Soike v. Evan Matthews and Co.Soike v. Evan Matthews and Co.
Lowell and Karen Soike retained Evan Matthews and Company to do cement work for their new house. When it appeared the house has been “staked” too low in relation to the street, the Soikes sued the contractor. While the petition and pretrial orders referred to duties arising out of the contract, the jury was also instructed on the theory of negligence. Matthews complains on appeal that it was error for the trial court to instruct the jury on negligence arising out of the performance of the contract because (1) the “staking” of the house was voluntarily assumed, and independent of its duties arising under the contract, and (2) submission of that issue was outside the scope of issues framed by the plaintiff’s petition and
The facts bearing on these issues are virtually undisputed. Matthews, a cement contractor, was low bidder on a project to pour the foundation and concrete flatwork on the home. The written contract which followed did not deal with the responsibility to set the elevation of the house; however, Matthews voluntarily assumed this responsibility. Matthews concedes on appeal that as a result of negligence in surveying the lot the foundation was built too low in relationship to the street. It contends the negligence, however, was that of the Soikes, whose directions were merely carried out by Matthews.
I.
Matthews first contends that any negligence in surveying was improperly submitted “when plaintiffs at all times maintained that the action was founded on contract alone.” However, the petition referred to an attached, written contract for the concrete work and to Matthew’s assumption of the surveying responsibilities. It alleged negligence as to the surveying because it was “not done with proper regard for the topography of the lot, resulting in the basement being dug too low.” Pointing to the contents of the petition, Matthews contends it was clearly based upon negligence in performing the contract, not upon a claim arising
outside
the contract by the voluntary assumption of a duty. It concludes that the petition, as framed, misled the company in the preparation of its defense. Matthews also points to the plaintiffs’ pretrial statement of issues, (
We note, first, that the petition could reasonably be construed to allege both a claim under contract and a parallel duty of due care in respect to the surveying. Following allegations concerning the concrete work which was to be performed under the contract, the petition alleged Matthews’ assumption of the surveying responsibilities and its negligence in performing them. Second, and more significantly, the petition was not required to identify a specific legal theory; it is sufficient if the prima facie elements of a claim are stated, and this statement is “fair notice” to the defendant.
Lamantia v. Sojka,
While a pretrial conference is a recognized means of narrowing the issues, 5 Wright & Miller,
supra,
at 59-60, Matthews claims too much for that procedure here. The trial court’s pretrial statement of issues is necessarily based upon information furnished it by the parties.
See
It is clear that the parties, who apparently undertook no discovery proceedings, did not know themselves at the time of the pretrial hearing what the specific issues would be. The trial court’s pretrial order merely reflected that fact. During the trial the Soikes were requested to advise the court whether they relied upon “a theory of contract breach or ... on a negligence growing out of a contract duty or other duty”. (Emphasis added.) In their response, they indicated a reliance on the negligence theory. No amendment to the petition was requested, apparently because, as the court pointed out at that time, the petition was susceptible to both contract and negligence interpretations. Although Matthews amended its answer, after leave was granted, it merely alleged that the Soikes’ negligence was the sole proximate cause of the damage. At no time prior to objections to the court’s final instructions did Matthews articulate to the court its complaint that the issues framed by the pleadings and pretrial order would not accommodate a theory of negligence in performance of a duty not covered by the contract. Even then it did not show any prejudice to it in presentation of a defense, nor does it now make such claim. It is difficult in fact to see how Matthews could be surprised or prejudiced by the submission of the issue of its alleged negligence in staking the house. The real issue was whether it was Soikes’ or Matthews’ negligence that was responsible for the staking error, not the collateral question of whether Matthews’ duty of care arose from within or without the contract.
We believe the issues were not restricted in the manner now complained of by Matthews, either by the petition or the court’s pretrial order, and the issue of negligence in surveying was properly submitted to the jury.
II.
Matthews contends that the court erred in not making the preliminary legal determination of whether any duty was owed to the Soikes in respect to the
In its ruling on Matthews’ motion for judgment notwithstanding the verdict,
Matthews also complains that submission of the gratuitous-duty issue, which it claims was not within the parameters of the pleadings or pretrial order, denied it due process of law. However, as we held in Division I, this issue was within the parameters of issues. Furthermore, we see nothing in the record to indicate it raised this argument in the trial court. Issues raised on appeal, even those of constitutional dimension, will not be considered for the first time on appeal.
Thiele v. Whittenbaugh,
We find no error. The judgment is affirmed.
AFFIRMED.