(after stating the facts). — It is argued by appellant and we are cited to Lloyd on Building (2 Ed.), sec. 68, where the learned author says: “Where a breach consists in a failure to erect a building as agreed, the measure is the additional value which would have accrued to the land.” We have taken pains to examine closely all of the cases cited by the author in support of the text above stated and find that many of those cases were controversies between a landowner and a railroad company arising by virtue of an obligation on the part of a railroad to maintain a depot on or at the plaintiff’s premises. In some of those cases, plaintiff had conveyed to the railroad a right of way and depot grounds in consideration of its erecting and maintaining a depot thereat and in others, the railroad had sold plaintiff grounds for hotel purposes, agreeing to maintain a depot adjacent thereto-. Upon these facts, the courts hold the covenant as running with the land, and upon suits for a breach of the covenant in failing to maintain, or in removing the depots provided for, have universally held that inasmuch as the maintaining of such depots in connection with the railroad would necessarily enhance the value of the lands, and that this was an element in contemplation of the parties when the contract was made, that the true measure of damages in such case would be the difference in value of the land with the depot standing as provided by the contract and with the depot removed therefrom; or in other words, as plaintiff had parted with the right- of way and depot grounds in consideration that a depot was- to be established, which would enhance the value of their remaining lands, that the measure of their recovery should be such increased value occasioned by the location of the depot thereupon. [Mobile, etc., Ry. Co. v. Gilmer, 85 Ala. 422; Louisville, etc., Ry. Co. v. Sumner, 106 Ind. 55; Watterson v. Ry Co., 74 Pa. 208; Houston, etc., Ry. Co. v. Molloy, 64 Tex. 607.] No case can be found by us in the books where, for a breach of a builder’s con
We cannot agree with appellant’s contention that the measure of damages in this case is the difference between the value of the land without the .buildings and the value thereof with the buildings erected thereon in accordance with the contract. If this were the measure of damages, it might be that one owning land would contract for the erection of a building much desired by the owner yet of such a character as not to enhance the value of the land and, in fact, depreciate the market value thereof. Upon a breach, the contractor could confess his fault, defend against and defeat a recovery upon the ground that the value of the real estate would not be enhanced by the erection of the buildings. Therefore, it has been well said that: “A man may do what he will with his own, having due reg’ard to the rights of others, and if he chooses to erect a monument to his caprice or folly on his premises, and employs and pays another to do it, it does not lie with the defendant who has been so employed and paid for building it to say that his own performance would not be beneficial to plaintiff.” [Chamberlain v. Parker, 45 N. Y. 569; 3 Sutherland on Dam. (3 Ed.), 697.]
The case of Real Estate Co. v. MacDonald, 140 Mo. 605, much relied upon by appellant in this behalf, is not in point here. In that case defendant had purchased from plaintiff certain grounds partially on credit, giving a deed of trust thereon and a certain bond for $35,000, which bond obligated defendants to erect buildings of the value of $35,000 thereon. One of the conditions of the sale on the partial credit extended was that
It is to be observed that the court passed upon that case, being properly guided by the matters within the contemplation of the parties at the time the bond was executed, that is, the enhancing of the value of the security for the deferred payments of the purchase price which was secured by the deed of trust mentioned, and that case is unlike the case at bar. This measure, applied to the case in decision here, would be violative of that general rule and fundamental principle of the law of damages, resting upon the idea of compensation for the wrong done which seeks to compensate for the thing contracted for. [8 Am. & Eng. Ency. Law (2 Ed.), 635; The Pittsburg Coal Co. v. Shaeffer, 59 Pa. St. 365; Amer. Surety Co. v. Woods, 105 Fed. 741; 3 Sutherland on Dam. (3 Ed.), 697.]
We find that when a'contractor, as in this case, has, first, wholly failed to perform any part of his contract; or second, when he has partially completed and abandoned the building; or third, when he has substantially completed the building, not in accordance with the contract, the same being insufficient and defective in workmanship, skill or material furnished, when measured by the requirements of the contract, and there being no waiver on the part of the employer, that in either of
(a) The true measure of which recovery in the first instance, if the contractor has been paid in advance for the building, is the value of the building when completed in accordance with the contract.
