Opinion
Since May of 1949, pursuant to a series of so-called master contracts, defendant has installed underground utility pipelines for use by plaintiff in the transmission of natural gas. However, contrary to a specification in the contract to that effect, defendant in several instances failed to apply proteсtive coating or wrapping, thus hastening the process of corrosion. Commencing in July of 1967, gas leaks were reported at several locations; investigation revealed that they were caused by corrosion *377 due to the above coating or wrapping deficiency. Immediate repairs were madе on each occasion by plaintiff’s employees, and defendant thereafter refused plaintiff’s demand that it be indemnified for, and held harmless from, the cost of such repairs. Plaintiff by its complaint then sought reimbursement for the cost of such repairs ($1,026.30) and a declaratory judgment determining the respective rights and duties оf each party under the series of contracts. The trial court ordered reimbursement of the sums expended, as prayed, and also declared the rights of the parties under the several agreements pursuant to plaintiff’s additional prayer.
The principal question on defendant’s appeal from the judgment is whether the superior court was authorized to grant declaratory relief, thus properly retaining jurisdiction of the matter; if not, as urged by defendant, the proceeding should have been transferred to the municipal court since the amount in controversy was less than $5,000.
A complaint for declaratory relief can be filed only in the superior court (Code Civ. Proc., § 1060). Accordingly, where the request for such relief is bona fide and not a vehicle for forum shopping or calendar preference, it has been consistently held that the superior court has jurisdiction regardless of the amount in question.
(Silverman
v.
Greenberg,
In the present case the dispute arose over which of two sections in the *378 contracts should be held applicable. 1 Specifically, defendant urgеd that its obligations were limited by section 11, 2 entitled “Guarantee,” whereas plaintiff asserted that the rights and duties of the parties were measured by the provisions of section 7.1(b), 3 appearing under the heading “Indemnity and Liability.” According to defendant, section 11 restricted its liability only to those defects concerning which it was nоtified “within one year” after installation, no such notification was given as to the claims for repairs asserted at trial and, a fortiori, no action could validly lie for future claims, if any, asserted thereinafter. On the other hand, since section 7.1(b) contains no time limit, plaintiff urged that defendant was liable thereunder for all damages tо its facilities caused by breaches of the specification pleaded regardless of the time of their discovery; plaintiff additionally asked for a declaration as to whether the costs of such inspection for possible future claims could be chargeable to defendant under the contracts in quеstion.
The trial court found in pertinent part that at the time and places alleged (with one exception) defendant failed to wrap the facilities it installed; that this was contrary to good workmanlike practice; that the failure to wrap permitted corrosion to occur which, in turn, caused gas leaks; that until said leaks were discovered, plaintiff was not aware of defendant’s failure to completely wrap said facilities. From the *379 above the following conclusions of law (among others) were drawn: section 7.1(b) obligated defendant to pay plaintiff the reasonable cost incurred in making repairs; defendаnt was not obligated to pay for excavation of other facilities installed by it for the purpose of determining other similar breaches of the contract; and “7. Said judgment will be conclusive only on claims actually presented at the trial and not with respect to future .claims, if any, based upon leaks discovеred subsequent to the trial resulting from corrosion due to failure of defendant to wrap other facilities it installed pursuant to said contract.” In a memorandum opinion, the trial court declared that the two sections (7.1(b) and 11), respectively relied on, were consistent though redundant. In the court’s view, section 11 covered faulty work in the installation of the facilities, 4 whereas section 7.1(b) applied to damage to plaintiff’s property caused by faulty work; further in the court’s opinion, section 7.1(b) was not limited to the claims of third persons and provided a contractual basis of liability for the claims asserted in plaintiff’s complaint.
Wе conclude that the court’s interpretation of the two sections is correct. Section 7.1(b) being an obligation to indemnify, “Indemnity agreements, like other contracts, must be so interpreted as to give effect to the mutual intention of the parties as it existed at the time of contracting, so far as the same is asсertainable and lawful. . . .”
