125 P. 412 | Utah | 1912
Lead Opinion
The respondent, William S. Smoot, for himself and as-the-assignee of other lien claimants, commenced this action to foreclose certain mechanics’ liens. Bay'A. Boss filed a cross-complaint, but, for the purposes of this opinion, he will be treated the same as though he were an assignee of the ret-spondent Smoot. The district court found the issues in favor of the lien claimants and ordered that the premises against which the liens were claimed bei sold.
The controlling facts, stated as briefly as possible, are: That Checketts & Bradeson, as copartners, and hereafter
One of the principal questions presented for determination arose out of the following circumstances, namely:
It is now insisted by the attorney for the association that the court erred in its findings as aforesaid. From the facts as found, which, in our judgment, are sustained by the evidence, the payments relied on by the association do not constitute an accord and satisfaction, nor did the transaction between the claimants and the officers of the association amount to a compromise and settlement of unliquidated or disputed claims. There was no' dispute whatever between the officers of the association and the labor claimants with respect to the amount that was due to any one of them from the contractors. Neither was there any question with regard to whether the claimants, as a matter of law, were entitled to file liens against the buildings and structures of the association for the full amount of their claims. The mere fact that, under such circumstances, the claimants executed receipts in full when they had in fact received only about one-third of the amounts then due them from the contractors for labor is of slight, if any, importance. As to whether the receipt of a less sum
2 When it is claimed that the payment by the debtor of a sum of money less than is due and owing to the creditor is a payment in full discharge of the entire amount due, a-receipt acknowledging full payment standing alone is not controlling. If such a payment is based upon a sufficient independent consideration, or upon a compromise of a disputed or an unliquidated claim, and under such circumstances the lesser sum is received as payment in discharge of the larger one, the payment is binding upon the creditor. (Barnum, v. Green, 13 Colo. App. 258, 259, 57 Pac. 757; Johnson v. Simmons, 76 Minn. 34, 78 N. W. 863; Canadian Fed. Co. v. McShane, 80 Neb. 551, 114 N. W. 594, 14 L. R A. (N. S.) 443, 127 Am. St. Rep. 791; Farmers’ & Mechanics’ Life Ass’n v. Caine, 224 Ill. 599, 79 N. E. 956; Prudential Ins. Co. v. Cottongham, 103 Md. 319, 63 Atl. 359; Ness v. Minnesota & Colo. Co., 87 Minn. 413, 92 N. W. 333.)
In the foregoing eases, the dictrine of what constitutes a sufficient consideration for the discharge of a debt then due by the payment of an amount less than the whole debt is fully illustrated. Under the authority of every one of the cases referred to above, with many others which might be.' cited, the payment in the case at bar did not amount to either a compromise of a disputed claim or an accord and satisfaction.
As we have seen, the contract price was not payable unless and until the structures contracted to be erected were completed. We have also called attention to the fact that Check-etts & Bradeson, the contractors, never completed their contract, but abandoned the structures, before completing them. The provisions of section 1374, supra, therefore became ap
It is further asserted that the court erred in allowing attorney’s fees. Comp. Laws 1907, see. 1400, expressly provides that, in actions to foreclose mechanic’s liens, the successful party shall be entitled to- recover an attorney’s fee to be fixed by the court not to1 exceed twenty five dollars. The amount allowed by the court not being in excess of the amount permitted by statute, and no other error being claimed in this regard, the assignment must be overruled.
“In some jurisdictions it is held that an inchoate mechanic’s lien may he assigned so as to invest the assignee with the right to perfect and enforce the same.”
In support of the foregoing statement, cases are cited from Alabama, Colorado, Florida, Iowa, Kansas, Maine, Massachusetts, Michigan, Minnesota, Mississippi, Rhode Island, and South Dakota. See, also, Roisot on Mechanics’ Liens, sec. 10; Phillips on Mechanics’ Liens, secs. 54, 54a, 55.
