This action arises out of a contract between Southern California Edison Company (SCE) and the City of Corona, California (Corona) under which SCE agreed to install interconnection facilities to provide electrical interconnection service to Corona. Under the parties’ Interconnection Facilities Agreement (Facilities Agreement or Agreement), Corona paid SCE in advance the estimated cost of installing the interconnection facilities and SCE agreed to furnish Corona with a final trued-up invoice for the actual installation cost within twelve months after the facilities’ in-sexwice date. SCE failed to meet the invoice deadline and instead filed rate revision sheets with the Federal Energy
I.
The facts are largely undisputed. On April 6, 2002, Corona applied to SCE to obtain wholesale distribution service for a proposed electricity distribution facility. In a letter approved by both parties and filed with FERC on August 2, 2002 (Letter Agreement), the parties memorialized an interim agreement both for interconnection service, with a proposed in-service date of December 1, 2002, and for installing the interconnection facilities. Pursuant to the Letter Agreement, Corona paid SCE an initial deposit of $10,000 toward the installation costs. Letter Agreement ¶¶ 2-3.
On January 31, 2003, SCE filed with FERC a “Service Agreement for Wholesale Distribution Service” and the Facilities Agreement, which the Commission accepted for filing in a letter order issued March 24, 2003. The Facilities Agreement, which by its terms supersedes the Letter Agreement, Facilities Agreement § 5.6, requires Corona to make to SCE an “Interconnection Facilities Payment,” which is the sum of all costs “associated with the design, engineering, procurement, construction and installation of the Interconnection Facilities,” id. §§ 4.14; see 4.16, 4.17, 4.19. Under the Agreement:
Corona shall make payments to SCE for the Interconnection Facilities Payment, according to the payment schedule shown in Exhibit C. The amount of such Interconnection Facilities Payment is based on SCE’s cost estimates and shall be subject to later adjustment pursuant to Sections 13.1.8.1 and 13.1.8.2.
Id. § 13.1.2. Section 13.1.8 of the Agreement provides:
Within twelve (12) months following the Interconnection Facilities In-Service Date ..., SCE shall determine the actual recorded Interconnection Facilities Cost ... and provide Corona with a final invoice.
Section 13.1.8.1 then provides that, if the estimated costs are less than the actual costs, SCE “will bill Corona for the difference between the amounts previously paid by Corona and the actual recorded costs, without interest, within twenty (20) calendar days of the date of such invoice.” Section 13.1.8.2 similarly provides that, if the amounts already paid exceed the actual installation costs, SCE is to refund the overage. The Interconnection Facilities Cost was initially estimated at $54,241.37, id. ex. B, with a balance due of $44,241.37 ($54,241.37 less Corona’s $10,000 deposit), id. ex. C.
In addition to the up-front Interconnection Facilities Payment, the Facilities Agreement imposes on Corona an ongoing monthly “Interconnection Facilities
Finally, the Agreement contains two general provisions of relevance here. The first is a choice of law provision:
Governing Law:
Except as otherwise provided by federal law, this Agreement shall be governed by and construed in accordance with, the laws of the state of California.
Id. § 23. The second reserves to SCE the right to apply to FERC to revise the interconnection rates:
Nothing contained herein shall be construed as affecting in any way: (i) the right of SCE to unilaterally make application to the FERC for a change in rates, charges, classification, or service, or any rule, regulation, or contract relating thereto, under Section 205 of the Federal Power Act and pursuant to the Rules and Regulations promulgated by FERC thereunder; [or] (ii) the right of Corona to oppose such changes under Section 205 of the Federal Power Act....
Id. § 18.2.
SCE installed the interconnection facilities as agreed, but with an in-service date of January 4, 2003.
See
FERC Ord. at 3; Corona’s “Motion to Intervene, Protest, and Motion to Reject” (Protest Motion) at 4; SCE’s “Answer to Motion to Intervene, Protest and Motion to Reject” (Answer to Protest Motion) at 3-4. Although the Interconnection Facilities Costs apparently exceeded the cost estimate in the Facilities Agreement, SCE did not submit a final invoice or bill Corona pursuant to section 13.1.8.1.
1
Answer to Protest Motion at 4. Instead, on August 17, 2005, SCE filed revised rate sheets with FERC pursuant to section 18.2 of the Agreement. In its filing, SCE claimed total installation costs of $72,198.50 and, accordingly, sought a supplemental Interconnection Facilities Payment of $17,957.13 and additional Interconnection Facilities Charges totaling $365.99 up to that time. Corona protested the revised rate sheets, asserting FERC should reject them as “inconsistent with rate [sic] on file with the Commission,” namely the previously filed Facilities Agreement requiring SCE to provide Corona with an invoice for the additional costs sought within twelve months after the interconnection facilities’ in-service date. Protest Motion at 4-5. SCE countered that FERC should accept the re
In an order issued October 11, 2005, the Commission rejected the revised rate sheets. The Commission concluded the revised rates are “contrary to the contract” because the Facilities Agreement requires SCE “to provide Corona with a final invoice within twelve months of the interconnection facilities’ in-service date,” that is, no later than January 4, 2004, and “SCE did not submit the final invoice through [the rate sheet] filing until August 17, 2005, 20 months after the deadline.” FERC Ord. at 3. The Commission therefore concluded that “SCE slept on its rights and thus forfeited the additional payment under the contract.” Id.
