154 Mo. App. 364 | Mo. Ct. App. | 1911
I. The plaintiff attempted a cross-appeal, and its purported abstract shows the following state of facts: That on the day the jury returned its verdict the plaintiff filed a motion for a new trial setting up (1) that the court’erred in admitting evidence over plaintiff’s objections; (2) in excluding evidence offered by plaintiff; (3) in granting instructions requested by defendant; (4) that the jury failed to follow instructions; (5) that the finding of the jury is contrary to the evidence; and (6) that the finding of the jury is contrary to law. That this motion was overruled and affidavit for appeal filed and appeal granted and ninety days given within which to prepare and file bill of exceptions.
When cross-appeals are taken in any case the parties may file a joint bill of exceptions and have their transcript prepared bringing up all the exceptions to this court; or, they may file separate bills of exceptions in the trial court and each party prepare an abstract to be filed in the appellate court. [Jungeman v. Brewing Co., 38 M'o. App. 458.] Neither of these courses was pursued by the plaintiff in perfecting its appeal. It appears that there is no separate abstract of the record, and no bill of exceptions was prepared or filed by the plaintiff in this case; that while plaintiff applied for and obtained leave to file a bill of exceptions, so far as we know, none was filed. From this statement it appeai-s that no cross-appeal was perfected by plaintiff and consequently its appeal has no existence in this court, and the only course open to this court is to dismiss the plaintiff’s abortive appeal as to the finding-on’ the first and second counts of the petition, which is accordingly done.
It is claimed by the appellant that it incurred no ■ liability by reason of the damage inflicted by the floods described in plaintiff’s petition because they were unusual and extraordinary, and that the law did not require it to anticipate such injuries, and that it was consequently not required to make preparations to avoid them. A railroad company constructing its road over a watercourse is bound to leave such waterways or openings as are sufficient to afford an outlet for all water that may reasonably be expected to flow through such watercourse, taking into consideration such fresh
The question as to whether the defendant should have anticipated the flood that occurred .on the 15th day of February, 1908, is to be determined by the evidence in this case. The petition is in three counts, each count claiming damages for a certain distinct flood, the first for the flood of November 17, 1906, the second for the flood of December 27, 1906, and the third for the flood of February 15, 1908. Witnesses who had lived in that country many years and who were famil
In. the face of this testimony as to the quantities of rainfall at times prior to the flood of February, 1908, there is no reasonable ground for the contention of the defendant that the rainfall on February 14th and 15th, 1908 was so unusual and unprecedented in amount that it could not have been reasonably anticipated and guarded against by the defendant; and this evidence at least presented to the jury the question whether the defendant should have known that such floods were to be expected prior to February, 1908, and we cannot say as a matter of law that the jury was not reasonably authorized in the inference they drew that the defendant should have anticipated and made due preparations to prevent the injuries arising to the plaintiff from the flood of February, 1908. The question of negligence under the evidence in this case was clearly one for the determination of the jury. [Gulf, C. & S. F. R. Co. v. Holliday, 65 Tex. 512.] In the case just cited it was also held that in an action against a railroad company •for damages caused by an overflow as a result of the
The defendant cannot escape the consequences of its negligence because the flood was an act of God. It is a Avell-settled principle that, if the defendant’s negligence commingled with and operated as a contributive element proximate to the injury, it is liable even though such injury was due to an act of God. In order for the defendant to escape liability under the exemption afforded by law, the act of God must be the sole and only cause of the injury, and this, too, unmixed with the negligence of the defendant, for if the defendant’s negligence commingled with it in the loss as an active and co-operative element, and the loss is proximate thereto, or, in other words, is a reasonable consequence of the negligent act, it is regarded in law as the act of the defendant rather than as the act of God. [H. A. Johnson & Co. v. Springfield Ice & Ref. Co., 143 Mo. App. 441, 127 S. W. 692; Brink v. Railway Co., 17 Mo. App. 177; Standley v. Railroad, 121 Mo. App. 537, 97 S. W. 244; Murphy v. Gillum, 73 Mo. App. 487.] This rule of law was again declared by this court in the case of Booker v. Railroad Co., 144 Mo. App. 273, 128 S. W. 1012, as follows: “The rule of law applicable to
such cases has been often declared, and is to the effect, that if the defendant’s negligence concurs with the act-of God, in point of time and place, or otherAvise so directly contributes to plaintiff’s damage that it is reasonably certain that the other cause would not have sufficed to have produced the injury, then the defendant is liable, notwithstanding he may never have anticipated the . intervention of superhuman force.” [See, also, Pruitt v. Railway Co., 62 Mo. 527; Moffatt Com. Co. v. Railroad, 113 Mo. App. 544, 88 S. W. 117; Davis v. Railway Co., 89 Mo. 340, 1 S. W. 327.]
