Affirmed by published opinion. Judge DUNCAN wrote the opinion, in which Judge MOTZ and Judge KING joined.
OPINION
The South Carolina Wildlife Federation and co-plaintiffs (collectively “SCWF”) brought suit against federal and state agencies and agency directors, alleging violations of the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq., arising from the proposed construction of the Briggs-DeLaine-Pearson Connector (“the Connector”) in South Carolina. Relevant to this appeal, the Director of the South Carolina Department of Transportation (“the Director”), who was sued in his official capacity, moved to dismiss on the ground that the claims against him were barred by sovereign immunity under the Eleventh Amendment. The district court denied the Director’s motion, and he filed this interlocutory appeal. 1 For the reasons that follow, we affirm.
I.
NEPA requires an agency undertaking a “major Federal action[]” to produce a “detailed statement” concerning “the environmental impact of the proposed action.” 42 U.S.C. § 4332(C). The environmental impact statement (“EIS”) must address, inter alia, any adverse impact a proposed project would have on the environment and possible “alternatives to the proposed action.” Id. For actions funded by federal grants to states, NEPA provides that the EIS may be prepared by state actors, with federal guidance, so long as the state actors have “statewide jurisdiction” and re *328 sponsibility for the proposed action. 42 U.S.C. § 4332(D).
The EIS process has several steps. The responsible agency must first prepare a draft EIS and solicit comments on it. 40 C.F.R. § 1503.1. Those comments must then be “assess[ed] and considered]” in drafting the final environmental impact statement (“FEIS”), which is published in the Federal Register. 40 C.F.R. § 1503.4, 1506.10(b). The FEIS is followed by issuance of a record of decision, which must: state the agency’s decision; “[ijdentify all alternatives considered by the agency,” specifically noting those that were environmentally preferable and the factors considered in rejecting them; and state whether the agency has adopted all proposed practicable means to minimize environmental impact. 40 C.F.R. § 1505.2. During the NEPA process, an agency cannot take any action which would “(1) Have an adverse environmental impact; or (2) Limit the choice of reasonable alternatives.” 40 C.F.R. § 1506.1(a).
The major federal action in the instant case is the construction of the Connector, a bridge which, when complete, will span fewer than ten miles and link the South Carolina towns of Rimini (pop.286) and Lone Star (pop.601). J.A. at 61; Appel-lee’s Br. at 7. The Connector is slated to cost between $100 and $150 million and will be fully funded through federal appropriations; no state money is scheduled to be used. J.A. at 94. Thus far, at least $16 million in federal funds has been appropriated for the project. J.A. at 95. In the ongoing case below, SCWF contends that the Defendants have failed to comply with the procedural requirements of NEPA and that therefore the Federal Highway Administration’s (the “FHWA”) approval of the project is invalid under NEPA.
The FHWA and the South Carolina Department of Transportation (“SCDOT”) undertook the NEPA process following Congressional approval of the Connector, with the federal and state agencies sharing responsibility for the preparation of the EIS. J.A. at 47-49, 64-65; see also Environmental Impact Statement: Calhoun, Clarendon and Sumter Counties, SC, 65 Fed.Reg. 71,349, 71,349-50 (Nov. 30, 2000). The agencies promulgated a draft EIS, which was prepared by state and federal officials in conjunction with outside consultants, in October 2001. J.A. at 8-9, 95-96. Following the receipt of comments, the FEIS was issued in December 2002; and in June 2003, the FHWA issued a record of decision approving the FEIS. J.A. at 96. The FHWA published notice of its decision in the Federal Register on March 17, 2006, establishing a 180-day period to challenge the agency action. SCWF timely filed suit seeking a declaratory judgment on the ground that the FEIS and record of decision were improperly issued and seeking an injunction against further action pending compliance with NEPA. J.A. at 37.
The named defendants below were the SCDOT, the Executive Director of the SCDOT,
2
the FHWA, and the Division Administrator of the FHWA. The SCDOT and the Director moved to dismiss, claiming that SCWF lacked standing to proceed, that SCWF’s claims were not ripe, and that both the SCDOT and the Director were entitled to sovereign immunity from suit pursuant to the Eleventh Amendment. The district court found that SCWF had standing and that the claims were ripe. On the question of Eleventh Amendment
*329
immunity, the district court found that there had been no congressional abrogation of the state’s immunity and so the SCDOT as a state agency was immune from suit. J.A. at 106-07;
accord City of Boerne v. Flores,
The Director also claimed Eleventh Amendment immunity. However, the district court found that the Director was not entitled to immunity pursuant to
Ex parte Young,
II.
As a court must satisfy itself of its jurisdiction, we turn first to the issue of standing.
Bender v. Williamsport Area Sch. Dist.,
We conclude SCWF alleged facts sufficient to survive a motion to dismiss for lack of standing. SCWF asserted that construction of the Connector would harm its members’ ability to use and enjoy the relevant area for a variety of educational, scientific, recreational, and aesthetic purposes, and that one or more of its members currently use the land for such purposes.
Sierra Club v. Morton,
Lastly, SCWF has shown that enjoining the Director from proceeding with the con
*330
struction of the Connector, and requiring the reexamination of the proposal in accordance with NEPA, would redress its procedural and substantive concerns. The re-dressability of an injury to a procedural right turns on the potential impact of the court’s action on the injury-causing party.
Massachusetts v. EPA,
The party seeking an injunction need not show that injunction of the state defendant would lead directly to redress of the asserted injury, but only that relief will preserve the federal procedural remedy.
Arlington Coalition on Transp. v. Volpe,
III.
A.
We now turn to the Director’s argument that the claims against him are barred by sovereign immunity. Neither NEPA nor the Administrative Procedure Act (“APA”) in itself provides a cause of action against state actors.
