Simon v. Granite Bldg. 2, LLCSimon v. Granite Bldg. 2, LLC
Published by New York State Law Reporting Bureau pursuant to
This opinion is uncorrected аnd subject to revision before publication in the Official Reports.
Decided on March 27, 2019
SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
WILLIAM F. MASTRO, J.P. JEFFREY A. COHEN JOSEPH J. MALTESE LINDA CHRISTOPHER, JJ.
Charles Simon, etc., plaintiff-respondent, v Granite Building 2, LLC, defendant-appellant-respondent, Kulka Contracting, LLC, defendant-respondent-appellant, FXR Construction, Inc., dеfendant-respondent, et al., defendants.
Quirk and Bakalor, P.C. (Shaub, Ahmuty, Citrin & Spratt, LLP, New York, NY [Timothy R. Capowski and Sofya Uvaydov], of counsel), for defendant-appellant-respondent.
Armienti, DeBellis, Guglielmo & Rhoden, LLP, New York, NY (Harriet Wong and Vanessa M. Corchia of counsel), for defendant-respondent-appellant.
Rosenberg & Gluck, LLP (Pollack, Pollack, Isaac & DeCicco, LLP, New York, NY [Brian J. Isaac and Michael H. Zhu], of counsel), for plaintiff-respondent.
White Fleischner & Fino, LLP, New York, NY (Nancy Davis Lewis of counsel), for defendant-respondent.
DECISION & ORDER
In an action to recover damages for personal injuries and wrongful death, the defendant Granite Building 2, LLC, appeals from (1) an order of the Supreme Court, Nassau County (Jeffrey S. Brown, J.), entered April 26, 2016, (2) an order of the same court entered September 13, 2016, and (3) a judgment of the same court entered March 23, 2017, and the defendant Kulka Contracting, LLC, cross-appeals from (1) the order entered April 26, 2016, and (2) the judgment. The order entered April 26, 2016, insofar as аppealed and cross-appealed from, denied those branches of the appellants’ separate motions which were pursuant to
ORDERED that the
ORDERED that the appeals from the order entered April 26, 2016, and from so much of the order entered September 13, 2016, as denied that branch of the motion of the defendant Granitе Building 2, LLC, which was for leave to renew are dismissed; and it is further,
ORDERED that the judgment is affirmed insofar as appealed from; and it is further,
ORDERED that one bill of costs is awarded to the plaintiff.
The appeals from the order entered April 26, 2016, and from so much of the order entered September 13, 2016, as denied that branch of the motion of the defendant Granite Building 2, LLC (herеinafter Granite), which was for leave to renew must be dismissed because the right of direct appeal therefrom terminated with the entry of judgment in the action (see Matter of Aho, 39 NY2d 241, 248). The issues raised on the appeals from the order entered April 26, 2016, and from so much of the order entered September 13, 2016, аs denied that branch of Granite‘s motion which was for leave to renew are brought up for review and have been considered on the appeal from the judgment (see
The plaintiff and his wife (hereinafter the decedent) were hired to hang wallpaper in a newly constructed offiсe building, which was owned by Granite. Kulka Contracting, LLC (hereinafter Kulka), had contracted with Granite to perform as the site construction manager. The incident giving rise to this action occurred at approximately 8:30 a.m. on February 13, 2008, the day the plaintiff and the decedent were scheduled to commence work in the building. While it had been snowing on February 12, 2008, the day before the accident, in the early morning hours of February 13, 2008, the snow changed to rain. It was raining on the morning of February 13, 2008, when the decedent drove her vehicle, with the plaintiff as a passenger, to the job site. When the plaintiff and the dеcedent were unable
The plaintiff, individually and as the administrator of the decedent‘s estate, subsequently commenced this action against, among others, Granite and Kulka to recover damages for personal injuries and wrongful death, alleging, inter alia, violations оf
Granite moved, inter alia, pursuant to
In an order dated April 22, 2016, the court denied the motions
“A motion pursuant to
We agree with the Supreme Court‘s denial of those branches of the defendants’ motions which were pursuant to
Contrary to Kulka‘s contention, the fact that it was the construction manager at the site did not absolve it of owing a duty of care to the plaintiffs, and entitle it to judgment as a matter of law dismissing the
Here, viewing the evidence in the light most favorable to the plaintiffs, and affording them every inference which may properly be drawn from the facts presented, a rational jury could have found that Kulka functioned as a general contractor having control over the work site, and possessed actual or constructive notice of the dangerous conditions that caused the accident, and was negligent with regard to keeping the premises safe. The jury made a credibility determination that, even though Kulka was designated a “construction manager,” it also acted as a general contractor. The jury‘s resolution of this credibility issue against Kulka is entitled to deference (see Lalla v Connolly, 17 AD3d 322, 323). The testimony demonstrated that there was no general contractor at the site, and that Kulka, as construction manager of the property, took on duties of a general contractor, and was responsible to make sure the job site was safe and to make recommendations regarding safety. Also, Kulka was aware the fence had been opened, and was also aware that at this stage of the construction the drains could be covered.
Contrary to the defendants’ contention, the reduced awards totaling $3,000,000 to the plaintiff for his past and future pain and suffering, and the award of $500,000 for the decedent‘s pre-impact terror, do not deviate materially from what would be reasonable compensation (see
Any error in the admission of certain testimony and jury instructions is harmless, as we are satisfied that the result would have been the same if the alleged errors had not occurred (see Rosenberg v Jing Jiang, 153 AD3d 744, 745;
The defendants’ remaining contentions either are without merit or have been rendered academic in light of our determination.
MASTRO, J.P., COHEN, MALTESE and CHRISTOPHER, JJ., concur.
ENTER:
Aprilanne Agostino
Clerk of the Court