This was an action brought by the plaintiff to recover a balance of moneys alleged to be due to him for cutting, sawing and manufacturing lumber and bark, upon *423 agreements made with the defendant's assignor, George Clarke. The defendant is the assignee of Clarke, under a general assignment made by the latter, in April, 1887, for the benefit of his creditors. At the time of the assignment by Clarke, the work contracted to be done by the plaintiff was unfinished and the latter claims that he was authorized and requested by defendant to go on with the contract. He does not claim that this request came directly from the defendant's mouth to him; but that it came through an agent of the defendant. The defendant, on the other hand, claims to have been ignorant of the plaintiff's contract with Clarke, that he never knew or was informed with respect to the plaintiff's work under it; that he never, directly or indirectly, authorized, or consented to, the work which the plaintiff did and that the request to plaintiff to continue the contract was not made by one who was then his agent. Upon the issue thus formed between the plaintiff and defendant, the referee, before whom the case was tried, determined in favor of the plaintiff and directed judgment for the sum which remained due for the work done by the plaintiff, after crediting upon the whole amount due the aggregate of various sums received from an agent of the defendant.

We think that the evidence sufficiently supports the findings of the referee upon the questions of fact relating to the agencies employed by the defendant, with respect to the management of the assigned estate, upon which the timber was to be cut under the contract with his assignor, and with respect to a ratification by him of acts of his agents in their dealings with the plaintiff. The defendant received the net proceeds of the sales of this lumber and, although they may have been turned over to him by his agent at a time subsequent to the cessation of work by the plaintiff, that circumstance is not very material upon the question of his liability to the latter for the work done subsequent to the assignment; provided that his agents, acting within the general scope of their employment, had induced the plaintiff to continue the performance of the contract. The defendant does not pretend *424 to have given any personal attention to that part of the assigned estate. He employed others to do it for him, whom he regarded as competent for that purpose, as he says; and there was evidence from which to imply the existence of authority in the defendant's agents to accomplish such apparently advantageous results to the assigned estate, as would be comprehended in the cutting and sawing of the timber and in preparing it for market. Nor is it to be doubted that the instrumentalities used by the defendant's agents to the end of realizing upon the assigned estate, even if involving an incidental indebtedness on the part of the assignee, might be so adopted and ratified by the latter as to preclude him from thereafter successfully disputing his liability. No citations of authority should be necessary in support of so just a proposition. We may assume that the defendant, personally, did not request the plaintiff to continue with the contract, which he had made with Clarke, and that the plaintiff was induced to do so by one who, at the time, lacked the authority to represent or to bind the defendant, and yet, if, subsequently, the defendant received the proceeds of the sales of the lumber, which plaintiff had cut and the agents of defendant had sold, with knowledge of the facts, or under circumstances which made him chargeable with their knowledge, he must be held to have ratified and adopted the previous unauthorized act. (Murray v. Bininger, 3 Keyes, 107;Leslie v. Wiley, 47 N.Y. 648.)

We think it unnecessary to consider this case at any greater length. The plaintiff labored under the difficulty of eliciting evidence from witnesses presumably, or possibly, hostile; but there was sufficient in the evidence adduced, from which the referee might find as he did upon the facts, and the legal conclusions establishing the plaintiff's right to recover against the defendant will not be disturbed by us.

The judgment should be affirmed, with costs.

All concur.

Judgment affirmed. *425

midpage