See
5 U.S.C. § 701 (agencies covered by the APA include authorities only of the United States government); 42 U.S.C. § 4332 (applying the provisions of NEPA to “all agencies of the Federal Government”);
Ely v. Velde,
*331
In light of circuit precedent, including our decision in
Maryland Conservation Council, Inc. v. Gilchrist,
In this case, the federal remedy to be protected is reconsideration of the FEIS. Although the Director argues that he will not proceed with construction absent FHWA approval, actions taken by the state short of building the road could change the cost of proposed alternatives, thereby impacting the federal agency’s review and reconsideration.
See Gilchrist,
B.
1.
The Director contends that regardless of the effect his actions might have on the NEPA process, the district court erred in finding that the Eleventh Amendment does not bar suits against him. The district court based its holding
*332
that the Director was not immune from suit under the Eleventh Amendment on
Ex parte Young,
which permits suits against state officers for prospective relief where there is an ongoing violation of federal law. J.A. at 107-10 (citing
Ex parte Young,
In Frew ex rel. Frew v. Hawkins, the Supreme Court summarized the Eleventh Amendment’s recognition of states’ sovereign immunity and the Court’s holding in Ex parte Young:
The Eleventh Amendment confirms the sovereign status of the States by shielding them from suits by individuals absent their consent. To ensure the enforcement of federal law, however, the Eleventh Amendment permits suits for prospective injunctive relief against state officials acting in violation of federal law. This standard allows courts to order prospective relief, as well as measures ancillary to appropriate prospective relief. Federal courts may not award retrospective relief, for instance, money damages or its equivalent, if the State invokes its immunity.
SCWF’s complaint falls within the doctrine of
Ex parte Young
permitting suits against state officials for prospective relief from ongoing violations of federal law. The declaratory relief SCWF seeks is simply the determination that past actions by the Defendants did not comply with NEPA. It adds no additional burden on the Defendants other than the injunctive relief, and therefore does not threaten the sovereignty of the state, represented by the Director.
See Verizon Md.,
2.
The Director further argues that he is not properly a party to this suit because he lacks the required “special relation” to the alleged violation of federal law.
See Ex parte Young,
Appellant argues that the required “special relation” is lacking in this case because the Executive Director of the SCDOT is not “charged with any duty under a federal statute or ... with enforcement of a state statute that would violate federal law.” Appellant’s Br. at 20. This test is inapposite. A court may look to state law to determine whether the requisite connection exists between an individual defendant and the federal statute at issue.
Lytle,
Under South Carolina state law the Director has supervisory authority over the state’s participation in the FEIS process. S.C.Code Ann. § 57-l-430(A) (2007). The Director and his agency are deeply involved in the preparation of the challenged FEIS and the procurement of permits to proceed with construction on the basis of the FEIS. By federal statute, the SCDOT is a “joint lead agency” with the FHWA in the preparation of any environmental document required by NEPA for the Connector. 23 U.S.C. §§ 139(c)(3), 139(c)(6)(B). Under the Director’s supervision, the SCDOT has participated in planning the Connector, in the process of applying to other state agencies for the permits necessary for construction, and in the EIS process. J.A. at 20-21, 27. The FEIS lists SCDOT employees among those who were responsible for its preparation and is jointly signed by two engineers, one from the FHWA and one from the SCDOT. Id. at 101 n. 3. And the SCDOT will be the agency eventually charged with the actual construction of the Connector. Id. at 101. As the administrative head of the agency with responsibility for carrying out its policies and representing the agency in its dealings with the federal government, the Director possesses a sufficient connection to the alleged violation of federal law.
Our jurisprudence supports the district court’s conclusion that a state official violates federal law by continuing work on a “major federal action” when the requirements of NEPA and its implementing regulations have not been satisfied.
E.g., Gilchrist,
IV.
The district court properly found that SCWF stated a cause of action for prospective relief under NEPA and that the Director was party to the suit. Accordingly, we affirm the order of the district court denying the Director’s motion to dismiss SCWF’s complaint.
AFFIRMED
Notes
. Denial of a motion to dismiss on grounds of sovereign immunity is immediately appeal-able under the collateral order doctrine.
See P.R. Aqueduct & Sewer Auth. v. Metcalf & Eddy, Inc.,
. At the time the suit was filed, Elizabeth Mabry was the Executive Director of the SCDOT. Appellant, H.B. Limehouse, Jr., subsequently assumed that position. Because the Director was sued in his official capacity, Limehouse was substituted as a party to the suit pursuant to Fed.R.Civ.P. 25(d).
. We consider the Director’s challenge to SCWF’s standing, although we do not ordinarily entertain claims raised initially on appeal because standing implicates this court’s jurisdiction. Though the Director did not challenge SCWF’s standing in proceedings before the district court, other defendants not parties to this appeal did so. Upon consideration of their motion to dismiss, the district court concluded that SCWF’s standing was adequately established. J.A. at 97-102.
. As the Director notes,
Arlington Coalition
did not specifically order injunctive relief against state defendants under NEPA.
See
In this case, the state agency is a named "joint lead agency” on an extant FEIS. The Director and his agency have been heavily involved in the entire EIS process required by federal law. Where, as here, sovereign immunity is not a bar, this court has jurisdiction over the state to preserve the integrity of federal remedies.
. In
Jersey Heights Neighborhood Ass’n v. Glendening,
the court assumed without deciding that the APA provided a cause of action to enjoin non-federal defendants from proceeding in violation of NEPA.
Other circuits, which have concluded that NEPA does not create a private right of action, have required litigants to bring NEPA actions through the APA. However, by its terms, the APA applies only to federal agencies.
See, e.g., Karst Envtl. Educ. & Prot., Inc. v. EPA,
