SOUTHERN LAND, TIMBER & PULP CORPORATION v. DAVIS & FLOYD ENGINEERS, INC.
40335
Court of Appeals of Georgia
JANUARY 9, 1964
FEBRUARY 26, 1964
The trial court erred in sustaining the general demurrers and in dismissing the petitions аs to the defendant Miss Georgia Dairies, Inc.
Judgments reversed. Nichols, P. J., and Jordan, J., concur.
Gambrell & Mobley, David H. Gambrell, Mays & Mays, Marshall T. Mays, contra.
EBERHARDT, Judge. Can the contract, as alleged here, withstand a demurrer attacking it on the basis of vagueness and indefiniteness? The defendant insists that uncertainty exists in four specifics, viz.: time for performance; when plaintiff‘s employees were to work; who would furnish the tools; and, the time for paymеnt. On the other hand, plaintiff contends that the contract, being one for the professional employment of engineers, would of necessity be somewhat indefinite and that these contracts cannot be drawn with the exactness of ordinary trade agreements.
There is a dearth of cases dealing with engineers and their professional contracts but we think an excellent analogy can be found in the more abundant architects’ cases. Georgia courts have generally grouped the two1 and usually architects have
An architect‘s contract case that directly supports plaintiff‘s theory is Folsom v. Summer, Locatell & Co., 90 Ga. App. 696 (83 SE2d 855). There the original record shows that the court was dealing with a standard American Institute of Architects’ Contrаct containing the following operative provision:
“1. The Architect‘s Services.—The Architect‘s professional services consist of the necessary conferences, the preparation of preliminary studies, working drawings, specifications, large scale and full size detail drawings, for architectural, structural, plumbing, heating, electrical, and other mechanicаl work; assistance in the drafting of forms of proposals and contracts; the issuance of certificates of payment; the keeping of accounts, the general administration of the business and supervision of the work.”
Plaintiff, having completed its services, declared on the contract seeking recovery of the fees as specified in it. In dealing with a vagueness аnd indefiniteness attack similar to that made here, Chief Judge Felton said: “The contract is for the performance of the enumerated architectural services required in the building of the motel and is definite and enforceable. It is not necessary that the contract set out the size of each room or unit, how many windows and doors each will contain, the type of plumbing, thе type of materials to be used, etc. The very purpose of this contract is for the formulation of these details by the architect. Such details will be contained in the architect‘s plans, drawings, and specifications which, among other services, the contract provides for. If detailed plans, drawings, and specifications were in existence and had to be incоrporated into this contract, there would be no need for a contract with an architect to perform these very services.” Folsom v. Summer Locatell & Co., supra, p. 698.
We view this direct holding as controlling. Certainly the contract here is no less definite than that involved in Folsom. Further support may be found in Curtis v. Burney, 55 Ga. App. 552 (1) (190 SE 866). There plaintiff was employed to draw plans and specifications and supervise construction of a house at $30 per week. After the plans were drawn and construction begun, defendant dispensed with plaintiff‘s services and com-
Architects’ cases from a number of other jurisdictions support this conclusion. Barton v. El En-Canto Apts., Inc. (Cal. App.) 6 P2d 1009, rev‘d on other grounds, 216 Cal. 503 (14 P2d 499); Johnson & Burns, Inc. v. Hayden, 98 Conn. 185 (119 A 50); Gaffney v. Switow, 211 Ky. 232 (277 SW 453); Wilkinson v. Orange Mountain Land Co., 103 N.J.L. 683 (137 A 591); Welch Mfg. Co. v. Herbst Dept. Store, 53 N.D. 42 (204 NW 849); Jacobberger v. School Dist. No. 1, Multnomah County, 122 Ore. 124 (256 P 652); Sauer v. School District, 243 Pa. 294 (90 A 150); Page v. Harlingen School District (Tex. Civ. App.) 23 SW2d 829, rev‘d on other grounds (Tex. Com. App.) 48 SW2d 983; Gould v. McCormick, 75 Wash. 61 (134 P 676). 1 Hudson on Building Contracts, Part IV, § 23 (4th Ed. 1914) states the English common law view to be in accord. And see Annot. 20 ALR 1356. Professor Corbin states: “If one contracts to produce a definite result, he is none the less bound because the means of producing that result are left to his own discretion.” 1 Corbin on Contracts § 100, p. 452 (1963 Ed.).
