Smith Sand & Gravel Co. v. Corbin

89 Wash. 43 | Wash. | 1916

Mount, J.

This case has been before this court on two former occasions. The first appeal was by the plaintiff from an order granting a new trial. The appeal was first heard by Department One of this court, and the order affirmed. Smith Sand & Gravel Co. v. Corbin, 75 Wash. 635, 135 Pac. 472. A rehearing was granted and the cause- was presented to the court En Banc. The order granting a new trial was again affirmed, the entire court concurring. In the En Banc opinion, speaking of the trial court’s ruling on the motion for a new trial, we said: *45temporaneous parol agreement.” Smith Sand & Gravel Co. v. Corbin, 81 Wash. 494, 142 Pac. 1163.

*44“The court, in ruling orally upon the motion, gave three reasons for granting a new trial; (1) that he had committed error in his instructions to the jury touching the burden of proof; (2) that he had erred in permitting any testimony to be introduced on the second cause of action; (3) that in any event the verdict was against the evidence. The formal order, however, did not state the grounds. Even under our decision antedating this appeal, which was taken prior to the adoption of the rule to that effect, in Rochester v. Seattle, Renton Southern R. Co., 75 Wash. 559, 135 Pac. 209, we are at liberty to examine the whole record, and, if it discloses any ground warranting the granting of a new trial, the order appealed from must be affirmed.
“Such an examination convinces us that the so-called second cause of action failed to state a cause of action. It pleaded an oral agreement, contemporaneous with the written agreement, and sought to put upon this oral agreement a construction which would vary the terms and legal effect of the writing. It is a rule of universal application that a written contract complete in itself, or in so far as it is complete in itself, cannot be contradicted, explained, enlarged, varied or controlled by extrinsic evidence of a different con-

*45We then held that, because the court at the first trial had committed error in admitting any evidence under the second cause of action, a new trial was properly granted. Por a synopsis of the pleadings and of the facts, we refer to the two former opinions.

On the transmission of the remittitur, the defendant moved the trial court to strike from the amended complaint, upon which the first trial was had, the second and third causes of action. The motion was granted, and a judgment was entered dismissing the second and third causes of action. The plaintiff again appeals.

There is grave doubt as to whether the order appealed from is appealable, but inasmuch as it must be affirmed on the merits, we prefer so to dispose of it.

The first claim of error is directed to the striking by the trial court of the second and third causes of action. The third cause of action was abandoned at the former trial. There was obviously no error in striking it. Counsel makes the surprising claim that the sufficiency of the second cause of action was not before the court on the hearing En Banc, and that therefore everything said in the opinion, save the final sentence affirming the order granting a new trial, is obiter dictum. Several pages of his brief are devoted to the elementary rule that dictum is not decision. It is then argued that the sufficiency of the complaint was not before us, because insufficiency of a complaint to state a cause of action is not made by statute a specific ground for the granting of a new trial. The statute, Rem. & Bal. Code, § 399, subd. 8 (P. C. 81 § 729),'however, does provide that a new trial may be granted for “error in law occurring at the trial and excepted to at the time by the party making the application.” It is self-evident that the admission of evidence addressed to a pleading which does not state a cause of action, over objection and exception taken, is error in law.' We *46were, therefore, compelled to pass upon the sufficiency of the second count of the complaint in order to determine whether the trial court had committed error in law by admitting evidence under it. Demonstrably, the determination of the insufficiency of the second cause of action was necessary to the conclusion that the new trial was properly granted. Our decision that it did not state a cause of action, therefore, became thenceforth the law of the case, and a sufficient warrant to the trial court to strike it from the complaint.

