John E. SMITH, husband, and as Trustee of the Smith Family Trust; Mary Lou Smith, wife; Pretzer Land & Cattle, an Arizona corporation, Plaintiffs-Appellants, v. CENTRAL ARIZONA WATER CONSERVATION DISTRICT, a municipal corporation of the State of Arizona, Defendant-Appellee.
No. 03-16962.
United States Court of Appeals, Ninth Circuit.
Argued April 14, 2005. Submitted: Aug. 3, 2005. Filed: Aug. 10, 2005.
422 F.3d 1028
Stuart L. Somach, Sacramento, CA, for the defendant-appellee.
Before: HUG, THOMPSON, and RYMER, Circuit Judges.
John E. Smith, Mary Lou Smith, the Smith Family Trust, and the Pretzer Land and Cattle Company (“the landowners“) own land located within the Maricopa-Stanfield Irrigation and Drainage District and the Central Arizona Irrigation and Drainage District (“the irrigation districts“), respectively. Through a master contract and related subcontracts with the Central Arizona Water Conservation District (“Conservation District“) and the United States Department of the Interior, the irrigation districts receive and distribute water reclaimed from the Central Arizona Project (“the project“).
In anticipation of a legal settlement, the terms of which would alter the amount of water the irrigation districts receive from the project each year for distribution to landowners and other users within their respective districts, the landowners filed this civil action in Arizona state court against the Conservation District. The landowners sought declaratory relief to prevent modification of the existing contracts, claiming vested water rights pursuant to state and federal law, and pursuant to the terms of the project contracts. The Conservation District removed the action to federal court. The landowners moved the district court to abstain from exercising federal jurisdiction and to instead remand their action back to state court. The district court denied the landowners’ motion to abstain and remand. It then dismissed their complaint for failure to state a claim pursuant to
I.
Congress enacted the Reclamation Act of 1902, ch. 1093, 32 Stat. 388 (1902), to provide federal financing, construction, and operation of water storage and distribution projects throughout the western United States. Pursuant to the 1902 Act, Congress in 1968 enacted the Colorado River Basin Project Act,
To this end, the Arizona legislature created the Conservation District. See
State law additionally authorized the Conservation District to enter into subcontracts with irrigation districts for the delivery of project water.
The landowners each entered into memoranda of understanding and water service agreements with their respective irrigation districts. These agreements provide that the relevant irrigation district will deliver project water for irrigation purposes to the landowners, such right to be appurtenant to the land, in exchange for which the landowners agree to pay taxes and water service fees. The agreements also provide that wells and other groundwater rights associated with the land are to be conveyed to the irrigation districts, in accordance with state law. Neither the Conservation District, nor the United States, is a party to the memoranda of understanding or to the water service agreements between the irrigation districts and the landowners.
In November 2001, the landowners filed an action in state court against their respective irrigation districts. Smith v. Maricopa-Stanfield Irrigation & Drainage Dist., No. CV-2001-00924 (filed Nov. 6, 2001 Ariz.Super. Ct.). The landowners alleged that the irrigation districts were in the process of considering a settlement agreement—the Arizona Water Settlement Agreement—that would offer the irrigation districts partial debt relief on their project financing obligations, and, in return, would require the irrigation districts to relinquish all or part of their allocated rights to non-Indian agricultural priority project water. Id. The landowners sought a declaratory judgment to preempt the possibility that the irrigation districts would give up these water rights through the proposed settlement. See id. The landowners’ action was stayed for approximately one year, with the stay lifted in March 2003 following the Conservation District‘s formal approval of the Arizona Water Settlement Agreement.3
The Conservation District removed the present case to federal court, and then moved to dismiss the landowners’ complaint for failure to state a claim, arguing that the landowners could not obtain the requested relief because they are neither parties to, nor third-party beneficiaries of, the relevant contracts. Alternatively, the Conservation District sought dismissal for failure to join the United States as an indispensable party. The landowners opposed the motion to dismiss and moved the district court to abstain and to remand the case to state court, arguing that dismissal pursuant to Colorado River Water Conservation District v. United States, 424 U.S. 800, 96 S.Ct. 1236, 47 L.Ed.2d 483 (1976), was warranted in light of the pending related state action, Smith v. Maricopa-Stanfield Irrigation & Drainage District.
