Southeastern Connecticut Regional Resources Recovery Authority (Southeastern Recovery) and Connecticut Resources Recovery Authority (Connecticut Recоvery) appeal from the judgment of the trial court denying their application to vacate an
Southeastern Recovery is a subdivision of the state of Connecticut that provides solid waste disposal services to its member municipalities. Connecticut Recovеry is also a subdivision of the state of Connecticut that develops solid waste proсessing and disposal facilities. Ref-Fuel is a company that constructed and operates a waste to energy facility (facility) located in Preston. In December, 1987, Connecticut Recovery and Ref-Fuel entered into a service agreement, under which Rеf-Fuel agreed to construct and operate the facility to provide waste processing services, and Connecticut Recovery agreed to issue bonds to finanсe the facility and to pay Ref-Fuel a service fee for its costs and services. Undеr a separate agreement between Southeastern Recovery and Connecticut Recovery, Southeastern Recovery agreed to deliver waste from its member municipalities to the facility and to pay the costs incurred by Connecticut Reсovery under its service agreement with Ref-Fuel. Fees to cover those costs arе collected by Southeastern Recovery from its member municipalities under separate waste management agreements. The service fees
Following the 1993-1994 contract year,
We are persuaded by our examination of the record, briefs and arguments of the parties that the judgment of the trial court should be affirmed. In a thoughtful and comprehensive memorandum of decisiоn,
The judgment is affirmed.
Notes
“The submission . . . defines the scoрe of the entire arbitration proceeding by specifically delineating the issues to be decided. . . . No matter outside that submission may be included in the award.” (Citations omitted.) Board of Education v. AFSCME,
The contract year runs from July 1 to June 30.
The trial court memorandum that we adopt, filed on March 22, 1996, addresses only the application to vacate. On July 22,1996, the court granted Ref-Fuel’s application to confirm by notation at the end of the application and incorporated that decision in thе consolidated judgment rendered on both files. The judgment states: “The court, having heard the parties . . . makes, in these consolidated actions, the findings set forth in its memorandum of decision . . . filed on March 22, 1996.”