98 Cal. 210 | Cal. | 1893
— This is an appeal from a final judgment entered in favor of appellant, who was plaintiff in the court below, decreeing the plaintiff to be the owner of certain land, and enjoining defendants from entering upon or interfering therewith.
The cause comes up on the judgment-roll, and the sole question involved relates to the right of appellant to damages in addition to the relief afforded him.
In November, 1866, the Los Angeles and Ostrich Farm Railway Company, a corporation, procured by ordinance of the council of the city of Los Angeles a franchise °to construct a street railroad from point A, near the center of the city, to point
The Los Angeles County Bail way Company, on the third day of October, 1887, entered into an agreement with the appellant and other donors, by which in consideration of the paynnent of the notes of appellant and others, “and in further consideration of the grants of right of way made by the said parties of the second part,” it agreed to do certain things, and among them that the conditions of the notes as to constructing the road should be carried out, except as to time, and it was to be relieved from the consequences of the delay. The note of the appellant, as well as those of the others due at four months,
On the eighth day of September, 1887, the three corporations, hereinbefore named, were duly consolidated under the name of the Los Angeles and Pacific Railway Company.^ Each of the three corporations, according to the findings of the court, assumed all the obligations of Wicks, and the second and third corporation, the obligations of their predecessor's to plaintiff, including the obligation on account of damages in the premises.
-Appellant never gave any license or granted any right of way over his laud, except such license as may be inferred from the language used in his promissory note or agreement of December, 1886.
The excavations and embankments on appellant’s land, made by Wicks and the Los Angeles and Ostrich Farm Railway Company, detracted from the value thereof in the sum of eight thousand dollars, and such damage or deterioration can be obviated and the value of the land restored only by filling up the excavations and spreading out the embankments, to effect which will costsix thousand dollars. Had the road been constructed from point A to point C, this damage would have been compensated by the increased value of the land and by the convenience afforded thereby in communication with the center of the city. Appellant, according to the findings, has suffered damages in all aggregating eight thousand dollars. Respondent, as well as its predecessors in interest, refused to construct the road from point A te point B.
The appeal being upon the judgment-roll, we must regard the findings as conclusive in favor of the assumption that the defendant is in the position of and subject to all the liabilities which would have attached to its predecessor, the Los Angeles and Ostrich Farm Railway Company and its agent Wicks, had that corporation remained the owner of the property and failed to execute the contract. To put it more broadly, the defendant has assumed the responsibility of all its predecessors in interest.
Was the refusal of defendant to construct its road from point A to point B, thus making a harmonious whole of its line from A to C, whereby plaintiff would have been compensated by the increased value of his land for the detriment caused thereto by the cuts and fills upon it, the proximate and efficient cause of the injury complained of? Respondent contends that when the construction was completed across appellant’s land, the act was legal and proper under an implied license of a contract for its construction; that the injury to appellant was then complete, and as the breach of the contract did not occur until afterward in point of time, until respondent refused to complete the road, the damage cannot be said to have be'en caused by the breach.
Suppose A, a farmer and the owner of broad acres in need of irrigation, contracts with B, the sole proprietor of water which can be used for such purpose, whereby the latter agrees with the former to construct an irrigating ditch from the center of his land to the source of supply, through which to conduct water. He constructs the ditch across the laud of A, and then refuses to complete the contract, and in consequence the ditch is a detriment to the land and must be filled up to restore it to its primary condition. In such a case is not the expense a direct and immediate effect of the breach of the contract? A contracts
A mechanic agrees to make and deliver, at a time specified, a carriage from materials furnished by his customer. Through ignorance or by design he ruins the materials and fails to deliver the vehicle. The value of the materials furnished is an element in the estimate of damages, though the breach occurred upon the subsequent failure to deliver.
In justice to counsel for respondent, it must be said, however, that their objection to the recovery of the damages by appellant, while it involves the consideration above referred to, goes a step further and may be thus stated : —
1. The original contract with appellant was to construct the railroad from point A to point C. Wicks and his principal built it from B to C, and caused all the injury to appellant’s laud now complained of; for which, but for the consent of the owner, an action might have been at once sustained.
2. The contract of October 3, 1887, by the Los Angeles County Railway Company, being subsequent to the injury, was in fact and effect a contract to finish the road, or, in other words, to construct it from A to B, and therefore a breach of this last contract cannot be made the basis of the damages demanded.
This position on its face seems entirely logical; but when we refer to the contract of October 3, 1887, and to the finding it appears: —
1. That by the contract the Los Angeles County Railway Company expressly agreed to perform all the conditions contained in the notes to appellant and others, as well as those of a bond given by Wicks and others for constructing the road, except that it was not to be held liable for the delay which had occurred in the completion of the work.
2. When appellant thereupon paid his note the new company gave him an agreement binding itself to perform the obligations incurred by the contract of October 3, 1887.
3. The defendant is a corporation resulting from a consolida*216 tion with the two corporations which preceded it in interest, and hereinbefore mentioned.
4. The defendant, according to the pleadings found by the court to be true, assumed all the obligations of its predecessors and of M. L. Wicks to the appellant, “including all obligations on account of damages to the plaintiff (appellant) on account of the premises.”
Two or more railroad corporations may legally consolidate under the provisions of section 473 of the Civil Code. True, such consolidation does not relieve either of the consolidating corporations from its liabilities. The consolidated corporation may, however, assume and make itself liable for the antecedent liabilities of such consolidating companies (Spelling on Corporations, sec. 108, and cases cited), and while such agreement does not without their assent bind creditors, yet suit brought by a creditor upon a demand so assumed against the corporation which has agreed to pay is of itself sufficient evidence of acceptance of the new debtor in lieu of the old. (Morgan v. Overman S. M. Co., 37 Cal. 534.) Viewed from this stand-point, and the case is presented in a different aspect from that assumed by counsel for respondent. The present defendant has absorbed into its corporate entity and stands as the embodiment of all the factors in the problem— is the representative of all the corporations. Coupled with this it has in express terms succeeded to all their responsibilities to appellant. Having of its own volition assumed this position, it cannot be permitted to divide up the obligation and thereby reduce the responsibility. It must be held to be liable precisely as though it had been the sole actor from the outset. The court below found, as before stated, that the damage to appellant’s land can only be obviated by filling up the excavations and spreading out the embankments, to effect which would cost not less than six thousand dollars. For this amount appellant was entitled to judgment.
The action, so far as it sounds in damages, is not for a tort in which plaintiff recovers for the injury done to his land as such, but upon a contract; and the question is, what is the condition of plaintiff as a direct consequence of the breach, compared with what he would have occupied had the contract been carried out?
Without determining the question whether or not in an action upon a contract a recovery can in any case be had for such cause, it is sufficient to say that if it can, that being in the nature of special damage, it can only be had upon a more full and specific statement of facts than appears in the complaint in this cause.
I am of opinion the judgment should be reversed, and the court below directed to enter judgment in favor of the appellant for six thousand dollars, in addition to the relief heretofore granted.
Haynes, C., and Vanclief, 0., concurred.
For the reasons given in the foregoing opinion the judgment is reversed and the court below directed to enter judgment in favor of the appellant for six thousand dollars, in addition to the relief heretofore granted.
McFarland, J., De Haven, J., Garoutte, J.
Hearing in Bank denied.