150 Iowa 73 | Iowa | 1911
The controversy out of which this action arose has been prolonged and the history of the case is unique. Plaintiffs are contractors and as such they secured a contract with the defendant city for paving certain streets in said city, the costs thereof, except for street intersections, to be taxed up against owners of abutting property, and the contractors agreed to receive assessment certificates in full compensation for their work and materials. By the terms of this contract, the' work was to have been commenced on or before May 1, and completed on or before July 1,- 1903, - and as will hereinafter be noted certain penalties were affixed for failure to complete within the time named. The work was not completed- within the time fixed, but sometime thereafter the . contractors, claiming to have completed the work, an assessment was levied upon abutting property owners according to the report of the city engineer. Certain of these property owners then brought action against the city, the contractors, and various other parties, to cancel these assessments and to enjoin the issuance of assessment certificates. To that action, Snouffer & Ford appeared, as did the city. Snouffer & Ford, plaintiffs herein, filed an answer to the petition of the property owners in which they
That decision held, in effect, that Snouffer & Ford had not complied with the terms of their contract, that there had been very material and substantial departures therefrom, and that there had been no acceptance of the work by the city council or by any officer authorized by it to act. The right of assessing abutting property owners and to issue assessment certificates was denied, and a decree of permanent injunction was issued as prayed. Deference is made to the opinion for a better understanding of the issues and of the facts disclosed upon the trial. Thereafter, instead of attempting compliance with its contract, plaintiffs brought suit directly against some of the abutting property owners, in which they sought to recover judgment for the value of pavement laid in front of their property, claiming that they had offered to cure
Thereafter, and while the last-named action was pending in this court, the present action was commenced. It was brought shortly after the decision of the first case mentioned and proceeds upon two theories: First, that plaintiffs are entitled to recover from the city the reasonable value of the pavement as upon quantum meruit; and, second, that they are entitled to recover the value of the work and materials from the city, for the reason that the city refused to point out the defects which it claimed existed in the pavement that plaintiffs might remedy them, which it offered to do, thus depriving the city of the power and authority to assess the cost of the improvement against abutting property owners and to issue assessment certificates to plaintiffs, as it had agreed to do. Plaintiffs assume the attitude now of having failed to comply with the terms of its contract, but they still insist upon their right to recover either on quantum meruit or because the city failed to point out. defects that they might remedy them, and thus pave the way to the making of valid assessments.
The reason for this is that assessments are not based upon contract; but are purely in invitum, imposed in virtue of sovereign power. It is a forced contribution and can only be sustained where the law providing for the assessment is followed. The irregularities, defects, etc., referred to in section 986 of the Code are those of the officers of the city relative to the proceedings which do not affect the substantial rights of the parties. Neither the city nor the property owners can be forced to pay for a pavement which fails to comply substantially with the contract made for its construction.
Defendant denies that any adequate demand was made upon it; says that the demand, ’ if any was made, was too late and ineffective; that when demand was made, it had no power to comply therewith, and further pleads an estoppel and an adjudication in virtue of the former decisions. Down until the time of the decision of this court in the first case plaintiffs were insisting without qualification, that they had fully complied with the terms of the contract on their part to be performed, and they did not, in their cross-petition filed against the city in that case, ask that the claimed defects be pointed out, aver a readiness to cure and remedy them, or ask a judgment for the value of the materials furnished and labor performed. They knew from the time of the filing of the petition in the Wingeri case that many defects were claimed and these were pointed out by the petition. Instead of offering to cure the defects, they elected to stand upon the proposition that there were no defects and to take the judgment of the court on that issue. The cause being in equity, they might then have made demand upon the city to point out the defects and have remedied them before putting the parties to the trouble and expense of long litigation. It was only when defeated in that case that they offered to remedy any defects and their offer then was:
We, the undersigned, having finished, as we believe, the .pavement under our contract with the city of Tipton, Iowa, for the construction of pavement on Fourth Street from the east line of Cedar Street to the east curb line of East Street, on Meridian Street from the north line of Fourth Street to the south line of Fifth Street, in your city aforesaid, do hereby respectfully ask your honorable body to order an assessment and issue certificates in payment for same to us, in city warrants as contract provides; and that same may be expeditiously done, we hereby*79 notify yon that we are ready and willing, and do hereby offer, to remedy any defects and reconstruct any portion of said pavement at our own expense, which your honorable body may point out or designate, and' to complete all of said work up to the substantial requirement of our said contract. That the matters herein referred to may be speedly accomplished and performed, we request early action hereon, so that we may be advised and act accordingly. Dated this 1st day of October, 1906. Snouffer & Ford, by J. J. Snouffer, Jr.
This offer was made six days after the original opinion was filed in the Wingert case. It was made, as will be observed, on October 1, 1906. Unless there be something in the original contract which gave them the right to reconstruct or remedy the defects, it is manifest that they are concluded by the adjudication in the original Wingert case.
. Not only is this the rule, but we are also of opinion that unless there be something in the contract authorizing it, plaintiff can not, after having insisted that the work was done according to contract and turned tlie same over to the city in compliance with that contract and after being defeated upon the issue of performance, then come in and claim that they have the right to remedy defects or reconstruct, unless there be something in the contract itself which permits it, and it may be that the city council had .no authority to extend the time for the completion of the contract. See Code, sections 813 and 815, as construed in Osburn v. Lyons, 104 Iowa, 160. Upon the latter proposition, we make no pronouncement at this time. Going now to the contract under which the work was done, and which it is claimed gave plaintiffs the right to reconstruct,, we find the following to be the only relevant provisions:
(13) If the contractor shall abandon his work under this contract, or if at any time the engineer shall be of the opinion and shall so certify to the committee that the work or any part thereof is unnecessarily delayed, or that the contractor is wilfully violating any of the conditions
(14) The successful bidder must sign the contract for the work to be done by him within six (6) days after the contract is awarded to him and he has been notified thereof, and must begin work on or before May 1, A. D. 1903. He shall proceed with the work, prosecuting it with due diligence from day to day, and complete the same on or .before July 1, A. D. 1903. . . .