W. C. Balm, who was well acquainted with the bridge, testified: “The probability of the girder in this bridge acting as a dam or obstruction to the water would naturally appear to anyone looking at the bridge. I computed the number of square feet in the space below the girder and the number of square feet in the surface of the girder which was Avithin the banks of the creek. There are 228 square feet in the space between the girder and the bottom of the creek and 230 square feet in the girder itself included within the banks of the creek.” It will be seen from this testimony that this girder obstructed the natural flow of the stream through its channel to the extent at least of nearly one-half of the channel. The evidence is beyond question that the 'defendant was warned of the condition of its bridge and the extent to which it was obstructing the flow of the stream, and that such bridge was causing injuries to the property owners aboVe the bridge. In a letter written to defendant by plaintiff on November 24, 1906, attention was called to the condition of this bridge across this creek, and defendant was therein notified that the same was so constructed as to interfere with the large volume of water which floA\rs through the creek in its natural course, and that during and after heavy rains, this bridge caused a large amount of damage to property along and near the creek on account of the creek being flooded, caused by the breaking of the water for the want of a proper outlet across defendant’s right of 'way. And it was further distinctly stated in this letter that plaintiff and other riparian owners had suffered great damage. To- this communication the defendant on December 30, 1906, made the following reply: “Referring to your several communications with reference to overflows of La Croix creek, we will immediately place an order for an additional span, and
As the evidence tended to show, the railroad bridge at the Cape La Croix crossing was supported by a massive iron girder, five feet wide and forty-six feet long; that it rested upon two bents of piling, each some sixteen inches thick and driven into the bed of the stream; that the bridge was so constructed that the girder extended down between the banks four and one-half feet and reached nearly from bank to bank. After the correspondence between the parties as to the insufficiency of this bridge, during the year 1907, the defendant, pursuant to its agreement, commenced to alter said bridge; in doing this, defendant moved the iron girder from under the bridge, but, instead of removing it from the watercourse so as to prevent the damming of the water and the injurious results occasioned by the overflows, left it practically in the same condition as an ob
Under this evidence it is sufficiently demonstrated that the defendant, wdiile exercising the privilege granted by the statute, disregarded the duty the law enjoins and so obstructed this stream as to reduce to one-half its capacity for carrying off the wmter. Not only that: After the consequences of the construction of the bridge were knowm to the defendant, it continued to maintain the bridge or girder across the channel of the stream and continued to maintain the obstruction after repeated requests to provide an increased water-wray and repeated promises on its part to do so, so as to protect the plaintiff and other property owners. But in this work of changing the bridge it moved the massive girder from beneath the bridge, leaving the same and the bents of piling to remain in the watercourse for a considerable period of time and it wras in that condition at the time of the flood in February, 1908. The evidence tends to show7 that there was no reasonable excuse for this delay; that the girder could easily have been raised and supported above the flow of the w’ater, and there is no evidence in the record to show
III. The appellant, however, contends that the damages awarded plaintiff — $1000—are excessive. That in its petition it claims damages in the first count for the overflow of November 17, 1906, in the sum of $1000 for restoring the soil washed away and expenses in endeavoring to protect the premises from further over-, flows; that in the second count of the petition, which was for the overflow of December 27, 1906, the plaintiff claims damages in the sum of $1000 because hindered and delayed1 in the use and improvement and rental of the said premises and because it would be put to great expense in restoring the soil washed away by the water and had been put to great expense in endeavoring to protect the premises from further overflow; that in the third count plaintiff claims damages for the flood, of February 15, 1908, in the sum of $1000 for expense it had been put to in restoring the soil washed away by the water, and had been put to great expense in en
