JEANNETTE M. SMALLEY, LOREN LEE WIELAND, STACEE PELTZ, аnd KYLE PELTZ, for themselves and on behalf of a class of all others similarly situated, Appellants, v. DUKE ENERGY FLORIDA, INC., a Florida corporation, formerly FLORIDA POWER CORP., d/b/a PROGRESSIVE ENERGY FLORIDA, INC., and FLORIDA POWER & LIGHT CO., Appellees.
Case No. 2D13-4746
IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT
December 31, 2014
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED
Aрpeal from the Circuit Court for Lee County; Keith R. Kyle, Judge. Frank B. Arenas, Coleman, and Alberto E. Lugo-Janer, Windermere, for Appellants. Stephen H. Grimes, D. Bruce May, Jr., Elizabeth L. Bevington, and Kevin W. Cox of Holland & Knight, LLP, Tallahassee, for Appellees.
The appellants, customers of Duke Energy Florida, Inc., and Florida Power & Light Company (the Utilities), brought suit against the Utilities challenging the constitutionality of sections
In 2006, the Legislature enacted section
Section
If the utility elects not to complete or is precluded from cоmpleting construction of the nuclear power plant, including new, expanded, or relocated electrical transmission lines оr facilities necessary thereto, or of the integrated gasification combined cycle power plant, the utility shall be allowed to recover all prudent preconstruction and construction costs incurred following the commission‘s issuance of a final order granting a determination of need for the nuclear power plant and electrical transmission lines and facilities necessary thеreto or for the integrated gasification combined cycle power plant.
The appellants sued the Utilities alleging that the 2006 legislation is unconstitutional and seeking a refund of the monies paid to the Utilities pursuant to the cost recovery statutes. The Utilities moved tо dismiss. The trial court dismissed the amended complaint, but with leave to amend. The appellants filed a second amended complаint and the Utilities again moved to dismiss. After a hearing, the trial court
The second amended complaint contained two counts, only one of which is at issue in this appeal. In that count the appellants allege that sections
The constitutionality of a statute is a question of law we review de novo. Fla. Dep‘t of Revenue v. City of Gainesville, 918 So. 2d 250, 256 (Fla. 2005). A facial constitutional challenge considers only the text of the statute, not its application to a particular set of circumstances. Abdool v. Bondi, 141 So. 3d 529, 538 (Fla. 2014). A determination that a statute is facially unconstitutional means that no set of circumstances exists under which the statute would be valid. United States v. Salerno, 481 U.S. 739, 745 (1987); City of Gainesville, 918 So. 2d at 256. “If any state of facts, known or to be assumеd, justify the law, the court‘s power of inquiry ends.” State v. Bales, 343 So. 2d 9, 11 (Fla. 1977) (citing United States v. Carolene Prods. Co., 304 U.S. 144, 154 (1938)). A facial challenge fails when a statute has a “plainly legitimate
While the appellants argue that the challenged statutes are facially unconstitutional, they have utterly failed in their burden to demonstrate that no circumstances exist under which the statutes would be valid. Rather, the crux of the appellants’ challenge focuses only on one particular circumstance contemplated by the statute—the recovery of costs of construction where a utility “elects” not to build the plаnt. The appellants contend that the “statutes authorize each Defendant to elect not to build, complete or opеrate the nuclear power plants and thereby defeat any public purpose or public use.” They have not alleged nor argued that in the event a utility is precluded from completing a power plant due to factors beyond its control, the public purpоse for the legislation, which is to encourage investment in new nuclear power plants, is defeated. As noted by the Florida Supreme Cоurt, transferring the risk for proposed nuclear projects to encourage utilities to invest in new facilities is a “policy considerаtion best addressed by the Legislature,” and not the courts. Graham, 113 So. 3d at 753. Because the appellants have not met their burden of demonstrating that the statute is unconstitutional in all its possible applications, we affirm.
Affirmed.
ALTENBERND and SILBERMAN, JJ., Concur.
Notes
After a petition for determination of need for a nuclear or integrated gasification combined cycle power plant has been granted, the right of a utility to recover any costs incurred prior to commercial operation, including, but not limited to, costs associated with the siting, design, licensing, or construction of the plant and new, expanded, or relocated electrical transmission lines or facilities of any size that are necessary to serve the nuсlear power plant, shall not be subject to challenge unless and only to the extent the commission finds, based on a preponderance of the evidence adduced at a hearing before the commission under s. 120.57, that certain costs were imprudently incurred.
