25 S.D. 36 | S.D. | 1910
The defendant board of education is a ■public school corporation. It contracted with its codefendant, J. J. Olsen & Son, for the erection of a school building. Olsen & Son entered upon the contract, and, when the building was partly completed, they failed in their contract, and the building was completed by the school corporation. Plaintiffs are, all subcontractors who -furnished to Olsen & Son material for such building. Plaintiffs each brought an action against -the above-named defendants, naming as codefendants the other parties now joined
There are several assignments of error in the record herein that are not discussed by appellants and may be considered as abandoned. The main question involved is one of interpretation -of a certain statute in connection with the terms of the contract that existed -between the school corporation and the contractors, and, in the view which we take as to the proper construction of such statute and contract, all other questions covered by -the assignments of error become immaterial.
It will be ’ unnecessary to set o-ut such contract in full; the material provisions being as follows: The contract price for erection of building was $66,475, and -changes were agreed to' increasing -this to $69,2x0.52. After work commenced on the building, -the supervising architect, twice a month, was to make an estimate as to -the value of the material and labor which shall actually have entered into the construction of said building and the materials which shall have been delivered upon the grounds since the last preceding estimate. Such material so delivered became the property of -the school corporation. After an estimate was so made by the architect, the corporation, upon demand of the contractor, was -to- pay such contractor 80 per cent, of such estimate. “The balance of twenty per cent, shall be retained by the •said second party [corporation] and shall be paid after the full and satisfactory completion of said building and after all claims for labor or materials furnished in, upon or for said work shall have been discharged and released.” The contract had -the usual provisions whereby the contractor agreed -to save the corporation from any liens of subcontractors, and also contained a provision
Estimates were made from time to time by the architect and the 8o- per cent, thereof paid the contractors; -the amount of such estimates reserved under the 20 per cent, provision being over $ii,qoo, which is more than thfe aggregate of the several plaintiffs’ claims. This was the 'situation when the contractors failed in their contract and the work was taken up by the corporation. The several appellants proceeded to file liens under the provisions of article 2, c. 31, Rev. Code Civ. Proc. being sections 713 to 721 of such Code. Section 713 of such Code is as follows: “Every person who shall perform any labor or furnish any material for the construction or repair of any work for any county or municipal or public school corporation in this’ state to any person who shall have made any contract for such work with such corporation, upon complying with the provisions of this article shall have for his labor done or material furnished a lien upon all moneys in the control of such corporation due or to become due under such contract.” Section 714 provides that such lien shall be filed within 20 days after labor performed or material furnished, but that failure to file within such time “shall not defeat the lien upon the amount remaining due to the contractor at the time of filing.” The several plaintiffs failed -to file within the 20-day period, but did file their Mens before, the payment of the above $ir,ooo to any one. In completing the building the corporation expended much more than the excess of the contract price over what had been paid the contractors.
It is the contention of the appellants that their liens attached to the said $11,000 fund it being the 20. per cent, reserved from such estimates, and that such liens were superior to' any rights of the corporation in such fund, and that the corporation must satisfy such liens regardless of the cost of completing the building. The appellants have cited several au
We have examined carefully the authorities' cited by appellants, and find nothing in any of them to support appellants’ contention, while some of them support respondent. Our statute clearly comes under what is known as the “New,York ’system,’’ and a very clear statement of the law thereunder is to be found in 27 Cyc. pp. 101 to 104. The case of Kelly v. Bloomingdale, 139 N. Y. 343, 34 N. E. 919, is directly in point, as the facts were practically identical with those in case at bar. The court in that case said: “lie filed a notice of lien for these amounts on the 8th of August, 1890. The plaintiff’s appeal raises the question whether at that date there was anything due to the contractor under the conraot, not absorbed by prior liens, to which lien could attach. The main contention on the part of the plaintiff, and the only one necessary to notice, is that, when his lien was filed, 20 per cent, of the cost or value of the work done, and materials furnished, up to' that time, remained unpaid by the owners, and that, as they have had the benefit of this work and material, a lien was impressed upon that sum, amounting to about $1,400, in favor of the plaintiff. This proposition cannot be sustained. The 20 per cent, was, by the contract which the owners made with the contractor, to be retained by them till the final completion of the contract. It never was completed, and hence this part of the price never became due to the contractor, and his subcontractors have no other or different claim to it than he would have. It was retained in order to secure the owners from loss by the contractor’s default, and the right to demand it by any one depended upon the substantial performance of the contract — a condition which was never fulfilled. Even with this sum retained, the owners still were at a loss on account of the default, as they paid in all a sum greater than the price agreed upon. Under such circumistanees, there is nothing in the statute, or any rule of equity, that will compel the owners to pay the plaintiff’s claim.” We would also cite in full support of re
What we have said above is perhaps sufficient to dispose of this cause; but appellants have urged that, inasmuch as respondent is shown to have not paid to the contractors the full contract price, and the building is shown to have been completed, the burden was on the respondent to show that it lawfully expended enough in completing the building so that no part of the contract price would be due the contractors. We think the evidence sufficient to show such expenditure on the part of respondent. Moreover, the burden was on the appellants to prove their right to recover, and, it having been proven that nothing was due the contractors when they ceased work under their contract, appellants were bound, in order to recover, to show that at some time thereafter, and while their liens were on file, there became some sum due to the contractors. Brainard v. County of Kings, 155 N. Y. 538, 50 N. E. 263.
The judgment of the trial court and order denying a new trial are affirmed.