Opinion
Thе subject of this appeal is application of the California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.) 1 to a project which received approval in 1988 without preparation of an environmental impact report (EIR) but which then lay dormant for nine years. The primary issue is whether the negative declaration given the project in 1988 should be deemed superseded by subsequent events, thereby requiring an EIR. The trial cоurt denied a petition for a writ of administrative mandamus upon concluding that municipal authorities did not abuse their discretion in determining that proposed modifications to the project did not entail new or more significant environmental impacts from those considered in 1988. The trial court further concluded that the negative declaration therefore remained valid. We conclude these conclusions have the suppоrt of substantial evidence and therefore affirm.
Background
The project at issue involves the demolition of an existing two-story parking structure located in downtown San Francisco, and its replacement
with a larger structure up to seven stories high (sixty-five feet). The existing structure, and an adjacent lot, could accommodate 125 cars; the completed project would have up to 330
For reasons not entirely clear from the record, no further action was taken and the project remained dormant until 1997, when officials of the city’s department of parking and traffic (DPT) began working on a modified' version of the project. The revised plan was for a 40-foot high structure with only about 200 parking stalls and no ground floor retail stores. San Francisco’s environmental review officer analyzed the 1988 negative declaration in light of more recent information and concluded that no material change of circumstances impaired the soundness or validity of the negative declaration. Based in part оn this review, the city’s planning commission approved a conditional use authorization for the revised project. At the same time the city’s zoning administrator granted the project a variance from rear yard set-aside requirements of the San Francisco Planning Code.
The requests for the variance and the conditional use authorization were opposed by Snarled Traffic Obstructs Progress (STOP), which describes itself as “an uni[n]corporated non-profit association comprised of property owners and residents who live and work in the immediate vicinity” of the project. STOP’S appeal was rejected by the board of appeals, which approved the variance as modified by DPT with a reconfiguration that would reduce adverse impacts to the light, air, and views of the occupants of two residential hotels adjacent to the project. Thereafter the city’s parking authority approved the final design for the project.
STOP then filed a petition for injunctive and declaratory relief, and for a writ of administrative mandamus. The general object of the petition was to overturn previous approvals of the project pending “subsequent and/or supplemental environmental review” of “new and legally adequate environmental documentation.” Upon consideration of the merits, the trial court denied all relief, a ruling embodied in the judgment from which STOP perfected this timely appeal.
Review
I
As a general rule, CEQA requires the preparation of an EIR whenever a public agency proposes to approve or carry out a project that may
have a “significant effect” on the environment. (§§ 21080, 21100, 21151; Guidelines, §§ 15002, 15063.) If, however, the public agency determines that the project will not hаve a significant environmental impact, it can issue a negative declaration to that effect and forego an EIR. (§§ 21064, 21080, subd. (c); Guidelines, §§ 15063, 15064, 15070.) In an obvious sense, an EIR and a negative declaration are the two sides of the same coin, the either/or options available to a public agency considering a project. Again, as a general rule, once a negative declaration is issued or an EIR is completed, that decision is protected by concerns for finality and presumptive correctness. (§ 21167.2;
Laurel Heights Improvement Assn.
v.
Regents of University of California
(1993)
“(a) When an EIR has been certified or a negative declaration adopted for a project, no subsequent EIR shall be prepared for that project unless the lead agency determines, on the basis of substantial evidence in the light of the whole record, one or more of the following:
“(1) Substantial changes are proposed in the project which will require major revisions of the previous EIR or negative declaration due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects;
“(2) Substantial changes occur with respect to the circumstances under which the project is undertaken which will require major revisions of the previous EIR or negative declaration due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects; or
“(3) New information of substantial importance, which was not known and could not have been known with the exercise оf reasonable diligence at the time the previous EIR was certified as complete or the negative declaration was adopted, shows any of the following:
“(A) The project will have one or more significant effects not discussed in the previous EIR or negative declaration;
“(B) Significant effects previously examined will be substantially more severe than shown in the previous EIR;
“(C) Mitigation measures or alternatives previously fоund not to be feasible would in fact be feasible and would substantially reduce one or more significant effects of the project, but the project proponents decline to adopt the mitigation measure or alternative;
“(b) If changes to a project or its circumstances occur or new information becomes available after adoption of a negative declaration, the lead agency shаll prepare a subsequent EIR if required under subsection (a). Otherwise the lead agency shall determine whether to prepare a subsequent negative declaration, an addendum, or no further documentation. . . .” 3
The issue for us, as for the trial court, is whether there is substantial evidence to support the determination that the proposed modifications for the project did not require either changes in the 1988 negative declarаtion or preparation of an EIR. (E.g., §§ 21168, 21168.5;
A Local & Regional Monitor v. City of Los Angeles
(1993)
We have visited this subject before. In
Benton v. Board of Supervisors, supra,
Benton
