Opinion
Plaintiffs appeal from an order denying their application for a preliminary mandatory injunction directing defendant to release a mechanic’s lien filed against one of plaintiffs’ residences. They contend that defendant is not entitled to file a mechanic’s lien because he was not licensed as a contractor at all times during the performance of his work on the property. We conclude that the trial court properly denied the requested injunctive relief.
Facts
On April 8, 1998, defendant Barry L. White doing business as Western Estates Construction (White) entered into a contract with Edgar Slatkin to build a residence (the Slatkin residence). On or about July 19, 1999, Edgar Slatkin transferred ownership of the Slatkin residence to Lawrence J. Slat-kin. After the completion of the house in April 2001, White recorded a mechanic’s lien against the property for monies allegedly owed for the construction of the residence. Thereafter, the Slatkins filed a complaint seeking damages for breach of contract and a mandatory injunction to vacate the mechanic’s lien and to prohibit the filing of any further liens on the ground that White did not have a current valid contractor’s license from the Contractors’ State License Board (CSLB).
White withdrew the original lien, and filed a new lien limiting its amount to the cost of work
Plaintiffs moved for a preliminary injunction seeking to order the release of the second mechanic’s lien. Plaintiffs’ contention that White was precluded from filing a lien because he was not licensed throughout the period of construction was evidenced by the certified record of White’s licensing history with the CSLB.
1
White opposed the motion, arguing that he had substantially complied with the licensing requirements. He claimed that he was licensed when he signed the April 8, 1998 contract to construct the Slatkin residence. On or about December 27, 2000, more than two years eight months into the project, and with only three months remaining to complete the house, he first received notice from the CSLB that his license had been suspended effective August 27, 2000, four months earlier, because of the cancellation of a bond. He claimed this was the first and only time he was advised that his
At the hearing on the preliminary injunction, plaintiffs relied on White’s admission that despite receiving the December 27, 2000 notice of his license suspension, he continued to work until the end of April. While his license was reinstated when he secured a bond on June 21, 2001, the reinstatement was retroactive only to March 12, 2001, so that there was a gap of approximately three months in which White knowingly worked without a license. White argued in opposition that plaintiffs were not likely to succeed on their claim to remove the lien and that plaintiffs would not be irreparably harmed by the pendency of the lien. The trial court refused to direct White to release the lien, noting that plaintiffs were seeking a preliminary injunction “on limited amounts of evidence.” This appeal ensued. 2
Discussion
“At this initial stage in the proceeding, the scope of our inquiry is narrow. We review an order [denying] a preliminary injunction under an abuse of discretion standard. [Citations.] Review is confined, in other words, to a consideration whether the trial court abused its discretion in ‘ “evaluating] two interrelated factors when deciding whether or not to issue a preliminary injunction. The first is the likelihood that the plaintiff will prevail on the merits at trial. The second is the interim harm that the plaintiff is likely to sustain if the injunction were denied as compared to the harm the defendant is likely to suffer if the preliminary injunction were issued.” ’ [Citation.] And although we will not ordinarily disturb the trial court’s ruling absent a showing of abuse, an order granting or denying interlocutory relief reflects nothing more than the superior court’s evaluation of the controversy on the record before it at the time of its ruling; it is not an adjudication of the ultimate merits of the dispute.”
(People ex rel. Gallo v. Acuna
(1997)
“California law . . . offers equitable remedies which the owner [of property] can employ to obtain a speedy hearing on the probable validity of [a
mechanic’s] lien.”
(Connolly Development, Inc. v. Superior Court
(1976)
However, a contractor may avoid the harshness of section 7031 by establishing that he or she has substantially complied with the appropriate licensing requirements. Subdivision (e) of section 7031 provides, in pertinent part: “[T]he court may determine that there has been substantial compliance with licensure requirements under this section if it is shown at an evidentiary hearing that the person who engaged in the business or acted in the capacity of a contractor (1) had been duly licensed as a contractor in this state prior to the performance of the act or contract, (2) acted reasonably and in good faith to maintain proper licensure, and (3) did not know or reasonably should not have known that he or she was not duly licensed.” 4
Plaintiffs challenge White’s ability to establish that he has substantially complied with the licensing requirements as permitted under subdivision (e) of section 7031. Plaintiffs concede that White was duly licensed when he signed the contract at issue, and for purposes of this appeal, they do not contend that White did not act reasonably and in good faith to maintain proper licensure. However, because White admitted that he received a notice of suspension in December 2000, they contend that as a matter of law he cannot establish the third requirement that he did not know that he was not “duly licensed,” and therefore, he necessarily has not substantially complied with the licensing requirements.
