92 Ark. 6 | Ark. | 1909
This is an action instituted by the plaintiff, L. E. Weatherford, against defendants Smith and others as partners, under the firm name of C. H. Smith Tie & Timber Company, on account for railroad ties and stave bolts and piling manufactured by plaintiff for defendants and alleged to have been delivered to them. The amount of balance alleged to be due on the account is $2,398.34, and on the trial below before a jury the plaintiff recovered $1,800.
It is alleged in the complaint that in July, 1905, the plaintiff was employed by defendants to make ties, stave bolts and piling out of timber which had been purchased by him from them; that for the first lot of ties he was to receive 23 cents each, and for subsequent lots the current prices at the time of the respective deliveries. The account exhibited with the complaint shows a debit of $12,032.21, with payments thereon aggregating $9,-633.87, leaving an unpaid balance of $2,398.34, the amount sued for; and it shows an aggregate of 35,930 ties claimed to have been delivered by plaintiff.
The defendants in their answer alleged that they had paid the plaintiff for 35,460 ties, but that they have received only 33,-024, leaving 2,436 ties which they had paid for but which had never been delivered. They further alleged that they had had a final settlement with plaintiff, and that plaintiff had given a receipt-acknowledging payment in full. The case was tried before a jury on conflicting evidence, and the result, as before stated, was a verdict and judgment for plaintiff in -the sum of $1,800.
It appears from the evidence that -the defendants were engaged in the business of supplying ties to a railroad company, and owned timber on two tracts of land. They engaged plaintiff to make ties and deliver them on the right of way of the railroad company, and agreed to let him have the timber at the prices they had paid for it; to purchase other tracts of timber for him and to charge the price thereof to him as an advance on ties to be delivered, as well as to advance him money to pay for cutting and hauling the ties. Afterwards they agreed also to take stave bolts and piling. The only point of difference between the parties, as far as concerns the contract, was as to the price to be paid for the ties. The plaintiff testified that he was to receive the ruling current prices for ties after the first lot delivered, for which he was "to receive 23 cents each; and the defendants contended that they were only to pay 23 cents each for all ties delivered.
The defendants admitted that during the progress of the transaction between them they agreed to increase the price of ties above the stipulated sum of 23 cents, but that this was a bonus or gratuity which they were not required under the original contract to pay. Both sides introduced testimony in support of their respective contentions. They also testified in support of their respective contentions with reference to the alleged settlement in full. One of the defendants testifies that he made a compromise and final settlement with the plaintiff and paid him $150, which he said the plaintiff accepted in full satisfaction of all his demands ; that the payment was made by two checks, one for $100 and the other for $50, the latter check containing in writing on its face the words: “Settlement in full for all lands and ties cut up to this date;” and that the plaintiff accepted the check with this written on its face and collected the same. The plaintiff denied' that the amount was paid in full settlement, and testified that the words above quoted were not on the check when it passed through his hands.
The defendant introduced in evidence the check containing the words quoted above. Numerous errors of the court are assigned, which will be discussed in the order presented in argument.
Doubtless, the defendants intended by this instruction to have the law declared .to be that if, under the original contract- with plaintiff, they were only to pay 23 cents each for all the ties delivered, they were not, without a new consideration, bound by their agreements to increase the price to 30 cents per tie. But the instruction falls far short of expressing this idea with sufficient clearness for jurors of ordinary intelligence to understand it. It entirely ignored the plaintiff’s contention that the price of ties furnished from time to time was to be increased to the prevailing or current price at the time of the respective deliveries; and it was calculated to mislead the jury into believing that, even though they accepted the plaintiff’s contention as true, if the prices were voluntarily increased by the defendants, the increased prices could not be recovered. The words “voluntarily gave plaintiff a bonus amounting in all to thirty cents” do not clearly express the idea intended to be conveyed, and might have had a misleading effect upon the minds of .the jurors.
The meaning of the latter part of the instruction is also far from being clear. It says that the plaintiff “cannot recover in law for said thirty cents on any ties on which same was not voluntarily given.” A party cannot complain of the refusal of a court to give an instruction unless it is correct in every particular. The court no doubt would have given an instruction on the subject if a correct one had been requested; for the law as contended for by defendant’s counsel was declared in another instruction. After setting forth these issues in the case, the court gave this to the jury:
“No. 10. You are instructed that the burden is on the plaintiff to show that he had a contract with defendant by- which defendant was to pay the prevailing market price for ties; that he furnished ties under that contract. If .you so find, your verdict will be for -the plaintiff in whatever sum to be due him by a preponderance of the evidence.”
With this instruction before them, the jury were properly advised as to the law on £his feature of the case.
Instruction No. i was erroneous in several particulars. In the first place, i-t was not -correct to say that the date each tie was made marked the time for fixing the price to be paid. The contract called for the delivery of the ties on the railroad right of way; and if -the plaintiff correctly stated the terms of the contract, he was entitled to the market value at that time. He could not rightfully withhold delivery after the making of the ties to await an increase in prices; but he was -entitled to a reasonable time in which to make his deliveries, and he was entitled to any increase in prices occurring during that time. What constituted a reasonable time under the peculiar -circumstances of the case was a question for the jury to determine.
Nor was it -correct to instruct the jury, as requested, that, if the plaintiff failed to show the date of making the ties, he could only recover the minimum price under the contract. The plaintiff was only bound to show the date of -delivery and the ruling prices at the time thereof. It devolved on ,fhe defendants to prove negligent or wrongful delay in -delivering the ties after they were manufactured.