On the specific issues raised by the defendant, the holding and rationale in Wolf v. Arant, 88 Ga. App. 568 (77 SE2d 116) would appear to be controlling. Thеre it was said, at p. 571 in ruling on a demurrer raising the vague and indefinite points: “There is a general proposition that that is certain which may be made certain. With respect to contracts, a contract calling for the payment of a sum of money or performance of an indefinite amount of service is sufficient where the key for the determination of the sum to be paid or the service to be rendered is contained in the contract. Cohn & Co. v. Brown, 7 Ga. App. 395 (1) (66 SE 1038); Anderson, Clayton & Co. v. Mangham, 32 Ga. App. 152 (123 SE 159). If no time is specified for performance, performance is due immediately or within a reasonable time after the contract is made.” See, 6 EGL 87, Contracts, § 4. “Nor is it necessary that a contract shall state definitely and specifically all facts in detail to which the parties may be agrеeing, but as to such matters it will be sufficiently
The contracts alleged in both counts here are not too vague and indefinite to be enforced.
Defendant also asserts as a ground for sustaining its general demurrer that all of the damages are too speculative and impossible to ascertain. The measure of damages cannot be attacked by general demurrer unless none of the damages can be recovered. Hodges v. Georgia Kaolin Co., 108 Ga. App. 115, 119 (2), 121 (132 SE2d 86) and citations.
The measure alleged here is the difference between the total cost of the work under the contract and what the cost of performance would have been to plaintiff. Under the Georgia cases, this is the proper measure. Wallace v. Tumlin, 42 Ga. 462 (4); Jones v. Ely, 95 Ga. App. 4 (3) (96 SE2d 536); Luckie v. Max Wright, Inc., 90 Ga. App. 243 (3), supra; Curtis v. Burney, 55 Ga. App. 552, supra; Pittman Construction Co. v.Ellis, 39 Ga. App. 490 (147 SE 420). The foreign authority cited in Division 1 of this opinion, supra, also supports this measure.
Thus, this argument is reduced to a variation of the vague and indefinite issue discussed in Division 1, supra, and the rationale there largely answers the question. The allegations of the petition specifically set out the amount of engineering services necessary to complete plaintiff‘s performance and the actual cost to the plaintiff of the services. These allegations must be taken as true if they have any basis in probability. Based on them, the damages are “capable of exact computation” (Sanford-Brown v. Patent Scaffolding Co., 199 Ga. 41, 33 SE2d 422) and are therefore recoverable.
This disposition controls renewed special demurrer 4 to both counts.
3. The Special Demurrers. All of the demurrers were overruled.
(a) One special demurrer seeks to have plaintiff declare whether or not the contracts were in writing and, if so, to have copies of the contracts аttached to the petition. Another is on the ground that since it does not appear from the petition that the contract was in writing it affirmatively appears that it is void and unenforceable under the statute of frauds.
That it would have been perfectly proper to attach copies if the contracts were in writing is clear from
The defendant cannot require a plaintiff to allege whether or not the contract sued on is in writing. Allen & Holmes v. Powell, 125 Ga. 438 (54 SE 137); Montgomery v. Alexander Lumber Co., 140 Ga. 51 (1) (78 SE 413); Georgia, F. &c. R. Co. v. Parsons, 12 Ga. App. 180 (1) (76 SE 1063); Kiser Co. v. Padrick, 30 Ga. App. 642 (1) (118 SE 791); Wade v. Hopper, 89 Ga. App. 87, 90 (3) (78 SE2d 809). And if the petition carries a statement of the stipulations, provisions or the substance оf the contract it is not necessary that a copy be attached. Mercier v. Copelan, 73 Ga. 636 (3); Gibson v. Robinson, 90 Ga. 756 (1) (16 SE 969, 35 ASR 250); Penn Tobacco Co. v. Leman & Co., 109 Ga. 428 (3) (34 SE 679); Lynah v. Citizens &c. Bank, 136 Ga. 344 (2) (71 SE 469); Ramsey v. Langley, 86 Ga. App. 544 (1) (71 SE2d 863). An extension of this rule has even led to the result that an amendment attaching a copy of the contract is not a material one, consequently it would neither have the effect of opening it up to further demurrer nor require the renewing of one filed prior to the amendment. Hodson v. Scoggins, 102 Ga. App. 44 (115 SE2d 715).
A reading of the cases cited will reveal that generally the courts were dealing with demurrers upon the same or substantially the same grounds as are urged here. For example, in Ramsey v. Langley, 86 Ga. App. 544, 548, supra, the court asserted: “Treating count one as a suit upon the note, we are confronted then with the question of whether or not the court erred in sustaining the special demurrer requiring the plaintiff to attach a coрy of the note to his petition. . . . In paragraph 4 of the petition it is alleged that the note was made by the defendant to the plaintiff on September 15, 1948, and it presumably bore that date; it is alleged that the note was in the original amount of $1300; it is alleged that the note is payable in monthly installments of $50, and presumably each installment matures on the day of the month on which it falls due; and it is alleged that the note is to bear interest at the rate of eight percent from maturity. These allegations make a
In Georgia, F. &c. R. Co. v. Parsons, 12 Ga. App. 180, supra, it was held not to have been error to overrule demurrers “on the grounds, among others, that the plaintiff failed to attach to the petition a сopy of the contract in question, or to allege whether the contract was written or oral.”
