Snider v. Production Chemical Manufacturing, Inc.Snider v. Production Chemical Manufacturing, Inc.
Plaintiff worked for defendant as its national sales manager. The parties entered into a four-year employment agreement in 1999, which they renewed in 2003. Section 9.02 of that agreement provided:
“Any controversy between [defendant] and [plaintiff] involving the construction or application of any of the terms, provisions, or conditions of this agreement shall on the written request of either party served on the other be submitted to arbitration. Arbitration shall comply with and be governed by the provisions of the California Arbitration Act.”
On January 30, 2005, defendant terminated plaintiffs employment. Approximately one week later, plaintiff filed a breach of contract action against defendant in Multnomah County Circuit Court. Over the next seven months, defendant challenged plaintiffs complaint, plaintiff filed amended complaints, defendant answered and filed affirmative defenses, and the parties engaged in discovery.
Trial was scheduled for October 6, 2005. On September 30, defendant moved to postpone the trial. The trial court granted the motion on October 3 and rescheduled the trial for mid-November. On October 7, defendant asked plaintiff to submit their dispute to arbitration. Plaintiff refused and, on October 12, defendant filed a petition to compel arbitration. Defendant’s petition came approximately eight months after plaintiff had filed his complaint and approximately five weeks before the rescheduled trial date. At no point before October 7 had defendant invoked its right to arbitration under the employment agreement.
The trial court denied defendant’s petition, reasoning that defendant had unduly delayed in seeking arbitration and thus waived its right to arbitrate the parties’ dispute. The court entered an order denying the petition on December 23, 2005, and the case proceeded to trial on January 17, 2006. The jury returned a verdict for plaintiff. The trial court entered a general judgment in plaintiffs favor on February 13, 2006. Defendant filed a timely notice of appeal from the general judgment and, in its opening brief on appeal, assigned error to the trial court’s order denying its petition to compel arbitration. Plaintiff responded that defendant had to file an interlocutory appeal pursuant to
In resolving defendant’s assignment of error, the Court of Appeals ruled initially that
In 2003, the Oregon legislature adopted the Revised Uniform Arbitration Act. Or Laws 2003, ch 598. Much of that act provides procedures for initiating and conducting
Defendant argues that sections 3 and 31 of the 2003 arbitration act establish that that act (more specifically, section 28 of that act) does not apply to this litigation. Defendant reasons that, because section 28 of that act (codified as
Section 3 of the 2003 arbitration act specifies which arbitration agreements are subject to the act. It provides:
“(1) Sections 1 to 30 of this 2003 Act govern an agreement to arbitrate made on or after the effective date of this 2003 Act [January 1, 2004],
“(2) Sections 1 to 30 of this 2003 Act govern an agreement to arbitrate made before the effective date of this 2003 Act if all the parties to the agreement or to the arbitration proceeding so agree in a record.
“(3) On or after September 1, 2004, sections 1 to 30 of this 2003 Act govern an agreement to arbitrate whenever made.”
Or Laws 2003, ch 598, § 3. Section 3 divides arbitration agreements into two categories. The first category consists of arbitration agreements made after the effective date of the act, January 1, 2004. The 2003 arbitration act governs all those agreements. Or Laws 2003, ch 598, § 3(1). The second category consists of arbitration agreements made before the effective date of the 2003 arbitration act and divides into two subcategories. Between January 1 and August 31, 2004, the 2003 arbitration act will not govern arbitration agreements made before the act’s effective date, unless the parties agree that the act applies. Or Laws 2003, ch 598, § 3(2). Beginning on September 1,2004, the 2003 arbitration act will govern all arbitration agreements, including those made before the act’s effective date. Or Laws 2003, ch 598, § 3(3).
In this case, the parties renewed their employment agreement, which included an agreement to arbitrate, before January 1, 2004. Section 3(1) accordingly does not apply; either section 3(2) or section 3(3) does. Defendant did not discharge plaintiff until 2005. Because the opportunity to arbitrate any dispute arising out of plaintiffs discharge did not arise until after September 1, 2004, section 3(3) of the 2003 arbitration act applies and provides that sections 1 to 30 of the act, including the section now codified as
The remaining question is whether the savings clause in section 31 of the act leads to a different conclusion. Section 31 provides:
“Sections 1 to 30 of this 2003 Act do not affect an action or proceeding commenced or right accrued before the effective date of this 2003 Act. Subject to section 3 of this2003 Act, an arbitration agreement made before the effective date of this 2003 Act, continues to be governed by [former] ORS 36.300 to 36.365 [(2001)] as though those sections were not repealed by section 5[7] of this 2003 Act.”
