55 Ct. Cl. 386 | Ct. Cl. | 1920
delivered the opinion of the court:
The plaintiff entered into a contract with the United States to construct a pier, causeway, and inner wharf at the Charleston Navy Yard. A part of the work ■ consisted in the sinking of cylinders to be filled with concrete, for which borings had been made to determine the depth to which the cylinders or caissons would be sunk to reach the marl or firm clay in or upon which they were to rest. The results of these borings were shown to bidders, along with the plans and specifications.
After the contract was made it was discovered that the depth of the marl was not uniform and that it dipped abruptly. This condition rendered it desirable to more accurately determine the average depths to which the cylinders would be sunk and a board was convened for that purpose, which found that the cylinders would have to go deeper
Later it was determined to be necessary, on account of the bottom formation and its dip, to sink the caissons or cylinders deeper than the supplemental contract required, and another board was convened to ascertain this additional depth and to fix the amount of compensation therefor. This board reported that the depth would be 5.1 feet additional to that specified in the- supplemental contract, and, after recommending certain omissions from the contract work, reported that the net amount to be paid plaintiff for the cylinders carried to the proposed new depth would be $13,131.05. A controversy arose between the parties over the sum that should be paid, and the plaintiff declined to sign a proffered supplemental contract providing for the additional work for the sum above stated. It expressed a willingness, however, to do the work, accept the sum named as part payment, and leave the question of amount open for future adjustment. The plaintiff was notified that the department would treat the matter as “ a change order ” and that it could proceed with the work without a supplemental contract. This the plaintiff did, and the work was completed in June, 1916. When the matters came on for final settlement the defendant’s officers in charge contended that the plaintiff should accept the sum of $13,131.05 as the proper compensation for the additional work, and should be charged with $3,275 as liquidated damages under the terms of the contract, and they insisted .that the plaintiff execute a final release such as is contemplated by the contract.
There is nothing in the case calling for an application of the principles decided in the Christie Case, 237 U. S., 234, Hollerbach Case, 233 U. S., 165, Atlantic Dredging Co. Case, 53 C. Cls., 490, or similar cases. No misrepresentation was made nor information withheld. The borings as made were submitted and their accuracy is not disputed. They did not show that the marl broke or dipped abruptly at or near the places where the cylinders were to be sunk, and there is nothing to show that this information was in the possession of the officer in charge who made the contract or of the officers or agents who made the borings. As has been stated, new borings were made and the results were covered into a supplemental contract executed by the parties. The provision in the latter that the additional depth would not exceed 5.1 feet was evidently intended for the contractor’s
A second question reserved in the release was whether the plaintiff was chargeable with liquidated damages. We think clearly not. The contract period for completion had been extended to January 31, T916. When that time had expired, the question of the new additional depth of 5.1 feet had not been determined by the board, nor the amount of compensation allowable for it. No new or supplemental agreement was executed, but in April the plaintiff was directed to proceed as upon a “change order.” Upon what theory the plaintiff was chargeable -with liquidated damages for delay in completing the work that was not even included' in the contract, or the supplement thereto, is not made plain. The plaintiff was duly authorized to do this work, and the time for doing it was not agreed upon or covered by former agreements. The plaintiff should recover the amount deducted as liquidated damages, as shown by Finding X.
Judgment for plaintiff in the sum of $30,883.95. And it is so ordered.