The requirement of
The petition here does allege what the contract declared upon provided and sufficiently meets the rule of these cases.
As to the ground of the demurrer that since it did not appear from the petition that the contract was in writing and that thus it did appear that it was void under the statute of frauds, “[i]f the contract is of a kind required by the statute of frauds to be in writing, the presumption is that it was in writing.” Georgia, F. &c. R. Co. v. Parsons, 12 Ga. App. 180 (1), supra. “It
The overruling of these demurrers was proper.
(b) A number of special demurrers attack as “irrelevant and immaterial, and highly prejudicial” the allegations concerning the services rendered by plaintiff prior to the alleged breach. We think that these are allegations of inducement which, while merely serving to show the history of the case, are pertinent to the alleged cause of action. Roswell Apts. v. D. L. Stokes & Co., 105 Ga. App. 163, 166 (3) (123 SE2d 682). It is not improper to plead matters showing the history of the case or matters of inducement, and less certainty is required as to these than in setting out the gist of the action. Woodruff v. Hughes, 2 Ga. App. 361, 365 (58 SE 551); Delta Air Corp. v. Porter, 70 Ga. App. 152 (27 SE2d 758). Another demurrer seeks to have plaintiff specify the work actually completed under the contract and the names of those doing the work. The work done is set out elsewhere in the amended petition and the names of those performing the work is evidentiary.
(c) Defendant seeks to have the specific offices held by named persons in plaintiff‘s employ, which persons are alleged to have been “officers and agents . . . authorized to enter into said contract on behalf of petitioner, and then and there acting within the scope of their said employment.” Where, as here, there has been a recognition of the contract by both parties in the partial performance by one accepted by the other this factitious demand need not be met. Moreover, “[a] general allegation of the execution of a contract is sufficient,” Georgia, F. &c. R. Co. v. Parsons, 12 Ga. App. 180 (1), supra, and “[a]n averment that an agent was ‘duly authorized’ to act for his principal is not objectionable as being a conclusion.” Kiser Co. v. Padrick, 30 Ga. App. 642 (13), supra.
(d) A number of demurrers seek to have plaintiff allege the number of employees in its employ and their particular jobs and skills. These are evidentiary facts which it is unnecessary to plead. Oxford v. Shuman, 106 Ga. App. 73, 84,
Another demurrer was eliminated because the language at which it was directed was changed by amendment. Thus, no ruling is required.
All of the demurrers were properly overruled.
Judgment affirmed. Nichols, P. J., Bell, P. J., Frankum, Hall, Russell and Pannell, JJ., concur. Felton, C. J., dissents in part. Jordan, J., disqualified.
FELTON, Chief Judge, dissenting in part. I concur in all of the rulings except the ruling in Division 3(a), and I dissent from that ruling and the judgment of affirmance. Demurrer number 2, filed by the defendant, is as follows: “2. Defendant demurs specially to said petition on the ground that plaintiff does not state therein whether the contract declared upon was in writing or in parol, and on the further ground that if said contract was in writing plaintiff has failed to attach a copy to said petition.” Special demurrer numbеr 3 filed by the defendant is as follows: “3. Defendant demurs specially to said petition on the ground that it does not appear from said petition that the contract declared upon was in writing, and for that reason it affirmatively appears from said petition that said alleged contract is void and unenforceable under the statute of frauds.” There is a serious question whethеr the services allegedly contracted for could not possibly be performed within one year, but the demurrers reach the point that the defendant is entitled to have a copy of the contract attached to the petition whether the alleged contract came within the Statute of Frauds or not. If the contract was not within the Statute, the defendant is entitled tо have the contract attached if it is in writing. If the contract is within the Statute of Frauds, the defendant is also entitled to have a copy of the contract sued on attached to the petition.
The cases cited in the majority opinion are not authority for the ruling by the majority. It is true that where a contract is required to be in writing it is not a ground of demurrer that the petition does not allege whether it is in writing or not for the reason that the law presumes that it is in writing, but an objection that there is no allegation that a contract is in writing is not the samе thing as an objection that a copy of the contract is not attached to the petition. I think the majority is confused by the rulings of both of the appellate courts to the effect that a written contract, admittedly sued upon, need not be attached if it is sufficiently set out in the petition.
The cases holding that in the field of pleading the law presumes that a contract within the Statute of Frauds is in writing is unsound because often they are not in writing. Such a presumption is not conclusive and often prolongs litigation which could have been ended by the requirement of proper pleading. If Kiser Co. v. Padrick, 30 Ga. App. 642, supra, is the law we may as well tear