Defendant raises two arguments under that section. Defendant argues initially that, under the second sentence of section 31, the former arbitration statutes
(former
Defendant also relies on the first sentence of section 31, which provides that sections 1 to 30 of the 2003 arbitration act “do not affect an action or proceeding commenced or right accrued before [January 1, 2004].” In this case, no action or proceeding was commenced before January 1, 2004; so, that part of the first sentence does not advance defendant’s position. Additionally, defendant has identified no right that accrued to it before January 1,2004. Defendant did not file a petition to compel arbitration until October 2005, and the trial court did not deny defendant’s petition until December 2005. Defendant’s right to appeal did not arise (or “accrue” in statutory terms) until long after the effective date of the 2003 arbitration act.
Defendant argues, however, that some of plaintiffs rights accrued before January 1, 2004, and that, as a result, the former arbitration statutes apply. Plaintiff has not invoked the savings clause of the 2003 arbitration act, and we fail to see how defendant can invoke the savings clause to protect plaintiffs accrued rights when plaintiff declines to do so. We accordingly conclude that, under sections 3 and 31 of the 2003 arbitration act, section 28 of that act (now codified as
Having concluded that
Specifically, before 2003, a timely appeal from a final judgment gave an appellate court jurisdiction of the cause.
In 2003, the Oregon legislature provided for the first time that “[a]n appeal may be taken from [a]n order denying a petition to compel arbitration.” Or Laws 2003, ch 598, § 28. The legislature, however, did not specify what consequences would follow from declining to take an interlocutory appeal. Specifically, the legislature did not expressly state whether the failure to take an interlocutory appeal pursuant to
In addressing that issue, defendant argues that the legislature’s use of the word “may” implies permission to take an appeal and that, without some clear evidence of a contrary legislative intent, we should not assume that the legislature intended to require parties to pursue what is phrased only as a permissive appeal. Plaintiff, for his part, responds that an order denying a petition to compel arbitration must be appealed within 30 days and that, after the passage of
It is true, as defendant argues, that the phrase “may be taken” is permissive, but the legislature could have used that phrase in one of two ways. On the one hand, the legislature could have used “may,” as defendant argues, to signal its intent to permit an interlocutory appeal without forclosing a party’s right to raise the issue on a later appeal from a general judgment.
See Salsitz v. Kreiss,
198 111 2d 1,
The Court of Appeals found more guidance in the text of
Another aspect of the text points in the same direction.
Defendant does not identify any context that supports its position, other than the general right to appeal from the judgment, which we have already considered, and there is no legislative history that bears on this issue.
See State v. Gaines,
In discussing the bill, no one mentioned that, in adopting the Revised Uniform Arbitration Act, the legislature would authorize an interlocutory appeal as a matter of right, nor was there any discussion of what the consequences would be if a party failed to take an interlocutory appeal pursuant to the bill. Not only was there no discussion of that issue in the legislative history, but there is no commentary to that section of the Revised Uniform Arbitration Act that might shed light on what the legislature intended.
Cf. Datt v. Hill,
Considering the text and context of
Although we view the effect of
The decision of the Court of Appeals and the judgment of the circuit court are affirmed.
Notes
In its petition for review, defendant asked us to consider other issues that the Court of Appeals decided. We decline that request and limit review to the issue stated above and to a related issue that defendant raises.
“(1) An appeal may be taken from:
“(a) An order denying a petition to compel arbitration.
“(b) An order granting a petition to stay arbitration.
“* * * * *
“(2) An appeal under this section must be taken as provided in ORS chapter 19.”
The parties’ agreement provides that “[ajrbitration shall comply with and be governed by the provisions of the California Arbitration Act.” It may be that, under the parties’ choice-of-law provision, the California Arbitration Act, not Oregon’s 2003 arbitration act, would govern the procedures by which any arbitration between them would be conducted. It does not follow, however, that California law also governs the procedures for taking an appeal from an Oregon circuit court’s ruling, nor have the parties argued that it would.
See Equitable Life Assurance v. McKay,
When the plaintiff filed the action in
Industra /Matrix Joint Venture,
the 2001 version of the Oregon Arbitration Act was in effect and continued to apply to that action because of the savings provision in section 31 of the 2003 arbitration act.
See
The Oregon legislature had adopted the previous arbitration provisions in 1925.
Peter Eiewit v. Port of Portland,