88 Va. 1019 | Va. | 1892
cleliArered tlie opinion of the court.
The contention of the plaintiff was that in June, 1888, he contracted with the defendants, the OAvners of a steam barge, to transport a quantity of poplar cord-wood from Wormley’s and other upper landings on the Pamunkey river, to the White House, at the rate of seventy-five cents per cord; that he had previously contracted for the delivery in Philadelphia of large quantities of such wood, on or before the 15th of December, of the same year; that the alleged contract Avith the defendants was made Avith a view to enabling the plaintiff to comply Avith his contracts to deliver wood in Philadelphia; that in June, 1888, the barge of the defendants Avas being constructed, and that the plaintiff advanced to the defendants- $300, to enable them to complete it; that the contract bound the defendants to have the barge ready by the 20th of the following November, but that it Avas not, in fact, completed until the folloAving February; that during the winter and spring of 1889, much of the wood was washed aAvay by freshets in the river, and that the plaintiff expended in efforts to save it $420 ; that the value of the Avood actually lost by the freshets was $1,925, upon Avhich the plaintiff' Avould have realized a profit of $355, had the defendants complied Avith their contract; and damages were claimed in the declaration to the amount of $3,000.
On the other hand, the defendants offered evidence tending to prove that the transaction between the plaintiff' and themselves was simply a loan to them of $300, to enable them to complete the barge, with the understanding that they were to repay the loan in Avork; that no time was specified for the transportation of the Avood, but that in February, 1889, the barge being then completed, they Avent up the river to bring doAvn a load of Avood, and did bring down one load to Turner’s Landing ; that whilst unloading the Avood, they were informed by the agent of the plaintiff’ that there Avas a misunderstanding
The jury found a verdict for the plaintiff for $188.26, which Avas the sum advanced by the plaintiff, with interest, less the amount of certain offsets proved by the defendants.
The plaintiff’ then moved to set aside the verdict, as being contrary to the law and the evidence, but the motion Avas overruled, and judgment entered on the A7erdict, to which judgment he afterAvards obtained a Avrit of error.
The bill of exceptions sets out the evidence, and not the facts proved, so that the case must stand as on a demurrer to the evidence; and vieAving-it in that light, it is clear, from what has already been said, that the judgment is right.
It is proper, however, to say that there was no error in the refusal of the circuit court to giA7e to the jury the two instructions asked for by the plaintiff. The first Avas that “ the measure of damages, in case of a failure of a carrier to deliver goods according to contract, and which are lost, is the market value at the time when and the place where they should have been delivered.”
This instruction was irrelevant. The defendants were not sued as common carriers, and, besides, there was no evidence tending to prove a "delivery to them of any wood other than the one load above-mentioned; and it is settled laAv that the responsibility of a common carrier for the goods themselves does not commence until there has been a complete delivery to him. 2 Kent, Comm. 604; Blanchard v. Isaacs, 3 Barb.
The second instruction offered was to the effect that the plaintiff was entitled to recover as damages whatever he may have expended in the recovery of wood washed away, if the jm’y should believe, that the wood would not have been washed away had the defendants kept their contract.
This instruction was also rightly refused, because there is nothing in the case tending to show that the damage mentioned in the instruction conld be fairly and reasonably'considered as naturally arising from a breach of the contract in question, according to the usual course of things, or as having been in the contemplation of the parties when the contract was made as the probable result of a breach of it. The rule upon this subject is well settled and familiar. Hadley v. Baxendale, 9 Exch. 341; Kendall v. Commissioners Sinking Fund, 79 Va. 563; Griffin v. Colver, 16 N. Y. 489 ; West. Union Tel. Co. v. Hall, 124 U. S. 444.
An exception was also taken to the giving of an instruction offered by the defendants, which was as follows, to-wit:
“ If the jury believe from the evidence that J. L. Slaughter and the defendants made the contract set out in the first and second counts, or either of them, in the plaintiff’s amended declaration, and that the defendants failed to transport pursuant to said contract any of the poplar wood of the said J. L. Slaughter from the Wormley and other landings on the Pamunkey river to the White House, without any fault on the part of the plaintiff or his agent, then the court instructs the jury that the plaintiff is entitled to recover from the defendants under the said contract for their failure to transport such wood of the plaintiff. And if the jury believe from-the evidence that the said poplar wood was prior to November 20th, 1888, named in said alleged contract, and at and after that date within the power of the plaintiff, then the difference between the value of the wood not transported at Wormleys*1023 and other landings on the Pamunkey river, and its net value at the White House at the time it would have arrived, if it had been carried according to the contract, is the measure of the plaintiff’s damage, the defendants being in no manner liable for the loss of said wood from freshets during the spring of 1889.”
As to this instruction, it is enough to say that though awkwardly expressed, it. certainly contains nothing injurious to the plaintiff. And as this sufficiently disposes of the case, it follows that the judgment must be affirmed.
Judgment aeeirmed.