76 S.E. 481 | N.C. | 1912
This is an action to recover damages alleged to have been sustained by reason of the wrongful levy of an attachment upon the property of the plaintiff in a former proceeding in which he was defendant and successfully defended the suit.
The plea of the statute of limitations cannot be sustained. Though the property seized under the attachment was released upon the execution of the defendant's undertaking more than three years before the beginning of this action, the "recovery of judgment by the defendant," which was the condition authorizing suit upon the undertaking (Revisal, 763) given by the plaintiff in procuring the attachment, took place less than two years before the institution of this action. Such recovery of *469 judgment in the former action was a "vacation of the attachment ordered by the court." Revisal, 786. In view of the rendition of such former judgment, the judge properly refused to charge the jury that the plaintiff had failed to show probable cause.
The items of damages allowed and excepted to are four:
1. Sixty dollars, which was the amount the plaintiff paid for (576) procuring the undertaking given by him to procure the release of the property attached. In the absence of evidence that it was excessive or unreasonable, it was properly allowed as damages. We cannot agree with the defendant that it should have been taxed as costs in the former judgment. It was no part of the court proceeding, but was a proper item of damages in an action upon the bond of the plaintiff in the attachment.
The second item, allowing the plaintiff $20.60 for railroad fare and berth and board on trip attending to the release of the attached property, and the third item of $25, for value of his time in so doing, cannot be allowed. Every litigant necessarily incurs some expenses beyond the fees of his witnesses and of the officers of the court. But for these personal expenses and his time he cannot be allowed compensation, for it would open the door to great abuses, and would often result in oppression. Hyman v.Devereux,
The only other item is $300, which the plaintiff was required to pay as penalties by reason of the delay in the execution of another contract for building caused by the attachment of his property which he was using in the execution of such other contract. The property was attached on 25 March and the undertaking to secure the release thereof from the attachment was filed on 8 April. The evidence is that there was no unreasonable delay in executing the undertaking to secure the release of the property and that he could not have purchased new material and had it shipped in less time. Such damage was within the purview of the bond, even under Sledge v. Reid,
The defendant contends that it was a misjoinder to join a cause of action against the principal for wrongfully suing out an attachment and an action against the surety upon the undertaking given by the plaintiff.R. R. v. Hardware Co.,
The judgment will be modified by striking out $45.60 as above pointed out. The judgment is therefore
Modified and affirmed. *470