89 Wash. 459 | Wash. | 1916
This action arises out of a building contract, and has for its basis a claim for an item in the sum of $4,078.40 as an extra. After the issues were framed, the cause was tried to the court sitting without a jury, and resulted in a judgment dismissing the action. From this judgment, the plaintiff appeals.
On April 23, 1912, the respondent contracted with the appellant for the erection of a six-story building at the southwest corner of Fourth avenue and Pike street, in the city of Seattle, for the sum of $188,000. This building was to be constructed according to plans and specifications then agreed upon. Thereafter, and before the construction of
The owner, within the time specified in the supplemental contract, notified the contractor that he desired the building erected to ten stories instead of six. The architect, acting for the owner, then directed the contractor to construct the building for the third elevator. The ten-story building was erected and three elevators provided for. In the construction of the three elevators, the contractor was not required to remove any previous construction. His claim as an extra for this work is based upon constructive work only.
The controversy in this case is over the claim by the contractor that the third elevator was an extra. The question is whether the plans and specifications required the installation of the third elevator if the owner exercised, as he did, his option to have the building erected the four additional stories. The contract between the parties, except in particulars not here material, made the architect the arbiter or umpire for the purpose of deciding questions that might
It is not claimed in this case that the parties did not have the right by contract to constitute the architect an umpire for the purpose of settling disputes and making his decision final, in the absence of fraud, arbitrary conduct, or palpable mistake; but it is claimed that the architect, in construing the plans and specifications as calling for a third elevator when the four additional stories were added, acted arbitrarily, and did not exercise an honest and independent judgment.
Upon the trial of the cause, the conti’actor produced a number of expert witnesses who testified that the plans and specifications could not reasonably be read to call for the construction of a third elevator when the four additional stories were added. The owner, the respondent, produced a number of expert witnesses who testified that the proper reading of the plans and specifications required the contractor to make the construction of the third elevator for the ten-story building. The trial court found that the contract, plans, and specifications reasonably meant that, if the additional stories were added, the third elevator was to be installed ; and that the decision of the architect was not fraudulent, arbitrary, or the result of palpable mistake on his part.
The question here is not whether the architect can. read into the plans and specifications what is not found there, and thus, in effect, make a new contract for the parties, but is whether the architect acted arbitrarily, and did not exercise
The judgment will be affirmed.
Mourns, C. J., Bausman, Holcomb, and Paeiceb, JJ., concur.