Appeal, No. 214 | Pa. | Mar 20, 1893

Opinion by

Mr. Justice Mitchell,

A written contract for building the house was made by defendant and the contractor Hill in April, 1890, and presumably destroyed, though the defendant, the only witness examined on that point, does not testify to the fact from his own knowledge. Then a supplementary contract was made, which was the one in evidence, under which defendant says the work was done. He says also that this new agreement was made about May 20, and that the original was destroyed because the contractor had made no progress on the work. Plaintiff testified that he made his contract, to deliver materials, with Hill in the early part of April, prior therefore to the destruction of the first contract between Hill and the defendant. It was held in Willey v. Topping, 146 Pa. 427" court="None" date_filed="1892-01-04" href="https://app.midpage.ai/document/willey-v-topping-6354075?utm_source=webapp" opinion_id="6354075">146 Pa. 427, and Cook v. Murphy, 150 Pa. 41" court="Pa." date_filed="1892-07-13" href="https://app.midpage.ai/document/cook-v-murphy-6240894?utm_source=webapp" opinion_id="6240894">150 Pa. 41, that a subcontractor is not bound by an alteration in the principal contract made without notice to him during the progress of the work. How far this principle may apply to the case of the cancellation of the original contract before work is begun *525under it, and the substitution of a new one nearly identical in terms but containing a new provision materially affecting the rights of subcontractors is an important question, which however we are not called upon at present to decide. The defendant testified that the new contract was made about May 20, while the plaintiffs alleged it was not made until several months later. Plaintiffs began to deliver materials on June 27, and the date of the new contract under which defendant alleged that the work was done, was therefore vital as regards this claim. When therefore plaintiff in rebuttal offered to prove that the old contract was in force up to August, and the new one was not made till then, the evidence was clearly competent and material. If true, then under Willey v. Topping and Cook v. Murphy, supra, the new contract not having been made until after plaintiff had begun to furnish materials did not affect his claim at all. The evidence should therefore have been received, and appellant’s second assignment of error must be sustained.

This result would probably be conceded by the learned judge below, and it is only just to him to say that he excluded the offer not on the ground that the new contract if made in August would be binding on plaintiffs, but on the ground that it was not proposed to show that the original contract was different from the one in evidence, in certain portions which he held to be conclusive against the right of a subcontractor to file a lien at all. In so holding he followed the apparent indication of Dersheimer v. Maloney, 143 Pa. 532" court="Pa." date_filed="1891-10-05" href="https://app.midpage.ai/document/dersheimer-v-maloney-6240491?utm_source=webapp" opinion_id="6240491">143 Pa. 532. The contract, in that case as in this, contained a clause that “ the owner will not in any manner be answerable or accountable for any loss or damage that shall or may happen to the said works, or any part or parts thereof respectively, or for any of the materials or other things used and employed in finishing and completing the said works.” But the other clauses in the two contracts, in connection with the foregoing, and bearing on its interpretation, are materially different. In Dersheimer v. Maloney, there was an additional provision that there should be no legal claims against the contractor from any source whatever for work or materials furnished, and it was on these two provisions taken together that the decision in that case was rested. The stipulation above quoted, as to the owner’s accountability for loss or *526damage to the works, or for materials, prima facie has no reference to liens, but to liability possibly arising from fire or accident or theft during the process of erection, and its meaning is not extended by the rest of the contract in the present case, but on the contrary would be restricted, if it were doubtful, by the express recognition, in the contract, of the right to file liens, by the stipulation, in clause 9, that before final payment the contractor shall furnish “ a full, complete and perfect release of all liens which may lie against the building on account of work done or materials furnished thereto. ” See Murphy v. Morton, 139 Pa. 345" court="Pa." date_filed="1891-01-05" href="https://app.midpage.ai/document/murphy-v-morton-6240219?utm_source=webapp" opinion_id="6240219">139 Pa. 345, and Moore v. Carter, 146 Pa. 492" court="None" date_filed="1892-01-04" href="https://app.midpage.ai/document/moore-v-carter-6354086?utm_source=webapp" opinion_id="6354086">146 Pa. 492. There is therefore a clear difference between the two cases. It must be said however that Dersheimer v. Maloney is not only on the border line, but that if read in the light of other and later cases, it is on the wrong side of the line and is virtually overruled. The whole subject has been discussed and the decisions authoritatively reviewed in Nice v. Walker, 31 W. N. 522, [153 Pa. 123" court="Pa." date_filed="1893-02-13" href="https://app.midpage.ai/document/nice-v-walker-6241261?utm_source=webapp" opinion_id="6241261">153 Pa. 123] in an opinion filed since the present case was argued, and intended to settle finally the questions involved.

We have not considered the effect of the supplementary clause at the end of the contract after the first signatures. Should the jury find that it was added after the plaintiffs had commenced the delivery of materials, then uuder the rule of Willey v. Topping and Cook v. Murphy, supra, it will drop out of the case. All we decide at present is that without this clause there is nothing on the face of the contract to prevent a subcontractor from filing a lien.

Judgment reversed and venire de novo awarded.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.