The district court denied the landowners’ motion to abstain and remand. The district court concluded that a stay or dismissal of the federal action was not warranted because the pending state court action was an entirely separate proceeding involving claims distinguishable from those presented in the federal action. The district court then granted the Conservation District‘s motion to dismiss the landowners’ complaint for failure to state a claim, determining that because the landowners were neither parties to nor third-party beneficiaries of the master contract or the project subcontracts, the landowners could not bring suit to enforce those contracts. Because the landowners had failed to state a claim, the district court found it unnecessary to evaluate the Conservation District‘s contention that the United States is an indispensable party. This appeal followed.
II.
The landowners appeal the district court‘s decision to exercise its jurisdiction despite their pending state court action against the irrigation districts, Smith v. Maricopa-Stanfield Irrigation & Drainage District. Whether the facts of a particular case conform to the requirements for a Colorado River stay or dismissal is a question of law which we review de novo. United States v. Morros, 268 F.3d 695, 703 (9th Cir.2001).
In Colorado River, the Supreme Court was concerned with the problem posed by the contemporaneous exercise of concurrent jurisdiction by state and federal courts. Gilbertson v. Albright, 381 F.3d 965, 982 n. 17 (9th Cir.2004) (en banc). In such cases, the Court recognized there may be circumstances in which traditional abstention principles do not apply, yet4 to exercise federal jurisdiction pursuant to Colorado River is more properly referred to as a stay or dismissal, as the case may be.
We have consequently held that “the existence of a substantial doubt as to whether the state proceedings will resolve the federal action precludes the granting of a [Colorado River] stay.” Intel Corp. v. Advanced Micro Devices, Inc., 12 F.3d 908, 913 (9th Cir.1993). “[E]xact parallelism” between the state and federal proceedings is not required, Nakash v. Marciano, 882 F.2d 1411, 1416 (9th Cir.1989); however, any substantial doubt is sufficient to preclude a stay:
When a district court decides to dismiss or stay under Colorado River, it presumably concludes that the parallel state-court litigation will be an adequate vehicle for the complete and prompt resolution of the issues between the parties. If there is any substantial doubt as to this, it would be a serious abuse of discretion to grant the stay or dismissal at all....
Intel, 12 F.3d at 913 (quoting Moses H. Cone Mem‘l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 28, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983)); see also Gulfstream Aerospace Corp. v. Mayacamas Corp., 485 U.S. 271, 277, 108 S.Ct. 1133, 99 L.Ed.2d 296 (1988) (quoting Moses H. Cone, 460 U.S. at 28, 103 S.Ct. 927) (district court may enter a Colorado River stay “only if it has full confidence that the parallel state proceeding will be an adequate vehicle for the complete and prompt resolution of the issues between the parties.” ).
Having reviewed the pleadings in both the state and federal actions, we conclude that the likelihood of the state court proceeding adequately addressing the issues presented in the federal proceeding was, at the time of the district court‘s decision, unclear at best.5 Although the landowners in their complaint in the state action referenced the project subcontracts as a basis for their asserted water rights, it was by no means clear from their state action complaint that they sought a determination of their rights under the project subcontracts. Rather, the relief they sought focused on their rights against the irrigation districts under the memoranda of understanding and water service agreements. Moreover, there was little to indicate that the state court proceeding would necessarily entail an examination of the landowners’ rights, if any, under the master contract or the project subcontracts. In these circumstances, substantial doubt existed regarding whether the state court action would resolve the claims at issue in
III.
We review de novo the district court‘s order under
The landowners contend that state law, rather than federal law, controls the interpretation of the master contract and the project subcontracts, and that, under state law, the landowners are third-party beneficiaries of those federal subcontracts. We disagree.
Federal law governs the interpretation of contracts entered into pursuant to federal law and to which the government is a party. O‘Neill v. United States, 50 F.3d 677, 682 (9th Cir.1995). Although we have recognized limited circumstances in which state law may apply to the interpretation of a federal contract, such as when the United States is not a party, or when the direct interests and obligations of the government are not in question, see, e.g., Flagstaff Med. Ctr., Inc. v. Sullivan, 962 F.2d 879, 890 (9th Cir.1992), such circumstances do not exist in the present case. The United States is a party to the master contract and to each of the relevant subcontracts. Moreover, the claims asserted by the landowners implicate the government‘s obligations and interests: the Arizona Water Settlement Agreement facilitates the United States government‘s obligations to certain Indian tribes, while protecting the government‘s interest in ensuring eventual repayment of the project‘s construction costs.