is of considerable assistance in narrowing our inquiry. First of all, the basis for reversing an initial environmental review (i.e., the decision to adopt a negative declaration or to prepare аn EIR) because there is a “fair argument” that a proposed project may have a
The initial approval was to replace a parking structure with a bigger parking structure. The modified version was still a parking structure but one more modest in scope; it would be less tall and with a smaller capacity than originally proposed. The surrounding area was described as “high-density neighborhood-commercial” in 1988; the city’s environmental review officer reported in 1997 that “the subject site and its surrounding area have not changed substantially since 1988, either in terms of land uses, intensity of use, or physical development.” That officer also concluded that “no physical or environmental characteristics of the modified project proposal and no changes in circumstancеs in the site vicinity would change any of the conclusions of the original Negative Declaration.” These circumstances, and the environmental review officer’s report, constitute substantial evidence for the conclusion that the revised proposal did not involve “new significant environmental effects or a substantial increase in the severity of previously identified significant effects” within the meaning of Guidelines section 15162, subdivision (a)(1) and (2). 5
STOP argues that the modified version of the project has a larger “footprint,” that is to say, that it will occupy more of the total space of the two lots than would the
This reasoning will also dispatch STOP’S contention that the increased “footprint” of the revised project will have a significant impact on the residents of the two residential hotels adjacent to the project site, specifiсally, the residents’ light, air, and views would be impeded if not obliterated if the parking structure is built according to the revised plans. There is no suggestion that these hotels were constructed after 1988. They would therefore have been considered in the process culminating in the negative declaration of that year. As just shown, there was no firm commitment at that time to a particular configuration of the project. The revised project proposal would thus not necessarily entail new and negative aesthetic impacts for the hotel residents. Moreover, the trial court found that these “potential impacts do not rise to the level of significance” because they were “mitigated by the project sponsor’s modification of the project.” The zoning administrator described this modification as follows: “As a result of negotiations with adjacent property owners, plans have been revised to establish a setback of 16 feet by 26.75 ... at the second level, and 16 feet by 31.75 feet at the third and fourth levels. This staggered setback provides an expanding ‘light well’ for the residential levels of the adjacent building[s]. . . . [¶] This revision . . . has the support or acquiescence of the affected property owners . ...” A letter from a parking authority director was to the same effect. The zoning administrator told the board of appeals that these property owners “also represent the occupants of the properties]” and that this latest revision would further reduce the number of parking spaces in the project. The executive director of the DPT also told the board of appeals that “The neighbors directly affected, both residents and owners, are in favor of the project.” Others speaking to the boаrd also conveyed the same general message. It may also be significant that after the “light well” revision was made, not a single resident of the neighboring hotels spoke against the project before the board of appeals. Taken in its entirety, all of this amounts to substantial evidence in support of the trial court’s refusal to issue the writ.
STOP’S only remaining contention is that exemption from the rear yard set-aside requirement should have been sought in the form of a waiver under section 134 of the city’s planning code, instead of the variance obtained under section 305 of the same code. Having looked at both statutes, we
discern in the former nothing like jurisdictional exclusivity. We agree with the trial court that these statutes “are two different mechanisms for reaching the same result.” In
Benton
we noted that agreement with an appellate contention “would constitute a triumph of form over substance.”
(Benton
v.
Board of Supervisors, supra,
The judgment is affirmed.
Reardon, J., and Sepulveda, J., concurred.
A petition for a rehearing was denied September 23, 1999, and appellant’s petition for review by the Supreme Court was denied November 23, 1999.
Notes
Statutory references are to this code unless otherwise indicated. References to “Guidelines” are to the regulatory guidelines which implement CEQA (Cal. Code Regs., tit. 14, § 15000 et seq.).
STOP appears to imply that the 1988 negative declaration was somehow defective or inadequate because it employed an “Environmental Evaluation Checklist.” If this was the sole basis for the negative declaration, it might be vulnerable; such a “bare bones” approach will not satisfy CEQA. (See
Sundstrom
v.
County of Mendocino
(1988)
The enabling authority for Guidelines section 15162 is section 21166, which provides in pertinent part: “When an environmental impact report has been prepared for a project pursuant to this division, no subsequent or supplemental environmental impact report shall be required . . . unless one or more of the following events occurs: [¶] (a) Substantial changes are proposed in the project which will require major revisions of the environmental impact report. [¶] (b) Substantial changes occur with respect to the circumstances under which the project is being undertaken which will require major revisions in the environmental impact report, [¶] (c) New information, which was not known and could not have been known at the time the environmental impact report was certified as complete, becomes available.”
In light of our limited function, authorities cited by STOP in which a reviewing court found substantial evidence supported an agency decision to require an EIR (e.g.,
Security Environmental Systems, Inc.
v.
South Coast Air Quality Management Dist.
(1991)
An entirely different result might be required if instead of reducing the the proposed project’s size the revised proposal had increased it. (Cf.
Concerned. Citizens of Costa Mesa, Inc.
v.
32nd Dist. Agricultural Assn.
(1986)