(b) If he has not been paid in advance for such building, the measure of recovery is the. difference in the price at which the contractor agreed to erect the building and the reasonable cost to or the reasonable expenditure of the owner or employer in erecting the building in accordance with the contract requirements.
This is true because, by virtue of the contract, the employer is entitled to a building at the hands of the contractor for the price therein agreed upon and upon the contractor defaulting and refusing, doing no act toward performance, the owner has the undoubted right to erect such a building and if it reasonably costs him more than the price at which the defaulting contractor was to erect it, he should, in justice, be reimbursed by the contractor for the additional expenditures which the defaulting contractor, by his wrongful act, has entailed upon him. [Laraway v. Perkins, 10 N. Y. 371; Chamberlain v. Parker, 45 N. Y. 569; Taylor v. Ry. Co., 56 Calif. 317; Cincinnati, etc., Ry. Co. v. Carthage, 36 Ohio St. 631; Morrell v. Ry. Co., 15 Daly (N. Y.) 127; Mayor, etc., N. Y. v. Ry. Co., 102 N. Y. 572; Gray et al. v. Reed et al., 65 Vt. 178; City of Sherman v. Connor, 88 Tex.
(c) The measure of recovery in the second instance for completing the unfinished building and in the third instance, for bringing up to the contract requirements the substantially yet defectively completed building, is the difference in the value of the partially completed building when abandoned by the contractor, or the substantially and yet' defectively completed building and the reasonable cost or value of the building completed in accordance with the requirements of the contract. [Haysler v. Owen, 61 Mo. 270-274; Hirt v. Hahn, 61 Mo-. 496-498; Spink v. Mueller, 77 Mo. App. 85-93; McCormack v. Lynch, 69 Mo. App. 524-529; Fairbanks, etc., Co. v. DeLissa, 46 Mo. App. 711-722; Fletcher v. Wilburn Mfg. Co., 35 Mo. App. 321-328; Wright v. Sanderson, 20 Mo. App. 534-541; Springfield Milling Co. v. Barnard, etc., Mfg. Co., 81 Fed. 261-266; Sunman v. Clark, 120 Ind. 142; Pittsburg Coal Co. v. Shaeffer, 59 Pa. St. 356; Carroll et al. v. Caine, 27 Wash. 402; Village of Brighton v. Auston, 19 Ont. Rep. 305; 3 Sutherland, Dam. (3 Ed.), sec. 299; 1 Sutherland on Dam. (3 Ed.), sec. 91.]
It will be observed that in stating the above rules, we have said the owner or employer was entitled to recover the reasonable cost of erecting the building or completing the building in accordance with the contract. There are authorities holding to the broad statement that a recovery can be had by the employer or owner for the actual cost or expenditure of completing the contract. We are inclined to the opinion that the better rule, that borne out by the most carefully considered cases and the most eminent authorities, is as stated in 1 Sutherland on Damages (3 Ed.), sec. 91: “A party to a contract which has been broken by the other, has a
The learned trial judge did not err in permitting respondent to prove the reasonable cost of erecting the building provided for under the contract.
It is said that the damages for breach of contract, admeasured by the rules above stated, are obviously just and proper and that such rules furnish a proper standard by which to measure the employer’s damages because the building, completed in accordance with the contract, is exactly what the employer is entitled to and thus the principle of compensation is met and satisfied and by the process of computing damages therein provided for, the contractor obtains just what his untouched work or unfinished work or his defective work is worth and he cannot complain. 3 Sutherland on Damages (3 Ed.), sec. 699.
