Southeastern Steel Erectors, Inc. (“Southeastern”) was the second tier subcontractor at a, job site owned by the lams Company (“lams”). On April 30,1990, Southeastern entered into an equipment rental agreement with Inco, Inc. (“Inco”) for a twenty-five ton Link-Belt crane. The agreement stated that Southeastern intended to Use the crane at “various jobs” and it also contained an option for Southeastern to purchase the crane at the end of the six month lease term. Inco provided no operator for the crane, but did on two occasions go to the lams site to make repairs, which repairs were not a part of the rental agreement.
Plaintiff-appellee Southeastern brought an action for a declaratory judgment “that [Inco’s] Notice of Claim of Lien of Third Tier Subcontractor ... is not valid, and that [Inco] is not entitled to a lien pursuant to Chapter 44A of the N.C. General Statutes.” Southeastern’s subsequent Motion for Summary Judgment was granted, the Superior Court finding that Inco’s Notice of Claim of Lien of Third Tier Subcontractor was, in fact, invalid and Inco was not entitled to a lien on the lams property pursuant to Chapter 44A. It is from this order for summary judgment that Inco appeals.
I.
Summary judgment is properly granted where there is no triable issue of fact so that the moving party is entitled to judgment as a matter of law.
Mace v. Lawyers Title Ins. Corp.,
A third tier subcontractor is defined as “a person who contracts with a second tier subcontractor to improve real property.” N.C. Gen. Stat. § 44A-17(5). Clearly, Southeastern is a second tier subcontractor. The rental agreement between Southeastern and Inco, however, is a simple contract regarding the use of the crane.The record indicates that Inco knew Southeastern intended to use the crane on various projects, and that the rental was not for the improvement of any specific property. Because Inco did not contract with Southeastern to improve real property, but rather to provide a crane, we conclude that Inco was not acting as a third tier subcontractor within the meaning of the statute.
However, even assuming arguendo that Inco did act as a third tier subcontractor, it is not entitled to a lien on the lams property because the rental agreement does not constitute the furnishing of labor or materials.
Article 2 of Chapter 44A provides no definition for the term “labor or materials” and there has been no North Carolina case up to now that has addressed this specific issue. There is, however, North Carolina case law addressing more generally the scope of “labor or materials” as used in Article 2, the statutory provisions of Article 3 of Chapter 44A, and case law from other jurisdictions addressing this particular issue. We discuss each of these in turn, and conclude that the rental of equipment is not within the scope of “labor or materials” in Article 2 of Chapter 44A.
A. North Carolina Consideration of Labor and Materials
This Court has recognized that the primary purpose of a lien statute is “to protect laborers and materialmen who expend their labor and materials upon the buildings of others.”
Carolina Bldrs. Corp. v. Howard-Veasey Homes, Inc.,
Section 44A-18 is found in Part 2 of Article 2 in Chapter 44A. Part 2 governs the liens of mechanics, materialmen and laborers dealing with someone other than the owner of the improved property, i.e., subcontractors. Part 1 of the Article, which includes section 44A-8, governs the liens of those dealing directly with the owner. A key concept in both sections is the furnishing of labor or materials. Much of the case law construing the terms' labor and materials have focused on 44A-8, but nonetheless govern the meaning of the same terms in 44A-18.
The concept of “labor” as used in the lien statute has evolved considerably through both case law and amendments to the statute. This Court has previously examined that evolution in
Wilbur Smith and Associates, Inc. v. South Mountain Properties, Inc.,
In 1969 the definition of “improve” was added to the statute and provided the following:
“Improve” means to build, erect, alter, repair, or demolish any improvement upon, connected with, or on or beneath the surface of any real property, or to excavate, clear, grade, fill or landscape any real property, or to construct driveways and private roadways, or to furnish materials, including trees and shrubbery, for any of such purposes, or to perform any labor upon such improvements.
The rules of statutory construction confirm that “providing rental equipment” is not equivalent to “furnishing labor.” Because it is not explicitly defined in Article 2, “labor” must be given its “common and ordinary meaning.”
