685 F.2d 414 | Ct. Cl. | 1982
delivered the opinion of the court:
This is an action under the Contract Disputes Act of 1978 (CDA or Act), 41 U.S.C. § 609(a)(1),
On August 16, 1979, plaintiff, a partnership, and defendant entered into DOE Contract No. DE-AC01-79ET11268, a technical support services contract relating to DOE programs in mining and preparation of solid fuels. The disputes clause of the contract contained the statement that the contract was subject to the CDA, and any claim over $50,000 had to be certified by the contractor upon submission to the contracting officer. By a letter dated December
In its motion to dismiss, defendant presents two grounds in support of its motion: (1) plaintiff has failed to certify its claims as required by the Act; and (2) plaintiff has failed to exhaust administrative remedies in regard to its first claim for relief. Since we find that plaintiff has not properly certified its claims, we dismiss the petition for that reason alone and do not reach the second defense.
The requirement that a claim be certified is contained in section 605(c)(1), which, in pertinent part, states:
For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.
In Paul E. Lehman, Inc. v. United States, 230 Ct. Cl. 11, 673 F.2d 352 (1982), we held that a claim over $50,000 is not a valid claim and cannot be entertained by this court unless it has been certified. See also Troup Bros. v. United States, post at 707. Furthermore, the fact that the contracting officer considered the claim on the merits does not vitiate this requirement, as he "had no authority to waive a requirement that Congress imposed.” Lehman, 230 Ct. Cl. at 14, 673 F.2d at 356. We have also held that a contractor cannot retroactively meet this requirement — for the purpose of direct judicial review — by certifying the claim after the final decision of the contracting officer. W. H. Moseley Co. v. United States, 230 Ct. Cl. 405, 677 F.2d 850 (1982), cert. denied, 459 U.S. 836 (1982). See also Troup Bros.
As to plaintiffs first argument, lack of certification is indeed the proper basis for a dispositive motion, as evidenced by our decisions in Lehman, Moseley and TriCentral, Inc. v. United States, 230 Ct. Cl 842 (1982). Rule 38(b), cited by plaintiff, states that every defense shall be asserted in a responsive pleading, except (among others) lack of subject matter jurisdiction, which may be raised by motion. In Moseley we stated "certification of a claim * * * is a jurisdictional prerequisite to a direct challenge in this court of a contracting officer’s decision * * 230 Ct. Cl. at 406, 677 F.2d at 851.
Plaintiffs assertion that the certification required by the Act need not be in writing is clearly without merit. Section 605(a) states that all claims "shall be in writing,” and it clearly follows that the requirement in section 605(c)(1) that the contractor certify the claim must also be in writing.
I certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of my knowledge and belief; and that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable. (Contractor’s Name)_ (Title)_4
Finally, plaintiff argues that certain statements contained in its reproposal (suggesting modification of the contract) satisfied the certification requirement. Specifically, plaintiff asserts that the printed statements, in the "Contract Pricing Proposal” form, that the proposal "reflects our best estimates as of this date” and that the cost summary conforms with the principles set forth in agency regulations, constitutes certification of the claim. The requirement that the claim be made in good faith, plaintiff asserts, can be satisfied by the introduction of depositions testifying to representations to that effect made by plaintiffs officers.
It is clear from a reading of the statute and prior decisions of this court that we have no jurisdiction, under the CD A, to entertain an uncertified claim for over $50,000. What is perhaps not clear from our prior decisions is the consequences of a contractor’s failure to certify the claim. In our recent decisions in Lehman
Both Lehman and Moseley involved a situation where the contract in question was entered into before the effective date of the Act (March 1, 1979), and the contractor filed its uncertified claim after the effective date.
The importance of certification to the statutory scheme of the CDA is clear, and has been enunciated by the court in Lehman and Moseley.
A reading of our prior decisions leads to the conclusion that the failure to certify the claim submitted to the contracting officer should taint every "decision” that follows. As mentioned earlier, we have previously ruled that the fact that a contracting officer has rendered a decision on .the merits of an uncertified claim is of no consequence,
In sum, any proceedings on an uncertified claim — under the CDA — are of no legal significance. In such a case, as in this case, the review process simply has not begun. The proper course of action — for a contractor whose case is dismissed for lack of jurisdiction — is the following: (1) properly certify the claim; (2) resubmit the claim to the contracting officer; and (3) if there is then an adverse contracting officer’s decision, appeal either to the board (section 606) or directly to this court (section 609).
Hereafter, all section numbers refer to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (Supp. IV1980).
It should be noted that in Moseley and Troup Bros. the contractor certified (or proposed to certify) the claim after filing its petition in this court.
Also, section 605(cX2) states, "A contracting officer shall, within sixty days of receipt of a submitted certified claim over $50,000 * * (Emphasis added.)
