167 N.Y. 234 | NY | 1901
This was an action by a contractor to foreclose a mechanic's lien, for the balance of the contract price alleged to be due. The only issue of fact presented by the pleadings was the performance of the contract by the plaintiff. Considerable proof was given upon the subject, but the learned trial court found that the plaintiff had performed the contract and that there was a balance due to him of something over six thousand dollars. The Appellate Division affirmed the judgment and the decision of that court was unanimous. Therefore, all the disputed facts are to be taken by this court as settled beyond all further controversy and we must assume that the facts so found are supported by evidence. The appeal can be sustained, if at all, only upon the exceptions taken at the trial and presented by the record. This was an equity action tried before the court and the judgment should not be disturbed upon any ruling relating to the admission or exclusion of evidence, unless it appears that the error was of such a substantial character as to affect the result, or prejudice the rights of the defeated party. The record presents only one exception that calls for any discussion, and indeed it is the only one that has been discussed by the learned counsel for the appellants.
It appears that the contract for the performance of the work contained a provision that when the work was completed in accordance with the contract and specifications of the engineer and he should make a final estimate of the quality, quantity and value of the work, according to the terms *237
of the contract, then the full amount appearing to be due to the contractor should be paid to him at such time and place as he might designate upon presenting the certificate of the engineer of the amount due. The contractor did not procure this certificate, but gave proof at the trial sufficient to satisfy the court that he had performed the contract. It was held in the case of Weeks v. O'Brien (
It appears in this case that the defendant gave written notice to the contractor that he would himself proceed to construct and complete the work at the contractor's expense, and would deduct the cost of such completion from the amount which would become payable to the contractor had he fulfilled his obligation under the contract. This notice was given to the contractor on the ground that he had failed and refused to perform the contract. The notice also, in substance, required the contractor to discontinue the work and turn it over to the parties selected by the defendant to finish it. These written notices clearly established the fact that the contractor was prevented by the defendant from completing the work, if anything then remained to be done, and that the defendant elected to finish and complete the work himself according to his own ideas of what the contract required at the expense of the contractor. If these letters were properly in the record, the learned court below on appeal committed no error in so amending the complaint as to conform to the proof. On an issue of performance it was competent for the contractor to prove, if he could, that the owner himself took the work out of his hands and assumed to complete it. In such a case when the contractor sues to recover the balance due to him upon the contract, he is not required to produce the certificate. (Wright v. Reusens,
Moreover, when performance of a contract is alleged by the plaintiff and denied by the defendant, it is competent for the plaintiff to prove that the defendant would not allow him to perform, or repudiated the contract, or had committed a breach of it himself, by hindering performance or refusing to abide by its obligations. (Burtis v. Thompson,
We are, therefore, of opinion that the record does not disclose any error of law which would warrant this court in disturbing the judgment, and so it must be affirmed, with costs.
PARKER, Ch. J., GRAY, MARTIN, LANDON and WERNER, JJ., concur; CULLEN, J., not sitting.
Judgment affirmed. *240