Action to recover damages for breach of contract. The appeal is prosecuted by defendants from a judgment rendered for plaintiff on a verdict of $375. The contract was oral and at the time it was made plaintiff was an architect employed by a firm оf architects in Kansas City. Defendants decided to erect a large building on property owned by them in the business district of Kansas City and after looking at rough plans submitted by plaintiff agreed to еmploy him to prepare the plans and specifications. Plaintiff had the consent оf his employers to take the employment on his own account as a side job. The consideration he was to receive was below the price usually charged by architects for such work. Defendants do not deny the employment, but claim that plaintiff agreed to open an office of his own where they might transact business with him without embarrassment and that they did not discharge him until after he had broken this agreement. Plaintiff denies making such agreement and contends thаt defendants knew he would remain with his employers and used that fact to beat him down in his price, аrguing that “as you are doing it on the side, it will be like finding money.” Defendants discharged plaintiff after he had partly performed the contract and employed other architects.
The prinсipal instruction given at the request of plaintiff was as follows: “If you believe from the evidence that the plaintiff and the defendants entered into an agreement by which plaintiff was to рrepare plans and specifications for a building for them at Ninth and Oak streets in Kansas City, Missouri, and defendants were to pay him for such services the sum of $375, and that plaintiff undertook to perform such agreement, but was prevented from completing it by the defendants without fault on his part, and that the plaintiff was
The first contention of defendants in substance is that the evidence adduced by them so greatly preponderates over that of plaintiff that its version оf. the transaction should be accepted as conclusively established. We disagree with this view of the evidence. We regard the evidence of plaintiff „ as substantial enough to tеnder the issue with respect to every fact constitutive of the cause of action аsserted and since it is not one of our functions to weigh conflicting evidence, we must decline to interfere with the judgment on the ground that the evidence is insufficient to support it. The objection to the instruction we have quoted is that it was too general in the directions relating to the measure of damages. It is argued that “instructions on the measure of damages where they are given at all should be right and tell the jury what elements enter into the measure of damages аnd then limit them in making their verdict to such elements. The instruction in the case at bar laid down no rule fоr the guidance of the jury on the measure of damages.” Among the cases cited in support of this position are the following: Sherwood v. Railroad,
These cases do support thе rule contended for by plaintiff, but in being distinguished by the Supreme Court in later cases, they have been practically overruled. [Dunn v. Northeast, etc., Co.,
Nor do we agree with dеfendants that the verdict is excessive. Prima facie, plaintiff, discharged while in the performаnce of the contract and without fault on his part, was entitled to recover the cоntract price as though he had fully performed the contract. The burden was on the defendants to plead and prove mitigating facts. They failed completely to discharge this burden and the verdict cannot be pronounced excessive. [26 Cyc. 1064; Hildebrand v. American, etс., Co.,
Respondent invokes the rule that “there can be no mitigation where the plaintiff is a professional man and is to be paid a fixed price for сertain work.” [McElhinney v. Kline,