As to the contention that recovery cannot be had until the employer has erected the building and ascertained definitely the cost thereof, it is laid down as a rule in 3 Sutherland on Damages (3 Ed.), sec 699, that: “In such cases the employer is generally entitled to measure his damages by what the necessary expense would be to procure to be done the work which the contractor neglected to do, whether it is done or not; for the same reason that a vendee in an executory contract for the sale of goods need not, in fact, purchase the goods he was entitled to receive from the vendor in order to have his damages computed on the basis of what they would cost him at the time of the breach.” In American Surety Co. v. Woods, 105 Fed. l. c. 746, the court said: “Where the employee or contractor without legal causé abandons the work, unfinished, the right of the employer to sue for the breach of the contract is not dependent on his completing the abandoned work. He may sue at once and recover of the employee or contractor such damages as under legal rules, he can show he has sustained.”
It will be observed that the evidence in this case on the reasonable cost of erecting the buildings was as to the reasonable cost at the time of the contract and the case was not rendered one of that uncertain class by indefinite testimony as to what might be the cost of the building some time in the future,, which would necessarily depend upon the fluctuating prices of labor and materials and therefore render the ascertainments uncertain, indefinite and conjectural to a great extent. The authorities are abundant sustaining the right of the employer to sue for his damages before erecting the buildings, as is shown by the following cases: King v. Nichols, 53 Minn. 453; Cincinnati, etc., Ry. Co. v. Carthage, 36 Ohio St. 631; Taylor v. Ry., 56 Calif. 317; Laraway v. Perkins, 10 N. Y. 317; Hawley v. Florsheim, 44 Ill. App.
The petition, after prefatory allegations alleging the contract, etc., alleges the breach thereon as follows:
“Plaintiff states that defendant has failed and refused to comply with his said contract to erect said cottages for said sum of $3,300 and has renounced his said contract and has informed plaintiff that he will not comply with same, or with any part thereof. Plaintiff states that defendant’s failure to comply with his said contract to erect cottages for said'sum entails a great loss upon plaintiff; that he has given public notice and has received bids for said construction of said cottages, and that the lowest bid submitted amounts to $3,860, which sum is the least at which the erection of said cottages can be procured; that defendant’s failure to comply with his contract entails a loss upon this plaintiff of five hundred and sixty dollars, for which sum plaintiff prays judgment and for costs.”
Under this allegation, the trial court permitted the respondent to prove what would be the reasonable cost of erecting the buildings and that such cost would be actually $300 more than the price at which plaintiff had contracted to erect them and thus arrived at the measure of damages. Appellant contends that inasmuch as there was no allegation of the reasonable cost of the buildings in the petition, that the court erred in admitting such testimony. Under our code, a plain and concise statement of the facts constituting plaintiff’s cause of action, provided, of course, the relief prayed thereon is in accordance with the rules of the law, is all that is required of the pleader. The petition states the facts constituting the cause of action in a plain and concise manner and then goes somewhat into detail and shows that respondent took some pains by advertising, etc., in order to discover just how much it would cost him to have erected the buildings for which he had contracted and just Avhat was the value of the buildings he Avas entitled
It is contended by appellant that inasmuch as the wife of the respondent owned the lands upon which the buildings contracted for were to be erected, therefore any damages resulting from a breach of such contract would be damages accrued to the wife, the real owner, and not to this respondent, therefore respondent cannot recover. This contention is based largely upon appellant’s other contention pertaining to the measure of damages, that the damages resulting from the failure to erect the buildings was damage to the realty and that the true measure thereof was the difference in value of such real estate with and without the buildings thereon. This proposition having been settled against him, we take it that the last contention now under consideration would not be seriously insisted upon. The contract sued upon is a personal obligation between appellant and respondent in this case. Respondent had the right, if he saw fit, to contract for and have erected on the lands of his wife, the several houses mentioned, and donate them to his wife. The relationship of husband and wife is a sufficient consideration therefor and besides, he would necessarily receive the indirect benefit therefrom by vir
“An executor or administrator, a trustee of an express trust, or a person expressly authorized by statute, may sue in his own name without joining with him the person for whose benefit the suit is prosecuted. A trustee of an express trust, within the meaning of this section, shall be construed to include a person with whom or in whose name a contract is made for the benefit of another.” [R. S. 1899, sec. 541.]
If appellant’s' contention that the wife is the real party in interest under this contract, is correct, then un
The case was well and carefully tried. Finding no error in the record, the judgment is affirmed.