By virtue of the stipulation between the parties, $17,383.62 retainage with interest on that amount has been liquidated between the parties and is not now an issue in this case. The only issue is the plaintiffs right to recover $74,508.12 together with interest on that amount and court costs for the plaintiffs "work of stock piling selected borrow before placing this material on the roadway in accordance with defendant’s orders.”
From the proof adduced there was a conflict as to whether the plaintiff was ordered or directed by the defendant’s engineer to
*165
stock pile material before placing it on the roadway. Since this is on motion for summary judgment, the evidence must be construed in favor of the party opposing the motion.
Hospital Authority of Fulton County v. AGN Mfg., Inc.,
The contract specifies 73$ per cubic yard for the work of "selected borrow.” It further provides that selected borrow will be paid for at the contract unit price established for this item and that "the price paid shall be full compensation for furnishing all labor, equipment, tools, superintendence, and incidentals necessary to complete the work.” (From 110.05 section of the contract.) On the other hand, Section 104.06 of the contract specifies with regard to material that is stock piled: "all such material shall be measured and counted for payment as Unclassified Excavation when it is first excavated, ... When the material is picked up from a stock pile and finally placed, both the excavation and the overhauls. .. will be measured and counted for payment under the appropriate Pay Items.”
In the construction of a contract it is to be construed most strongly against the party who formulated it.
State Hwy. Dept. v. Wright Contracting Co.,
The key is to ascertain the contractual intention of the parties. Here, as in
Western Contracting Corp. v. State Hwy. Dept.,
In the case sub judice where from the facts it cannot be definitely established whether the actions taken by the contractor fall within one section or the other section and the contract is ambiguous as to which section should control, it was error for the trial judge to grant the defendant’s motion for summary judgment.
There is no necessity here to establish that the defendant’s actions were fraudulent or such gross mistake as would necessarily imply bad faith or failure to exercise honest judgment. See
State Hwy. Dept. v. W. L. Cobb Construction Co.,
The trial judge erred in granting the defendant’s motion for summary judgment.
Judgment reversed.