(17) No charge made by the contractor for any delays or hindrance from any cause during the progress of any portion of the work embraced in his contract will be allowed. If the delay be caused by any act or neglect of the city, then lie will be entitled to an extension of the time allowed for the completion of the work sufficient to compensate for the delay, to be determined by the committee, provided the contractor shall give the committee immediate notice of the cause in writing. If the contractor fails to complete the work at the time specified, unless caused by unavoidable or accidental delays, or by express agreement with the committee, he shall forfeit to the city, as liquidated damages, the sum of ten ($10) 'dollars per day for each and every day which the completion of the work is delayed beyond the time fixed by the contract. . . .
(20) All materials furnished and work done will be inspected by the engineer, and ■ if not in accordance with these specifications and the contract, they will be rejected and shall be immediately removed, and other work done and materials furnished in accordance therewith. If the contractor refuses to remove the work and materials as
Inspectors may be appointed by the committee, whose duty it shall be to point out to the contractor any neglect or disregard of these specifications, but the right of final acceptance or condemnation shall not be affected by such inspection.....
(21) . . . The contractor shall enter into a bond with the city, guaranteed by a corporate surety authorized to do business in Iowa, in an amount -equal to one-half of the contract price, conditioned upon the full and faithful performance of the contract in accordance with its terms and with the plans, general specifications, and detailed specifications attached to and made a part of said contract, . . . conditioned further upon the keeping of the pavement in perfect repair and condition for the period of two (2) years from the acceptance of the work. Said bond to be approved by the mayor of the city and retained by him, as such officer until the expiration of the guarantee period.
(22) No estimates will be made on any part of the work not completed, nor any materials, except in completed work.
A final estimate of all the work done and materials delivered according to the contract and these specifications will be made immediately after the engineer has satisfied himself by tests, examinations, or otherwise that the work has been and is finally and fully completed in perfect
(23) Payments will be made on the completion of the contract and the acceptance of the work by the city council in assessment certificates and warrants on the improvement fund, as provided by the laws of Iowa and the ordinances of the city, as soon as such certificates may be legally issued. ...
All work will be done under the general supervision of the committee, and. in accordance with stakes set by the engineer. He shall set line and grade stakes for the curb, but all other grades shall be taken from the curb elevations by the contractor.
These provisions are found either in the proposals for bids or in the specifications, each of which was made part of the contract.
In the contract itself is found the following:
Said party of the second part hereby agrees to commence said work on or before the 1st day of May, 1903, and to have the same fully and finally completed on or before the 1st day of July, 1903. Said party of the second part and his bondsmen hereby agree to keep said pavement in good repair for the period of two years after completion thereof, and it is agreed and understood that in case the party of the second part shall fail to enter upon the work at the time fixed so to do or to do and to perform and complete said work as herein stated and within the time specified, they shall forfeit and pay the sum of ten dollars ($10) to the party of the first part for each day they are so in default as liquidated damages, and in case they shall be so in default for thirty days, then, without impairing the right of the party of the first part to such damages, the party of the first part may at once take possession of the said work and employ sufficient force, under a competent foreman, to complete the work within the time specified, or as soon as may be, and the cost of such work shall be paid by the party of the second part and the cost of said work together with said damages shall be a valid claim on behalf of the city of Tipton against the party of the second part and the sureties on their bond.
Now, if the said obligor shall faithfully perform its part of the contract hereto annexed and referred to above, according to the plans and specifications hereto annexed and referred to above, and shall properly complete said improvement within the time specified in said contract and specifications, and shall hold the city of Tipton harmless in ease of accident or damage of any kind whatsoever during the construction of said street improvements, and shall keep said street improvement in good repair for a period of two (2) years from and after the completion thereof as above, without expense to the said city of Tipton, then this obligation to be void, otherwise to remain in full force and virtue.
That we may eliminate the matter of acceptance of the job by the city, we here refer to what is said on that matter in the original Wingert case. The contract was entered into on December 3, 1902, and the time for completion was fixed as July 1, 1903. Plaintiff assumes that, notwithstanding this limit as to timé, it had the right at any time, when objection was made thereto, to reconstruct or remedy defects no matter how long it had been in default. We do not take this view of the contract. It seems to ns that the only right of reconstruction given the contractor was during the life of the contract, that is, prior to July 1, 1903. Time was made'the essence of the contract, and the bond guaranteed performance within the time so fixed. A penalty in the form of liquidated damages is also provided for in the contract and in the bond. It is difficult to see how the parties could have more effectively made time of the essence of the contract. We are constrained to hold that the offers to reconstruct or remedy defects must have been made during the life of the contract or not later, at least, than when the defects were pointed out, as they were in this case, when the original action was brought, or when the city responded to plaintiffs’ cross-
In the law of estoppel, we find this well-settled principle. A party who has, with knowledge of the facts, assumed a particular position in judicial proceedings is estopped to assume a position inconsistent therewith to the
These doctrines are to be distinguished from what is known as election of remedies. They are all bottomed, it is true, upon estoppel, but an election of remedies upon a given state of facts is quite different from an estoppel,
The decree of the trial court is correct, and it is. affirmed.