Appellant now urges us to reconsider the question of the sufficiency of the second cause of action, insisting that all that was said in the opinion En Banc was an inadvertence, and in conflict with the holding of this court in Interstate Engineering Co. v. Archer, 64 Wash. 629, 117 Pac. 470. We find no such conflict. In that case, there was no formal written contract. The writing consisted of an order for structural iron and the letter acknowledging receipt of the order, stating the price, kind of material, manner of shipment and terms of payment, but failing to state the quantity of material or the time when it was to be delivered. The defendant pleaded, and was permitted to prove, that the plaintiff agreed to ship the iron within a reasonable time and not to exceed thirty days after the date of the contract. We said:

“The letter upon its face does not purport to state the whole agreement. . . . Where it appears that only a part of the contract is in writing, the part not in writing may be proved by parol, in so far as it is not inconsistent with the written portion. 17 Cyc. 746-7; Wigmore, Evidence, § 2430. It was proper, therefore, for the court to receive oral evidence as to the time when the materials were agreed to be delivered.”

The phrase which we have italicized in the above quotation states an essential qualification in every such case. It marks a plain and elementary distinction between the Interstate Engineering case and the case before us. In the case here, there was neither allegation nor offer of proof that any *47definite time was agreed upon as a reasonable time for the removal of the rock. The written contract definitely provided what work was to be done, and at what price, but did not provide when it was to be completed. There being no allegation that any definite time was agreed upon, either orally or otherwise, it became an implied term of the contract that it must be done within a reasonable time. It follows that the only competent evidence as to time was evidence of what was a reasonable time to do the work of removing the rock, which was the only work contemplated in the written contract. Such evidence was admitted, and we held properly so. But the appellant, as its so-called second cause of action, pleaded an alleged oral agreement which would extend the time of performance beyond the legally implied reasonable time for the removal of all the rock to such time as it might find necessary to crush the rock and sell it at a profit. As we said on the rehearing En Banc:

“Such an agreement would change the whole tenor of the written contract. It would extend the time of performance beyond the legally implied reasonable time for the removal of all the rock to such time as the appellant might find necessary to crush the rock and sell it at a profit. This would contradict and change the whole scope and meaning of the written contract touching a stipulation upon which the writing is clear and unambiguous. The written contract was not for a sale of rock, but for the removal of rock; hence no damages could be recovered for a loss of profits upon the rock without first showing that the respondent terminated the contract and reentered before the expiration of a reasonable time for the removal of all the rock; not before the expiration of a reasonable time for crushing and selling of all the rock at a profit. These two things are so widely different that a contract for the one is wholly inconsistent with an agreement for the other.”

If, in the Interstate Engineering case, the plaintiff had pleaded an oral agreement that it should have such time to furnish the iron as might be required to purchase it at such price as to make a profit on the written contract to furnish *48the iron to the defendant, proof of such a collateral agreement would have been plainly inadmissible. It would have changed the whole tenor of the written agreement to furnish the iron at a given price for a given purpose. It would have had no tendency to prove what was a reasonable time to furnish the iron. Furnishing the iron was the definite purpose covered by the writing. The distinction is just this. The rule that the failure to fix a definite time in the writing to do the definite thing provided in the writing to be done will admit parol proof of what is a reasonable time to do that definite thing, does not authorize parol proof of what would be a reasonable time to do that thing and something else not mentioned nor implied in the writing.

Counsel quotes with emphasis the following from the En Banc opinion:

“In the case before us, the appellant, by its so-called second cause of action, did not merely seek to plead facts showing what was a reasonable time for the removal of all the rock. . . . but sought to set up and substitute for such reasonable time, an oral agreement that the appellant should have such time as would be required to crush and dispose of the rock by sale at a profit as the agreed time for the removal of the rock.”

