51 Md. 83 | Md. | 1879
delivered the opinion of the Court.
This is an action brought by the appellants against the appellees, for an alleged balance due on contract for extra work on the new City Hall in the City of Baltimore.
The appellants were the contractors for supplying the marble and doing the marble work'on the new City Hall; and the marble was furnished and the work all done in accordance with the requirements of the contract. The work and materials were all accepted by the appellees, through their Building Committee, and the contract price, amounting to a sum between $900,000 and $1,000,000, was paid, according to the terms of the contract, excepting only the price for the extra work which had been done.
In the specifications for the building, in reference to which the proposals of - the appellants for the work were made, and which proposals are referred to and made part of the contract between the parties, this provision occurs: “All extra work, additions or omissions, not referred to in the following lists, shall be valued by the architect, with reference and in proportion to the contract price.’'
Having thus adjusted the question in regard to the extra work, there was still another question of difference between
This being the state of the case, there are two questions presented: 1. Whether the appellants are concluded by their acts in reference to the award of Mullett, the referee, upon the claim for the extra work; and, 2. Whether they are bound by their agreement that the cost of the railway track should be retained out of the money found to be due them by the award. The Court below determined both these questions against the appellants, and consequently rejected all their prayers, and the judgment was for the appellees.
1. The theory upon which the action is sought to be maintained in respect to the extra work is, that the reference and award were not binding upon the appellants; that they were not binding upon the appellees, because the submission or reference was not made by competent authority; and that being so, there was no mutuality in the agreement of reference, and consequently the award was simply void, and the amount ascertained by Frederick remained the amount to which the appellants were entitled. But, according to our apprehension, the case does not depend upon the abstract question, whether the appellees were bound by the submission, nor whether the appellants were bound by the award before it was acted on and made the basis of settlement, and the money received under it; but the real question is, whether the Building Committee had the right to raise the question of difference with the appellants, and if so, whether, after resorting to the amicable means of a reference, in order to settle the question, and the appellants have acquiesced in the result of that reference, and received the money ascertained to be due by the award, they can now repudiate it, and fall back upon the claim for the amount ascertained by Mr. Frederick before the reference was made P The law always favors compromises and amicable adjustments of
The Building Committee represented the city under ordinance No. 78, approved 5th August, 1868, providing for the erection of the New City Hall; and they were clothed with large supervisory powers, as well in regard to the making of contracts as to their faithful execution; and no money could he paid to any contractor for work on the building, unless he produced an order from this committee certifying that it was justly due. By the 6th section of the ordinance, it was expressly provided that the Register, of the city should pay the different contractors such amounts as might become due on their contracts, upon the production of an order for the same, duly signed by the Superintendent and a majority of the Building Committee, stating that the money was legally and justly due, and certified to as being correct by the City Comptroller. If, upon the measurement and valuation of the extra work by the regular architect, the Building Committee had reason to believe that it was not correct; that it was excessive, and largely to the prejudice of the city, their plain duty required them to withhold their approval of such measurement and valuation, and to refuse the order stating that the amount as ascertained was legally and justly due. How then was the matter to be dealt with ? What mode better than, by mutual consent, to invoke the aid of some competent person to revise the measurements and calculations of the regular architect, as a means to a just and satisfactory settlement of the question ? This was done by the reference, and it was not only voluntarily done, but the appellants, and also the regular architect, Mr. Frederick, attended the referee and furnished him the necessary data to enable him to make his award. The
2. Then, as to the cost of the railroad track retained by the Building Committee, with the consent of the appellants, from the amount ascertained to be due for the extra work. As we have already stated, it is not disputed that the appellants used the road for the delivery of their material, and that the city was under no obligation to the contractors to make or pay for the road. It authorized the making of the road, and paid the Northern Central Railroad Company the cost of construction; but it insisted that as the road inured to the benefit of the appellants they should pay for it. This was certainly a proper question for adjustment between the parties concerned; and, as was said by the Supreme Court of the United States, in the case of Sweeny vs. U. S., 17 Wall., 75, 78, “Parties may adjust their own disputes, and when they do so voluntarily and understandingly, no appeal lies to the Courts to review their mutual decision.” There is no suggestion here that
In view of these well settled principles of the law, we think the Court below was entirely right in rejecting the several prayers offered by the appellants, and in entering judgment for the appellees, and that judgment will be affirmed.
Judgment affirmed.