The general rule of damáges is that the person suffering the damage is entitled to be compensated for all loss caused by the wrong or injury; and in actions for tort, the genera] rule is that the wrongdoer is liable for all injuries resulting directly from the wrongful acts, whether they could or could not have been foreseen by him, provided the particular damages are the legal and natural consequences of the wrongful act, and are such as according to common experience 'and the usual course of events might reasonably have been anticipated. The general rule as to the measure of damages in actions for injuries to real property is the difference in value before and after the injury to the premises. gome courts have held that where soil has been excavated or carried away by the wrongful act of another, the party injured is entitled to the cost of restoring it to its former condition. In this state it has been held that in actions for damages to real property caused by an overflow, the measure of damages to the land itself is the difference in value of the land before and after the flood by reason of the particular injuries; and, as .to houses or fences, their actual value is the measure of damages, guch value is measured by the sum which would be properly expended to restore the premises to their former condition. If the destruction of the houses or fences or other erections on the premises interfered with the beneficial enjoyment of the premises, then, in addition to the value of the property destroyed, the loss of rental value for the time it would take to re
The evidence herein tended to show that prior to the last flood plaintiff had constructed a levee along the creek in order to protect the land from overflow which cost between thirty and forty dollars; but, as the evidence did not show that the third flood injured this levee to any material extent, no recovery could be had for that. There was evidence tending to show that plaintiff had constructed a four-room frame house on the property costing about |425 which it rented at eight dollars a month. It appeared, however, that the tenant stayed in the house until After the third flood and moved out sometime in the year 1908, the plaintiff having sold the house before the tenant moved out. As this house continued to rent at the rate of eight dollars a month for some eight months after the third flood, it is not apparent that plaintiff sustained damage by reason of loss of rent on the house. The evidence tended to show also that by reason of the three floods some 900 cubic yards of earth was washed away from plaintiff’s land. On examination after the first flood, the evidence showed, about 400 cubic yards had been washed away. The second flood increased the depth of the channel that previous floods had washed out, cutting deeper and wider, and washed it out farther north, and this flood washed out some 200 cubic yards or more. The evidence further shows that the third flood caused additional damage to the land; that the ditch on plaintiff’s land was washed farther down and farther north and was made wider and deeper, and that possibly 250 cubic yards more of soil was washed away. It further appeared that it had cost the plaintiff forty cents a cubic yard to restore the earth. The evidence further showed that the plaintiff corporation was organized and engaged in buying and selling real estate and erecting houses; that after it purchased this tract of land, it laid it out in blocks and lots,
Under the evidence no data is furnished by which, under legal principles, the amount of plaintiff’s damages by reason of the failure to market its lots can be ascertained. Nor is it made to appear to what extent the failure to sell the lots was due to the several overflows, separately, or all combined, much less as to how much of such damage accrued to plaintiff by reason of the third flood to which alone the verdict of the jury limited plaintiff’s recovery. It will thus be seen that the evidence offered failed to show the special damages to the sale of the lots caused by the third overflow. Prom the evidence adduced it does appear that the verdict of $1000 was clearly in excess of the damages to which the plaintiff was entitled by reason of the third overflow.
For the reason above stated, tbe judgment is reversed and tbe cause remanded.