were included in and settled by the decree; that the claim of the Menhaden Company for $3,750.00 against the How Company for alleged delay in completing the plant provided for a penalty, and not liquidated damages, and that the Menhaden Company had suffered no damage whatever by reason of the delay, and that it was not entitled to the penalty by reason of any agreement alleged to have been made after July. 5, 1912, and the claim was disallowed; that after deducting the $4,-939.15 from the principal sum of $12,200.00, there re
The original bill and amendment thereto alleged, that complainants obtained a judgment in March, 1913, against How Company in the sum of $2,067.69, that the judgment had never been satisfied nor had any pa3unent been made thereon, and that in December, 1912, the John Wood Manufacturing Company recovered judgment against the complainants and How Company in the sum of $252.42 for material furnished to How Company in the construction of the plant, and that judgment had not been satisfied, but complainants had agreed to pay it on or before July, 1914. These two items complainant
The complainant’s bill alleged that the How Company failed to substantially comply with their contract; that the plant was fatally and totally deficient and, defective in the particulars named in the bill; that these defects were pointed out to the How Company, but they ignored the complaint and abandoned their contract, and complainant had never accepted the plant as completed, and that by reason thereof it owed How Company nothing under the contract, and was not indebted to them at the time Orr and Sembower, Webster Manufacturing Company and Morris Engineering Company served notice of their intention to claim liens upon, complainant’s plant; that the clause in the original contract providing for the payment of $75.00 per day by How Company for each day’s delay in the completion of the plant provided for liquidated damages and not a penalty, and that it was entitled to receive from the How Company $3,-750.00 for 50 days delay to July 2, 1912, on account thereof.
The How Company in their answer denied that they had failed to comply with their contract, and denied that the plant was defective or inefficient, and averred that the clause above mentioned provided a penalty, and not liquidated damages. The cross-bill of the How Company alleged a full compliance with the contract and
We think that the conclusion of the Chancellor as to the balance remaining due from the Southern Menhaden Company to Piarían W. How and Edward S. How for labor and materials furnished in the construction of the manufacturing plant of the Southern Menhaden Company, and that the claim; of that company against Piarían W. How and Edward S. How for $3,750.00 for alleged delay in the completion of the plant is for a penalty and not liquidated damages, is error. The clause in the original contract providing for the payment of $75.00 for each day the completion of the plant should be delayed from the date agreed upon provides for liquidated damages, and is not a penalty. There is nothing to show that the delay in the completion of the plant was due to any fault of the appellant. There seems to have been an agreement between the parties as to the number of days the plant remained uncompleted. It was conceded that How Company notified the Menhaden Company on July 2, 1912, that the plant was completed. May 5th was the day upon which the parties seem to have agreed that the plant should have been finished; between those dates there seem to have been fifty working days after allowing for bad weather and other unavoidable delays.
The circumstances surrounding the parties to the contract at the time they entered into it, were known to all of them. The construction of an oil and fertilizer plant in which Menhaden fish were to constitute all, if not the greater part, of the raw material, was a new enterprise in that section of the State; the plant was to be occupied by the owner as soon as completed; a'large sum of money was necessary to be invested in a site for the plant,
The sum stipulated does not appear to be disproportionate to the probable damage that the complainant might have sustained; the parties could not compute with certainty the probable damage, it would have been difficult, perhaps impossible to prove the actual loss or damage resulting to complainant from the failure to complete the plant on the day named, yet there would be no doubt that damage would result equal to if not in excess of the amount stipulated The parties knew exactly their own situation and were in better position than anyone else to appreciate and make provision for the consequences of a failure to complete the contract on the day named. This language is in substance that of Judge White of Colorado in the case of Bilz v. Powell supra, and we think it peculiarly applicable to the circumstances of this case. See also Madler v. Silverstone, 55 Wash. 159, 104 Pac. Rep. 165.
We think, therefore, that the sum of $12,200.00 found by the Chancellor to be due from the Southern Menhaden Company to Harlan W. and Edward S. How should have been reduced by the sum of $3,750.00, the amount of liquidated damages.
The decree is reversed with directions to enter a decree in conformity with this opinion.