Southern Counties Gas Co. v. Ventura Pipeline Construction Co.Southern Counties Gas Co. v. Ventura Pipeline Construction Co.
Opinion
Since May of 1949, pursuant to a series of so-called master contracts, defendant has installed underground utility pipelines for use by plaintiff in the transmission of natural gas. However, contrary to a specification in the contract to that effect, defendant in several instances failed to apply proteсtive coating or wrapping, thus hastening the process of corrosion. Commencing in July of 1967, gas leaks were reported at several locations; investigation revealed that they were caused by corrosion
The principal question on defendant’s appeal from the judgment is whether the superior court was authorized to grant declaratory relief, thus properly retaining jurisdiction of the matter; if not, as urged by defendant, the proceeding should have been transferred to the municipal court since the amount in controversy was less than $5,000.
A complaint for declaratory relief can be filed only in the superior court (Code Civ. Proc., § 1060). Accordingly, where the request for such relief is bona fide and not a vehicle for forum shopping or calendar preference, it has been consistently held that the superior court has jurisdiction regardless of the amount in question.
(Silverman
v.
Greenberg,
In the present case the dispute arose over which of two sections in the
The trial court found in pertinent part that at the time and places alleged (with one exception) defendant failed to wrap the facilities it installed; that this was contrary to good workmanlike practice; that the failure to wrap permitted corrosion to occur which, in turn, caused gas leaks; that until said leaks were discovered, plaintiff was not aware of defendant’s failure to completely wrap said facilities. From the
Wе conclude that the court’s interpretation of the two sections is correct. Section 7.1(b) being an obligation to indemnify, “Indemnity agreements, like other contracts, must be so interpreted as to give effect to the mutual intention of the parties as it existed at the time of contracting, so far as the same is asсertainable and lawful. . . .”
(Indenco, Inc.
v.
Evans,
In light of the above considerations we find substantial evidence in the record to support the court’s construction of the. relevant portions of the agreement in suit. “ ‘It is well-settled that an appellate court will accept the interpretation of a contract adopted by the trial court and will not substitute another of its own where parol evidence has been introduced in aid of its interpretation and such evidence will support conflicting inferences. [Citations.]. . .’ ”
(Collins
v.
Home Savings & Loan Assn.,
The trial court having correctly construed the applicable portions of the contract to permit future claims based on leaks thereafter discovered, if due to the wrapping failures hereinabove discussed, there is the further question whether declaratory relief wаs the sole means by which such rights and duties could be adjudicated. (As previously shown, it is not improper to seek declaratory relief and damages simultaneously even if the latter demand is less than the jurisdictional minimum.) Defendant relies on the rule that declaratory relief should be denied where all of the issues involved in the declaratory relief action can equally be resolved in the plenary action—the above principle was adverted to in
Mascarin Professional Pharmacy
v.
Hart,
The facts at bar are likewise dissimilar. A gas leak due to the causes alleged in the complaint would not become nоticeable for from three to five years; since 1961 defendant had installed thousands of feet of underground pipeline for plaintiff in connection with a multitude of jobs; the leaks discovered through the time of trial (March 1970) related to installations made during the years 1962-1964. Absent a physical examination and inspection of thе underground lines, no way existed whereby it could be said that other deficiencies would not present problems in the future. As was held in
Eye Dog Foundation
v.
State Board of Guide Dogs for the Blind,
The above discussion disposes of all contentions on appeal save one, which is subsidiary in nature. Specifically, the claim is made that a previously quoted conclusion of law (No. 7) violates the rule requiring a unitary determination of all damages accruing from a breach of contract; such rule, however, is not applicable to actions for declaratory relief. In such an action the plaintiff has no obligation to submit for determination all or any part of accrued claims for coercive relief he may then possess as a part of the application for a declaratory judgment.
The judgment is affirmed.
Wood, P. J., and Thompson, J., concurred.
Notes
As for the monetary award, it is not now contended that the evidence fails to support the determination that the facilities were installed by defendant and that the reasonable cost of repairs was in the sum demanded by the complaint.
Section 11: “In addition to the specific guarantees required by other provisions in this agreement and the specifications for the work, Contractor guarantees all the work to be performed and all the materials to be furnished by him or his subcontractors (except for paving repairs) against defects in materials or workmanship which may develop within a period of one year from the date of final acceptance of the completed work by Company. Contractor shall, within a reasonable time after receipt of written notice of any such defects, correct or replace the defective work and shall pay for any resulting damage without cost to Company. If Contractor does not correct such defective work within a reasonable time after notice thereof, Company may correct such defects and charge to Contractor all costs plus a reasonable supervisory fee. Contractor guarantees paving repairs only to the extent that such shall be done pursuant, to specifications and to the satisfaction of the controlling governmental authority.” (Italics added.)
Section 7.1(b): “Contractor shall also indemnify Company against, and save it harmless from, all' liability and claims, demands, damages and costs of every kind, and shаll upon request by Company defend all suits, for injury to or death of any and all other persons, including, without limitation, employees and representatives of Company; and for injury, destruction, loss or consequential damages to property, including that of Company, resulting from or in connection with the performance of the work under this contract, excluding from this paragraph injuries to or deaths of persons, and injury, destruction, loss or consequential damage to property, resulting solely from negligence on the part of Company’s employees or representatives.”
Thus, section 11 was held applicable to the clаim resulting from the loose discovered at a certain location in Santa Susana.
One such rule, to which the above realistic approach must yield, declares that any uncertainties should be interpreted against the party-draftsman who caused them to arise; but, as noted in
Beverly Hills Oil Co.
v.
Beverly Hills Unified Sch. Dist.,