(Indenco, Inc.
v.
Evans,
In light of the above considerations we find substantial evidence in the record to support the court’s construction of the. relevant portions of the agreement in suit. “ ‘It is well-settled that an appellate court will accept the interpretation of a contract adopted by the trial court and will not substitute another of its own where parol evidence has been introduced in aid of its interpretation and such evidence will support conflicting inferences. [Citations.]. . .’ ”
(Collins
v.
Home Savings & Loan Assn.,
The trial court having correctly construed the applicable portions of the contract to permit future claims based on leaks thereafter discovered, if due to the wrapping failures hereinabove discussed, there is the further question whether declaratory relief wаs the sole means by which such rights and duties could be adjudicated. (As previously shown, it is not improper to seek declaratory relief and damages simultaneously even if the latter demand is less than the jurisdictional minimum.) Defendant relies on the rule that declaratory relief should be denied where all of the issues involved in the declaratory relief action can equally be resolved in the plenary action—the above principle was adverted to in
Mascarin Professional Pharmacy
v.
Hart,
The facts at bar are likewise dissimilar. A gas leak due to the causes alleged in the complaint would not become nоticeable for from three to five years; since 1961 defendant had installed thousands of feet of underground pipeline for plaintiff in connection with a multitude of jobs; the leaks discovered through the time of trial (March 1970) related to installations made during the years 1962-1964. Absent a physical examination and inspection of thе underground lines, no way existed whereby it could be said that other deficiencies would not present problems in the future. As was held in
Eye Dog Foundation
v.
State Board of Guide Dogs for the Blind,
The above discussion disposes of all contentions on appeal save one, which is subsidiary in nature. Specifically, the claim is made that a previously quoted conclusion of law (No. 7) violates the rule requiring a unitary determination of all damages accruing from a breach of contract; such rule, however, is not applicable to actions for declaratory relief. In such an action the plaintiff has no obligation to submit for determination all or any part of accrued claims for coercive relief he may then possess as a part of the application for a declaratory judgment.
*382
(Lortz
v.
Connell,
The judgment is affirmed.
Wood, P. J., and Thompson, J., concurred.
Notes
As for the monetary award, it is not now contended that the evidence fails to support the determination that the facilities were installed by defendant and that the reasonable cost of repairs was in the sum demanded by the complaint.
Section 11: “In addition to the specific guarantees required by other provisions in this agreement and the specifications for the work, Contractor guarantees all the work to be performed and all the materials to be furnished by him or his subcontractors (except for paving repairs) against defects in materials or workmanship which may develop within a period of one year from the date of final acceptance of the completed work by Company. Contractor shall, within a reasonable time after receipt of written notice of any such defects, correct or replace the defective work and shall pay for any resulting damage without cost to Company. If Contractor does not correct such defective work within a reasonable time after notice thereof, Company may correct such defects and charge to Contractor all costs plus a reasonable supervisory fee. Contractor guarantees paving repairs only to the extent that such shall be done pursuant, to specifications and to the satisfaction of the controlling governmental authority.” (Italics added.)
Section 7.1(b): “Contractor shall also indemnify Company against, and save it harmless from, all' liability and claims, demands, damages and costs of every kind, and shаll upon request by Company defend all suits, for injury to or death of any and all other persons, including, without limitation, employees and representatives of Company; and for injury, destruction, loss or consequential damages to property, including that of Company, resulting from or in connection with the performance of the work under this contract, excluding from this paragraph injuries to or deaths of persons, and injury, destruction, loss or consequential damage to property, resulting solely from negligence on the part of Company’s employees or representatives.”
Thus, section 11 was held applicable to the clаim resulting from the loose discovered at a certain location in Santa Susana.
One such rule, to which the above realistic approach must yield, declares that any uncertainties should be interpreted against the party-draftsman who caused them to arise; but, as noted in
Beverly Hills Oil Co.
v.
Beverly Hills Unified Sch. Dist.,