The language of subdivision (e) of section 7031, which was added in 1994, was intended to ameliorate the harsh consequences of the section. (Sen. Com. on Business and Professions, com. on Sen. Bill No. 1844 (1993-1994 Reg. Sess.) as introduced Feb. 24, 1994, p. 2 [“This bill is sponsored by the author (sponsor) in order to remove the overly harsh application of the Contractor’s State License Law which, in court actions, denies contractors payment for services rendered, when for clerical or otherwise minor errors, they become unlicensed during the term of a contract”].) As plaintiffs would read the current subdivision, a contractor who continued to perform after learning that his or her license was no longer in effect would .automatically lose the right to be compensated—both for work already performed and for work performed while the license was no longer in effect. This result would encourage the contractor to act irresponsibly, contrary to the best interests of both the contractor and the client or property
owner. Assuming that the first two conditions of subdivision (e) have been satisfied and that the contractor did not know and should not have known of the loss of licensure before commencing work, the contractor will have been duly licensed before entering the construction contract and will have acted reasonably to maintain the license, but at some point during the course of performance will have learned that the license was no longer in effect. Under plaintiffs’ interpretation, the contractor, in order to preserve his or her right to payment, would be required to shut down the job immediately. Depending upon the nature of the project and the stage of construction at which the discovery occurs, abruptly halting performance could be financially ruinous not only to the contractor but to the client or property owner as well. As section 7031 has been interpreted, a contractor could not rely on any pleas or promises made by the property owner to induce the contractor to remain on the job.
(Hydrotech Systems, Ltd. v. Oasis Waterpark
(1991)
Under the “plain meaning” rule, “[t]he court looks first to the language of the statute; if clear and unambiguous, the court will give effect to its plain meaning.”
(Young v. Gannon
(2002)
For the reasons indicated above, the more sensible construction of subdivision (e) of section 7031 is that the contractor does not necessarily lose the right to be compensated simply because he or she performs additional work after discovering the loss of licensure, so long as the individual did not have knowledge or notice of the loss before the start of the job. Plaintiffs’ reliance on
Pacific Custom Pools, Inc.
v.
Turner Construction Co.
(2000)
By construing section 7031, subdivision (e) in this maimer, we do not indicate that a contractor who learns of the loss of licensure after work has begun necessarily may complete the project as if the license had not been lost. CSLB regulations might be helpful in this area (§ 7008), but factors relevant to the contractor’s right to recover would seem to include the reason for which the license was lost, the stage of
In any event, the issue now before the court is whether the superior court abused its discretion by determining that White should not be ordered to release his lien without affording him an evidentiary hearing as provided under subdivision (e) of section 7031. We conclude that the present record does not establish a likelihood that plaintiffs will prevail in defeating
White’s mechanic’s lien and there has been no abuse of discretion. “The granting of a mandatory injunction pending trial ‘ “is not permitted except in extreme cases where the right thereto is clearly established.” ’ ”
(Shoemaker v. County of Los Angeles
(1995)
Disposition
The order denying the preliminary injunction is affirmed.
McGuiness, P. J., and Parrilli, J., concurred.
Appellants’ petition for review by the Supreme Court was denied January 15, 2003.
Notes
As part of their motion papers, plaintiffs requested the superior court to take judicial notice of (1) a two-page “Certification of Records” document from the CSLB; and (2) a 168-page record of White’s licensing history from the CSLB. At the superior court hearing, both parties referred to these documents, although the court did not explicitly rule on plaintiffs’ request. By our order filed March 11, 2002, we granted plaintiffs’ unopposed request to take judicial notice of the documents on this appeal.
After filing their opening brief, plaintiffs posted a surety bond that released the contractor’s lien from the property as a matter of law. (Civ. Code, § 3143.) Because the subject property is no longer encumbered by a lien, White filed a motion seeking to dismiss the appeal as moot, which we denied by our order filed on June 10, 2002. In his brief, White also requests that we dismiss the appeal as moot. White does not present any new arguments in his brief in support of his request for dismissal, and we therefore decline to revisit the issue.
All further statutory references are to the Business and Professions Code, unless otherwise indicated.
At the time of the superior court’s decision in August 2001, the exception to the prohibition in section 7031 appeared in former subdivision (d). (Stats. 1994, ch. 550, § 1, pp. 2803-2804.) “When [former] subdivision (d) was first added to section 7031 in 1989, it eliminated altogether the [judicial] doctrine of substantial compliance. [Citation.] In 1991, [the] subdivision . . . was amended to provide that a court could ‘determine that there has been substantial compliance with licensure requirements, for purposes of this section, if it is shown at an evidentiary hearing that the person was a duly licensed contractor during any portion of the 90 days immediately preceding the performance of the act or contract for which compensation is sought, that the person’s category of licensure would have authorized the performance of that act or contract, and that noncompliance with the licensure requirement was the result of (1) inadvertent clerical error, or (2) other error or delay not caused by the negligence of the person. . . .’ [Citations.] [As noted, the] subdivision . . . was amended in 1994, this time to read as quoted in the text.”
(ICF Kaiser Engineers, Inc. v. Superior Court
(1999)