We are aware that the Supreme Court of California, in Mills v. La Verne Land C.O., 97 Cal. 254, 32 Pac. 169, 33 Am. St. Rep. 168, has arrived at a contrary conclusion to that stated in Cyc. The ease, however, is, to some extent at least, based upon a California statute. From an examination of the cases cited by the Supreme Court of California, it develops that some of the decisions relied on by the California Supreme Court have since then been modified, if not overruled. Iowa in early cases held with California, and in ai later decision (Peatman v. Centerville Light, etc. Co., 105
It is further asserted that the district court erred in allowing a lien for labor for which the statute does not authorize a lien. The record1 discloses that one of the assignors performed a few days’ labor for which there may be some doubt whether the statute gives a lien or not. In view, however, that the construction of the statute in this regard is of grave importance to all lien claimants, and thaft counsel for neither side has thoroughly discussed the question nor cited any authorities, and for the further reason that the amount involved is small and that, in view of the finding of the court, the association is not injured by the court’s ruling, we have less hesitancy than we otherwise would have in refraining from passing upon the question at this time.
The assignment that one of the assignees had been paid by the contractors must likewise fail. The agreement between the contractors and the assignor amounted to no more than an agreement that the assignor should be paid' in a particular manner. The agreement, however, was not fulfilled by the contractors, and the assignor received no pay for his labor. This left the question precisely the same as though the assignor had been promised payment in cash by the contractors, but they did not redeem their promise.
The judgment is affirmed, with costs to respondent.
Dissenting Opinion
(dissenting.)
I dissent. The evidence shows: (1) The fair association made two written contracts with Checketts & Bradeson to construct and repair buildings, etc., upon an agreed price of $2,839. It also entered into another agreement with them for extras at an agreed price of $235.75. That made a total contract price of $3,074.75. It paid to them and for their use and benefit $2,935.50. It paid out $146.69 for labor and material to finish the contract. That was a total of $3,-083.19, or more than the contract price. In addition to
The agreement between the fair association and the plaintiff and his assignors and the giving of the receipts were testified to by the directors and officers of the fair association. The receipts themselves- were put in evidence. Their execution and delivery are undisputed. They are not assailed
The testimony of the officers and directors is also corroborated by that of Ross, the counterclaimant, a witness for the plaintiff. He testified that he was present at the conferences between the plaintiff and his assignors and the fair association and when the receipts were signed, and the money paid by the association to himself and to the plaintiff and his assignors, and that the .association claim'ed that it did not have money enough to pay “us in full.”, Ha further testified: “We had been talking about filing ai mechanic’s lien. While we were talking, they called our attention to several things in the contract which hadn’t been completed. At first the association refused to pay anything, and they refused to recognize any liability on their part towards us, and we stated that we had a right to put a mechanic’s lien, and if no settlement was made we would do so, and they told us, if we would make some concession and agree not to file a lien, that they would pay us some portion of our claim, and we should make them a receipt in full. We agreed to this later on. They told us no settlement would be made unless we came to that agreement and we finally did so, accepting the money and signing the receipts, and they told us then that this settlement with the association would not release Checketts & Bradeson from the balance of our claims.” He further testified that the amount so agreed upon was one-third of their claims, and that, in accordance with the agreement, that amount was paid, and the receipts given.
I think the agreement and the payment of the money thereunder, and the giving of the receipts, constituted a settlement between the fair association and the claimants. It was so pleaded in defense; It was not assailed on the ground of fraud, misrepresentation, or mistake, or that it'was not fairly 'entered into, nor is there any evidence to dispute the fact that the agreement was made and that the terms thereof were as testified to by Ross and the officers of the association. I also think that the agreement was founded upon a good consideration. This is not a. case where one party owes another an undisputed and liquidated amount which was settled for less upon no independent or other consideration. Here the defaulting contractors were primarily liable to the claimants. The fair association was not at all liable to them. Its property upon which the work was done was secondarily and only conditionally liable. That liability was not in excess of the contract price nor beyond the moneys in the hands of the association and unpaid to the contractors.
The great weight of the evidence shows that the fair association had paid the contractors the full amount of the1 con
I think the judgment as.against the fair association wrong, and therefore dissent.