99 Cal. 262 | Cal. | 1893
This is an appeal from a judgment of the superior court of the county of San Bernardino commanding the board of supervisors of said county to take action on the claim of plaintiff, filed on the twenty-seventh day of October, 1891, before the said board of supervisors, by approving or rejecting the claim. Plaintiff filed a claim against the county of San Bernardino based upon the same contract which is relied upon in the present litigation, and the claim was rejected by the board. After six months had expired from the date of such rejection, but within one year from the date when the liability accrued, plaintiff filed a second claim based upon the same contract. The board of supervisors refused either to reject or approve this claim, upon the ground that the same claim had been previously rejected and the law did not require further action in the premises, and this proceeding by mandamus followed.
There is no issue of fact in the case. Both claims are before the court, and the only question to be determined is, Upon a comparison can it be said that there is a material difference between these claims? We believe they differ in important respects. The contract for the bridge work provided, among-other things, that the contract price was payable upon the presentation of the written certificate of the superintendent of construction of said bridge, that said bridge has been erected and completed in every respect in accordance with the terms of the contract. The production of the certificate of the superintendent of construction before the board of supervisors was a necessary condition to the allowance of the claim. This certificate, bearing date October 27, 1892, is attached to the second claim presented, but was not attached to the first, and, viewed iu the light furnished by'its date, could not have been issued at that time.
Let the judgment be affirmed
Harrison, J., and Paterson, J., concurred.