The omitted portion of the twelfth instruction above quoted was -also erroneous in saying that th-e plaintiff was not entitled to recover more than the minimum -price if he failed to prove accurately the true date of making the ties. The instruction would have -cut the plaintiff off from a recovery of more than the minimum price for any -of the ties, notwithstanding he proved the increase in price, merely because he could not show the date of making the ties.
The part in italics was objected to on the alleged ground that there was no evidence of business transacted between the parties after the date of the alleged settlement. If it be conceded that there was no such evidence, we fail to see how the instruction could have had a prejudicial effect. The jury could not, by the abstract instruction, have been misled into disregarding the settlement. It has often been held by this court that it is prejudicial error to give an abstract instruction which might be construed as an intimation from the court that there was some evidence on that issue when there was in fact none. St. Louis & S. F. Rd. Co. v. Townsend, 69 Ark. 380; St. Louis, I. M. & S. Ry. Co. v. Woodward, 70 Ark. 441; Harris Lbr. Co. v. Morris, 80 Ark. 260; Fordyce v. Key, 74 Ark. 19; Ark. & La. Ry. Co. v. Stroude, 77 Ark. 109.
But the rule thus announced is not an, inflexible one; and, where it can be seen that no prejudice could have resulted from the giving of such an instruction, the verdict .will not be set aside. It is only where it can be seen that prejudice might have resulted that a reversal follows. Miller v. Nuckolls, 77 Ark. 64; Jonesboro, L. C. & E. Rd. Co. v. Cable, 89 Ark. 518.
The distinction will be found by a comparison of the cases above cited.
The court also gave the following instruction over the defendant’s objection: “14. The burden of proof is upon the defendant to show that such a final settlement was had between the parties, if any, must outweigh the evidence tending to show that he (no) such settlement was made.”
This instruction is not complete, and there is a manifest error in copying it into the transcript. Teamed counsel for the defendant, in their argument, have presented this instruction as having told the jury in substance that the burden of proof was on the defendant to show that a final séttlement had been made between the parties. They say that an instruction to that effect was erroneous, and in conflict with the principle announced in Decker v. Laws, 74 Ark. 286. We do not think so. The case above referred to was quite similar to the instant case. The defendant in that case, as in this one, claimed to have consummated a settlement in full with a check containing words acknowledging payment in full. But the plaintiff denied that the check contained those words when it passed through his hands. . In that state of the proof the court instructed that if the check contained those words when it was given and accepted, the burden was on the plaintiff to show that the check was not given and accepted as full payment; but that the burden of proof was on the defendant to show that those words were not contained at the time plaintiff accepted it. This court approved those instructions, and in the opinion said: “As appellants were claiming a special benefit from certain words in the $50 check, the burden was upon them to prove that Laws was bound by these words. The check was a special phase of the case introduced and relied upon by appellants, and it was correct to place the burden upon that particular question upon appellants. For Laws denied in his proof that the check contained any such words when he signed the check. There is nothing antagonistic or inconsistent in the two instructions. If Laws really signed the check with the words ‘in full payment of all demands’ in it when he signed, then the burden was upon him to show that these words were not intended as full payment, as they purported to be, as the court told the jury in instruction numbered 2. But, on the other hand, if the check did not have the words ‘in full of all demands’ when Laws signed same, then he was not bound by them, and the burden was upon appellants, in order to get the benefit of these words, to show that Laws signed the instrument containing them.”
And again the court said: “The.’words, ‘in full payment of all demands,’ being contested, the question as to when, by whom, and with what intent they were written was left to the jury upon the whole evidence, with the burden upon him who produced and claimed the benefit of the instrument to prove it, and the burden left with the plaintiff to establish his claim.”
So in the present case, having pleaded settlement in full, it devolved on the defendants to prove it. It also devolved on them to .prove that the check contained words acknowledging acceptance of the amount in full satisfaction when it passed through' plaintiff’s hands, that being denied by the plaintiff. It was an essential part of their defense of payment. They would have been entitled to an instruction, as in Decker v. Laws, if they had requested one, to the effect that if the plaintiff accepted the check with these words in it, .then the burden would be on him to show that the check was not accepted as full .payment. But the defendants did not ask for such an instruction, and cannot now complain because none was given.
The part in italics is objected to on the álleged ground that it incorrectly stated the defendants’ admission to be that all of the timber except 2,436 cross ties was delivered, when in fact they . only admitted that they had received the ties in the woods, but that the same were not hauled to the stipulated place or delivered, and that they had to do, the hauling at their own expense. Their answer on this point reads as follows:. “The defendants deny that they received 35,930, but admit that they received 33,024, and claim that they paid for the hauling of the same and for the making of 35,4602 leaving a balance due to the tie company of 2,436 ties paid for by defendants but never delivered by plaintiff.”
We think the court was correct in its interpretation of the defendant’s admission. The acceptance of the ties in the woods amounted to a waiver of delivery by the plaintiff at the place named in the contract. But they were entitled to credit for the additional expense of hauling. This instruction did not deprive them of the right to claim credit for the expense of hauling. If they feared such a prejudicial effect on the minds of the jury, they should have asked for a specific instruction saying that the expense of hauling the ties to the stipulated place of delivery should be deducted from the amount which would have been due the plaintiff had the ties been delivered at the agreed place.
Judgment affirmed.