This statement of certification is identical to the one set out in the Federal Procurement Regulations, 41 C.F.R. § 1-7.102-12 (February 19, 1980). Section 1-1.318-7 requires that the above clause be inserted in every contract to which the CDA applies. The clause was prescribed by the Office of Federal Procurement Policy on February 26,1979. See section l-1.318-8(2Xb).
Apparently plaintiff means to demonstrate compliance through oral certification.
In Lehman we stated: "The plaintiff seems likely to obtain a full and fair review of its claim before the Board, with the right to subsequent judicial review in this court of any unfavorable decision by the Board.” 230 Ct. CL at 17, 673 F.2d at 356.
In Moseley we stated: "The court in Lehman directed the plaintiff to a relevant board of contract appeals, with the right to subsequent judicial review in this court.” 230 Ct. Cl. at 408, 677 F.2d at 852. This statement strongly implied that the plaintiff in that case could follow the same procedure as the plaintiff in Lehman.
See Folk Constr. Co. v. United States, 226 Ct. Cl. 602 (1981), where we held that when a contracting officer issues a decision after the effective date of the Act on an uncertified claim submitted prior to that date, a contractor may proceed under the Act and appeal directly to this court.
The CDA states that with respect to pre-March 1, 1979 contracts, "[notwithstanding any provision in a contract made before the effective date of this Act, the contractor may elect to proceed under this Act with respect to any claim pending then before the contracting officer or initiated thereafter.” Pub. L. No. 95-563, § 16,92 Stat. 2391,41 U.S.C. § 601 note (Supp. IV1980).
But cf. Tuttle/White Constructors, Inc. v. United States, 228 Ct. Cl. 354, 656 F.2d 644 (1981), where we held that a contractor who first filed an appeal to the board (under a pre-Act contract) has made an election to proceed under pre-Act (disputes clause) procedures, and could not, therefore, file a direct access suit in this court. Conceivably, a board could use this same rationale to bar an appeal after we dismissed a direct access claim because of failure to certify the claim. For elections involving a choice of forums under the CDA, see Santa Fe Engineers, Inc. v. United States, 230 Ct. Cl. 512, 677 F.2d 876 (1982), where we found that the Act authorizes the alternative forums as an "either-or” proposition — i.e., once a contractor elected to appeal to the board, it could not seek judicial review under the direct access provisions (where the contractor was adequately apprised of its options under the CDA). However, since we hold that where a contractor has not certified the claim, the review process has not begun (see discussion later in text), no valid "election” has taken place. As a consequence, a contractor — who resubmits a certified claim to the contracting officer for a new (valid) decision — should not be foreclosed from appealing such a decision under either of the alternative routes.
Another (potential) obstacle to going directly to the board after dismissal by this court is the period of limitations for filing an appeal of a contracting officer’s decision. Under pre-Act procedures, a contractor (generally) has 30 days in which to appeal an adverse contracting officer’s decision to the board. In most instances, then, a board could dismiss such an appeal for lack of timeliness. Whether or not the board decides to waive this requirement would be a matter within the board’s discretion, absent abuse of that discretion. Linair, Inc. v. United States, 219 Ct. Cl. 654 (1979); Tapper v. United States, 206 Ct. Cl. 446, 514 F.2d 1003 (1975).
In brief, certification plays a serious role-in the statutory scheme because it triggers a contractor’s potential liability for a fraudulent claim under section 604 of the Act. It is also designed to "discourage the submission of unwarranted contractor claims and to encourage settlements.” Folk Constr. Co., supra, n. 8.
That a board may indeed refuse to hear a claim because of lack of certification was recognized by the court in Lehman, which cited with approval decisions of the Armed Services Board of Contract Appeals and Defense Acquisition Regulations to that effect. 230 Ct. Cl. at 16, 673 F.2d at 355.
Further support for the statement that a contracting officer does not have the authority to issue a decision on an uncertified claim is contained in the Federal Procurement Regulations, which state that a claim over $50,000 "must be certified * * * before settlement or decision on the claim * * (Emphasis added.) 41 C.F.R. § 1-1.318-3 (February 19,1980).
See White Plains Iron Works, Inc. v. United States, 229 Ct. Cl. 626 (1981), where we remanded a claim (certified subsequent to the filing of the petition) under the CDA to the contracting officer, under the authority of section 605(cX5). In White Plains, unlike the present case, no decision (valid or not) was ever issued by the contracting officer. Since we hold that a contracting officer does not have the authority to issue a decision on an uncertified claim (under the CDA), a similar remedy would seem to be appropriate in this case. However, the authority under section 605(cX5) to "stay the proceedings to obtain a decision on the claim by the contracting officer” appears to be predicated on the failure of the contracting officer to issue any decision at all within