He then says that this construction of the second cause of action is not borne out by an inspection of the complaint, because “nowhere in the complaint is it alleged that the time for performance was to be extended for the purpose of enabling appellant to find purchasers or for any other purpose.” He then immediately states that, under the allegations of the second cause of action, he was at the first trial permitted to introduce evidence “respecting the difficulty of finding a market for the crushed rock and of delays in the work consequent thereon.” Further along in the same connection he argues:

“Now, since the oral portion provided that the rock when removed should become the property of the appellant as an additional consideration, then it was proper to inquire and *49introduce evidence to prove under what circumstances and conditions the rock so contracted to be removed could be rendered available and valuable as an additional consideration, and the question of what constituted a ‘reasonable time’ for performance was to be determined in the light of those conditions as they might be disclosed by the evidence. This line of inquiry was permitted to some extent by the court at the former trial and it was thereby disclosed, as commented upon by this court, that the value of the rock when crushed, likewise the demand therefor, was dependent upon a variable market, which was controlled in turn to a large extent by the business conditions of the city of Spokane and the amount of public work in progress wherein crushed rock might be used as a building material. These things, we repeat, were undoubtedly in the minds of the contracting parties at the time of the execution of the contract, and necessarily constituted the surrounding circumstances and conditions which must be considered in order to arrive at a just conclusion as to the time within which performance was to be completed.”

If in this counsel does not construe his own pleading precisely as we construed it in the quotation from our En Banc opinion, which he criticises, then his language has no meaning at all. Nothing which we could say could make it plainer than this language of counsel does that the purpose of the second cause of action was to plead, in order to prove as an additional consideration to that named in the writing, a contemporaneous parol agreement contradicting the terms, enlarging the scope, and varying the purpose of the contract as written, and thus, under the guise of proving an additional consideration, engraft on the written agreement new terms and covenants by parol so as to enlarge the time of performance. Counsel cannot in one breath disclaim that purpose for his second cause of action as pleaded, and in the next breath claim that purpose for the only evidence offered under that pleading.

Counsel intimates that the question of the sufficiency of the complaint was not raised in the briefs on the former appeal, and complains that the arguments in support of it *50“were the exclusive products of the industry of the court.” The point was raised in respondent’s opening brief on the first appeal and was thereafter discussed in the appellant’s reply brief, and again in appellant’s brief on rehearing En Banc. Moreover, the trial court discussed the point in his oral ruling on the motion for a new trial. It is simply idle to intimate that the question was not presented in the record.

The statement that the arguments in support of our opinion En Banc .were the product of the court’s industry is largely true, but furnishes no just ground for criticism. The responsibilities of this court as a court of review are not limited to what the briefs may offer. Many appeals are presented in which the respondent fails to appear and file any brief, but we never treat the appellant’s case as confessed on that account. In such a case, we always make an independent investigation to the extent that our limited time will permit and endeavor to reach a correct result. For an example, see Mesher v. Osborne, 75 Wash. 439, 134 Pac. 1092, 48 L. R. A. (N. S.) 917.

Finally, the appellant, though insisting that the second trial should have been had on the pleadings as they stood when the new trial was granted, somewhat inconsistently now claims that the trial court erred in refusing to permit an amendment of the second cause of action. The trial court committed no error in this respect. The purpose of the proposed amendment was to claim a breach of the contract on respondent’s part in failing to pay ninety per cent of the monthly estimates of rocks removed, as provided in the written contract. This was not claimed as a breach in the original amended complaint. To have permitted the amendment would have introduced an entirely new cause of action. Moreover, to now assert this as a reason for the appellant’s delay in removing the rock would be a plain departure from the position taken by appellant in its reply, wherein it is alleged, in substance, that its delay in removing the rock was *51contemplated by a collateral oral agreement that appellant should have such time to remove it as might be necessary to dispose of it to third persons for commercial purposes. To permit such a departure by amendment would be to encourage successive trials on wholly different theories and to entertain appeals in piecemeal. Such a course would lead to a never ending litigation of the same transaction. Perrault v. Emporium Department Store Co., 83 Wash. 578, 145 Pac. 438, and cases there cited.

Affirmed.

Morris, C. J., Fullerton, Chadwick, and Ellis, JJ., concur.