Contracts implementing federally-funded water reclamation projects are by nature necessarily federal, cf. Nebraska v. Wyoming, 325 U.S. 589, 615, 65 S.Ct. 1332, 89 L.Ed. 1815 (1945), and we have therefore “consistently applied federal law to interpret reclamation contracts.” Mohave Valley Irrigation & Drainage Dist. v. Norton, 244 F.3d 1164, 1165 (9th Cir.2001) (citing Klamath, 204 F.3d at 1210, and Kennewick Irrigation Dist. v. United States, 880 F.2d 1018, 1032 (9th Cir.1989)). Accordingly, we apply federal law principles of contract interpretation to evaluate the landowners’ claims under the project master contract and the relevant subcontracts.
The landowners contend, whether the contracts are interpreted pursuant to state or federal law, the landowners are properly classified as third-party beneficiaries of the contracts who can therefore assert claims against the Conservation District. Having reviewed the text and purpose of the master contract and the relevant subcontracts, we conclude the landowners are not intended third-party beneficiaries.
In both Klamath and Orff v. United States, 358 F.3d 1137 (9th Cir.2004), aff‘d on other grounds, 545 U.S. 596, 125 S.Ct. 2606, 162 L.Ed.2d 544 (2005), we determined that nonparties to federal water reclamation contracts were not intended beneficiaries of the contracts, even though the contracts operated to the nonparties’ benefit and were entered into with them in mind. Orff, 358 F.3d at 1147; Klamath, 204 F.3d at 1212; see also Long v. Salt River Valley Water Users’ Ass‘n, 820 F.2d 284,
Klamath involved a dispute over water recovered and appropriated through a water reclamation project in the Klamath Basin. 204 F.3d at 1209. The project agreement, authorized pursuant to the Reclamation Act of 1902, specified that the California Oregon Power Company (COPCO) would construct the Link River Dam, and in return would retain the right to operate the dam for a specified period of time.
We held that the irrigators would not be entitled to enforce the contract unless they could qualify as third-party beneficiaries.
To sue as a third-party beneficiary of a contract, the third party must show that the contract reflects the express or implied intention of the parties to the contract to benefit the third party. The intended beneficiary need not be specifically or individually identified in the contract, but must fall within a class clearly intended by the parties to benefit from the contract.
Id. at 1211 (internal citations and footnotes omitted). We further noted the relative difficulty of demonstrating third-party beneficiary status in the context of government contracts: “Parties that benefit from a government contract are generally assumed to be incidental beneficiaries, and may not enforce the contract absent a clear intent to the contrary.” Id.
We found no language within the contract in Klamath sufficient to overcome the “clear intent” hurdle. See id. Nor could we confer third-party beneficiary status on the irrigators consistent with the objectives of the contract. We noted that “[a]lthough the Contract operates to the Irrigators’ benefit by impounding irrigation water, and was undoubtedly entered into with the Irrigators in mind, to allow them intended third-party beneficiary status would open the door to ... a result not intended by the Contract.” Id. at 1212.
In Orff, individual farmers and water users within a water district brought suit against the United States. 358 F.3d at 1141. The farmers sought to prevent the United States from modifying an existing water allocation contract pursuant to which the water district received water from the Central Valley Project, a federal water management project authorized pursuant to the Reclamation Act of 1902. Id. The government asserted the farmers’ claims were barred by sovereign immunity. Id. at 1142. Although Congress had expressly waived the government‘s sovereign immunity for suits seeking to interpret contractual rights in federal water reclamation contracts where the United States is a necessary party defendant, the waiver was limited to suits involving the rights of a “contracting entity.” Id. at 1144 (citing
Citing Klamath, we determined that the contract in Orff did not evince the necessary “clear intent” to benefit the farmers. Id. at 1145. The contract‘s language pertaining to the obligation of the water users to pay tolls and assessments as a prerequisite to the receipt of water did not “delineate[] a contractual relationship between the farmers and the government.” Id. at 1146. We found “similarly unavailing” language providing that “anyone having or claiming to have by, through, or under the District the right to the use of any of the [Central Valley Project] water supply” would be entitled to an account adjustment in the event of a water shortage. Id. As in Klamath, that this language might show the contract was entered into with the farmers “in mind” was not enough to confer third-party beneficiary status. Id. at 1147. The government had therefore not waived its immunity from suit, and the district court lacked jurisdiction. Id. at 1149.6
Notwithstanding the fate of the farmers in Orff and the irrigators in Klamath, the landowners here allege the requisite clear intent to confer third-party beneficiary status is displayed by various provisions of the master contract and of the relevant subcontracts.