In re Clayton-Marcus Co.,
B. North Carolina Bond Cases, Article 3 of Chapter 44A
Article 3 of Chapter 44A, which governs Performance Bonds, specifically provides that for the purposes of Article 3 “ ‘[l]abor or materials’ shall include all materials furnished or labor performed in the prosecution of the work called for by the construction contract . . . and further shall include . . . rental of equipment . . . directly utilized in the performance of the work . . . .” N.C. Gen. Stat. § 44A-25 (1989). Thus far, the legislature has not included any such definition in Article 2 and we, therefore, decline to apply the Article 3 definition to the provisions in Article 2.
Despite the difference between the two articles, appellant asserts that the reasoning of
Interstate Equipment Co. v. Smith,
Moreover, the suretyship relationship is unique and as such precludes our construing the legislature’s action in Article 3 as being meant also for Article 2. “[Suretyship creates a tripartite relationship between and among the party secured (the bond obligee), the principal (the bond obligor), and the party secondarily liable (the surety).” B.C. Hart,
Bad Faith Litigation Against Sureties,
24 Tort and Ins. L. J. 18 (1988). The surety’s duty arises at the time the bond is issued. In entering a contract to execute a bond, “the surety is [therefore] chargeable with notice ... as to whether [the contractor] possesses the plant, equipment, and tools required in undertaking the particular work, or will be compelled to rent and hire the same, or some part thereof, all of which matters are factors . . . upon which the surety fixes the premiums exacted for executing the bond.”
Interstate Equipment,
Other jurisdictions have directly addressed the issue of whether rental equipment should be included in the term “labor or materials.” The prevailing view appears to be that, absent a specific statutory provision stating otherwise, rental equipment is
not
“labor or materials.”
Logan Equipment Corp. v. Profile Constr. Co.,
Those jurisdictions which recognize rental equipment as labor adopt reasoning similar to that expressed in the North Carolina bond cases, Wiseman v. Lacy and Interstate Equipment Co. v. Smith, both discussed supra. While we recognize that the construction industry is changing and the traditional supply of manual labor is being rapidly replaced by machinery, we believe it is up to the legislature, and not this Court, to make corresponding changes in the statutes. Until our legislature indicates otherwise, then, we conclude that rental equipment is not “labor” under Article 2 of North Carolina’s lien statute.
The prevailing view of other jurisdictions appears also to be that rental equipment is not a “material” furnished for the improve
The minority view on the issue of whether rental of equipment is a “material” furnished, as asserted by the Tennessee Supreme Court in
R.L. Harris, Inc. v. Cincinnati, New Orleans, and Texas Pacific Railway Co.,
We conclude first that Inco was not a third tier subcontractor within the meaning of Article 2. Assuming for the sake of argument, however, that Inco was acting as a third tier subcontractor, we further conclude that the use of the term “labor or materials” in Article 2 of Chapter 44A does not encompass rental equipment. The history of the cases examining “labor” and “materials” supports such a conclusion, as does our recognition that, despite its addition of a definition of “labor or materials” expressly including rental equipment to Article 3, the legislature chose to make no such addition to Article 2. In so concluding, we adopt the prevailing view on this issue from other jurisdictions, which we believe is consistent with our direction. We, therefore, overrule appellant’s first assignment of error and hold that the general lease of this
II.
Appellant asserts, in its second and final assignment of error, that the repairs made by Inco on the crane, while it was at the lams site, are a lienable item pursuant to Article 2 of Chapter 44A. We disagree. To hold that the rental of equipment in this case will not give rise to a lien on the real property composing the lams site and then to subsequently hold that the repairs made to that equipment will give rise to such a lien is illogical.
The statute allows a third tier subcontractor to realize a lien on funds arising out of the improvement on which the third tier subcontractor worked or for which.it furnished materials. N.C. Gen. Stat. § 44A-18(3)..- Clearly, this statute contemplates work or materials directly effecting the real property.
Appellant once again points us to a bond case in an effort to support its contention that the repairs in question are within the scope of the statute. Even were we to agree with, appellant that such cases are relevant to the subject case, we cannot agree that the repairs in question constitute a lienable item.
Continental Casualty Co. v. Clarence L. Boyd Co.,
For the foregoing reasons, the decision of the trial court is,
Affirmed.