SCE filed a request for rehearing, asserting that FERC had not applied California law, as the Facilities Agreement requires, and that under California law SCE’s delay in performance was not a material breach that excused Corona’s performance. See SCE Req. for Reh’g at 8-10. FERC denied the reconsideration motion in an order issued April 24, 2006 on the ground that “[t]he contractual language ... establishes a condition precedent for SCE to recover true-up costs” and “SCE failed to meet that condition precedent.” Reh’g Ord. at 4. The Commission rejected Corona’s California law argument, stating:
With regard to SCE’s argument that the Commission should have applied state law, we note that first the Facilities Agreement provides that the agreement “shall be governed by, and construed in accordance, with the laws of the state of California, except as othenoise provided by federal laio.” SCE’s arguments focus on an outcome based on California law. However, SCE sought to collect these additional costs by filing its amended rate sheets with the Commission. SCE’s request involves interpreting a jurisdictional agreement that is on file with the Commission and that contains rates, terms, and conditions of service by a public utility. Accordingly, it was appropriate for the Commission to review SCE’s filing to collect the additional costs and the Facilities Agreement based on Commission precedent.
Id. at 4-5 (emphasis by FERC) (footnote omitted).
SCE petitioned for review of FERC’s orders on June 15, 2006.
II.
A.
Before addressing the merits of SCE’s petition, we consider FERC’s challenge to SCE’s standing under Article III of the United States Constitution.
See Steel Co. v. Citizens for Better Env’t,
In
Brotherhood of Locomotive Engineers,
the petitioner union argued that certain railroad track about to be acquired by
In
Brotherhood,
there was no dispute that the union through its collective bargaining agreement voluntarily relinquished its right to bargain in any section 10901 transaction or that its relinquishment of the right caused its injury (the inability to bargain).
2
Here, by contrast, it is sharply contested whether SCE in fact forfeited its right to recover the costs if it did not provide an invoice within the twelve-month period. Whether the Agreement makes recovery contingent on timely invoicing is precisely the issue of contract construction and law that FERC decided in its orders and that the parties argue here. Thus, FERC’s argument “is nothing more than an effort to bootstrap standing analysis to issues that are controverted on the merits.”
Pub. Citizen v. FTC,
B.
On the merits, SCE contends that FERC erred in failing to apply California
As already noted, the Agreement’s choice of law provision states: “Except as otherwise provided by federal law, this Agreement shall be governed by and construed in accordance with, the laws of the state of California.” Facilities Agreement § 23. Notwithstanding this language plainly mandates that the Agreement be construed under California law unless federal law is in conflict, FERC concluded it was “appropriate for the Commission to review SCE’s filing to collect the additional costs and the Facilities Agreement
based on Commission precedent”
because “SCE sought to collect these additional costs by filing its amended rate sheets with the Commission” and “SCE’s request involves interpreting a jurisdictional agreement that is on file with the Commission and that contains rates, terms, and conditions of service by a public utility.” Reh’g Ord. at 5 (emphasis added). Thus, FERC appears to have selected federal law over California law simply because the Agreement was filed with the Commission, without identifying any difference between federal and California law to justify such selection under the first clause of the choice of law provision. In this the Commission erred. The Commission may not ignore the plain language of a contract but instead must “give effect to the unambiguously expressed intent of the parties.”
Ameren Servs.,
Because the Commission did not give effect to the unambiguously expressed intent of the parties that California law govern construction of the Interconnection Facilities Agreement, we grant SCE’s petition for review and remand to the Commission to enforce the Agreement’s choice of law provision and to determine whether the twelve-month deadline to provide an invoice to Corona is a condition precedent under California law.
So ordered.
Notes
. According to SCE, it “finalized the true-up internally in December 2003“ and “informed Corona of the difference between the actual costs and the estimated costs of the Interconnection Facilities around that time." Answer to Protest Motion at 4. According to Corona, SCE' — apparently for the first time — "indicated that there had been cost overruns” in a letter dated May 7, 2004 but did not provide Corona with an invoice before then or thereafter. Protest Motion at 4.
. Similarly, in two other cases FERC cites, Resp’t's Br. at 12 n. 5, it was undisputed that the parties found to lack standing committed voluntary acts that caused the alleged injuries.
See Pennsylvania v. New Jersey,