The landowners point to three provisions of the master contract to support their claim to intended beneficiary status. First, the landowners cite ¶ 8.3 of the master contract which provides that “[t]he obligation of the United States to deliver water under this contract is subject to: The availability of such water for use in Arizona under the provisions of the Colorado River Compact, ... the Boulder Canyon Project Act, ... the Colorado River Basin Project Act, ...” and the Supreme Court‘s opinion in Arizona v. California, 373 U.S. 546, 83 S.Ct. 1468, 10 L.Ed.2d 542 (1963). Amended Master Repayment Contract ¶ 8.3(a). This language does not manifest an intent to benefit the landowner. Rather, it merely specifies that the government‘s obligation under the master contract to deliver water is subject to specified federal law.
The landowners’ reliance on ¶ 8.17 of the master contract is likewise misplaced. Paragraph 8.17 provides “the Contractor [Central Arizona Water Conservation District] agrees that all project facilities will be available for the diversion, transportation, and carriage of water for Indian and non-Indian uses pursuant to arrangements or contracts therefor entered into on their behalf with the Secretary.” Amended Master Repayment Contract ¶ 8.17. This phrase simply indicates that the Conservation District agrees to abide by the terms of the project subcontracts for the delivery of project water; it does nothing to create vested water rights in the recipients of the project water.
Finally, the landowners argue that ¶ 10.5 of the master contract, which requires Arizona state court validation before the United States may be bound, necessarily incorporates the procedural requirements of state law. They argue that, under state law, one purpose of the validation proceedings was to intentionally
The landowners also invoke various provisions of the subcontracts to support their claim of third-party beneficiary status, yet we find the language of the subcontracts similarly unavailing. The landowners rely on the subcontracts’ explanatory recitals which state a purpose to “furnish[] irrigation and municipal and industrial water supplies.” Subcontract ¶ 2. This hortatory statement of purpose at best might qualify the landowners as incidental beneficiaries, a status that does not confer enforceable rights. Indeed, the sheer breadth of the objectives expressed in the subcontracts, including flood control, wildlife conservation, and recreation, undermines the landowners’ contention that the particular groups who might be benefitted are intended beneficiaries as opposed to incidental beneficiaries of the subcontracts. We conclude here, as we did in Klamath, that to allow third-party beneficiary status to all of the groups potentially benefitted under the subcontracts would produce a result certainly not intended. See Klamath, 204 F.3d at 1212.
Nor does the subcontracts’ requirement that the United States “use all reasonable diligence to make available to the Subcontractor the quantity of Project Water specified [herein],” Subcontract ¶ 4.1, meet the “clear intent” standard required for intended third-party beneficiary status. This language obligates the United States to the subcontractor, in this case the irrigation districts, and is silent as to any other beneficiary. We assuredly will not infer a contracting party‘s required intent from complete silence.
The landowners are also unaided by the subcontracts’ requirement that “[a]ll uses of Project Water and Return Flow shall be consistent with Arizona water law unless such law is inconsistent with the Congressional directives applicable to the Central Arizona Project.” Subcontract ¶ 4.3(a). This provision does not, as the landowners assert, confer vested rights to non-Indian agricultural priority water rights under state law. To the contrary, this language limits the possibility that project water rights might indefeasibly vest in the landowners or any other end users of project water.
IV.
We conclude that the district court properly declined to stay the proceedings in this case pending the resolution of a related state court action. Substantial doubt existed at the time of the district court‘s decision as to whether the state court action would provide complete and prompt resolution of the issues presented in this case.
AFFIRMED.
DAVID R. THOMPSON
UNITED STATES CIRCUIT JUDGE