47 N.Y.S. 360 | N.Y. App. Div. | 1897
The action is founded on an alleged breach of the contract by the defendant. •
The plaintiffs by their complaint charge:
• 1. That they, having nearly completed the work under the first or-causeway contract, were, on or about June 29, .1895, prevented by the defendant from' proceeding further in the fulfillment of it, and that the defendant had failed to make payments to which the plaintiffs were entitled.
. 2. That the plaintiffs had also nearly completed the work under the other or bridge contract when they, at the same time) were wrongfully prevented from proceeding further with it, and that the defendant refused to pay them.
3. That the plaintiffs performed extra work upon the causeway, for which they are entitled to recover.
• 4. That they also performed extra work upon the drawbridge^ .
The alleged breach of the contracts on the part of the defendant mainly arises out of the fact that, during the progress of the work, and on June 29, 1895, the defendant, by its president, addressed and sent to the plaintiffs a telegram, of which the following is a copy: “Your men quit work Thursday; have instructed Smith to finish road under your contract.” The name subscribed to the telegram was Geo. 0. Band, who was such officer. Thomas D. Smith was the engineer who had been selected by the defendant. This was Saturday, and thereafter the plaintiffs did no more work upon the causeway job) but the defendant, on the second day of July, took charge of it and proceeded with its completion. For that purpose the men and tools theretofore in the service of the plaintiffs were employed by the defendant. This taking possession of the work to finish it, the defendant alleges, was pursuant to the provision of the contract, to the effect that in case the plaintiffs failed to supply a sufficiency of materials or workmen the defendant should have the power, on three days’ notice, to provide them, complete the work and deduct the expense from the amount of the contract. The defendant also alleges that the expense of its accomplishment exceeded the amount of the contract price remaining unpaid to the plaintiffs. ■
Whether or not the defendant was, by any fault of .the plaintiffs,
Of course the amount chargeable and expended under the contracts could not exceed the compensatory sums provided for by them, nor is it claimed that the expense incurred in the performance of the work specified in the'contracts exceeded such sums; but including the expenditures for extra work on the causeway, the evidence on the part, of the plaintiffs tended to prove that they amounted to $15,519.16, of Which the sum of $4,660 was- expended for what the plaintiffs’ evidence tended to prove was extra- work.. The. plaintiffs received from the defendant on account of their work on the causeway $8,241.16... They also claim, and evidence on their-part was given tending to prove, that the drawbridge- was substantially completed by them prior to July 2, .1895, and that, they had expended $1,300 in its construction, and having received on account of that work $700, they claimed the right to the allowance - of the further sum of $500, the residue of the contract,price for the construction of the bridge, and the further sum of $72.40 for extra work. In addition to this, the plaintiffs claim by their evidence that the expenses incurred by them, in consequence of the delay to which they were subjected as before mentioned in the outset, were $650, of which amount they were paid $340 by the defendant on that account,
The matter of extra work which the ¡ffaintiffs claimed to have performed, was the subject of controversy at the trial. And the evidence on the part of the defendant was to the effect that the value of the work done and materials furnished by the plaintiffs upon the causeway was only $9,448, and on the drawbridge $860, and that the defendant expended in completion of the causeway upwards of $5,000 after taking possession of the work, and that the work to be done to. complete the bridge and remedy the. defects would' cost $1,020. Of the sum so expended by the defendant upon the causeway, $3¡,600 were paid to Murray and De Mott, who in May,
The court charged the jury that if they found from the evidence ■ that the “ plaintiffs were not in fault, but that they prosecuted the work with reasonable diligence, and that the defendants unwarrantably and without cause, as contemplated by the contract, took possession of the work and excluded the plaintiffs from it, then the plaintiffs are entitled to recover the amount actually expended by them upon the work under the contract,” less the amounts which they had received under it. Exception to this charge was taken by the defendant’s counsel, who requested the court to charge that if the jury so found, and that the plaintiffs elected to rescind the contract, then the measure of damages claimed by them in the first cause of action was the actual value of what had been done under the contract, less payments made to them. This was declined by the court, and, thereupon, the defendant’s counsel excepted and made the further request to charge “that such actual value is not determined by what the plaintiffs have paid therefor, but by the testimony of those competent to value work of the kind and character in question.” This Was also declined arid exception taken.
In such case the contractor may seek relief upon the quantum meruit for the work done, and such is a proper remedy. (Clark v. Mayor, etc., 4 N. Y. 338.) The purpose of the remedy in such case is to enable him to obtain indemnity by way of damages for the loss, legitimately suffered by him in consequence of the breach of the con- • tract, and there would seem to be reason for the support of the rule which will permit him to prove as the basis of damages what he has fairly and reasonably expended in the performance of or under the contract. (United States v. Behan, 110 U. S. 338; Watts v. Board of Education, 9 App. Div. 143.) This is a method of proving the
It is urged-with some force that the jury would have been warranted in finding that the plaintiffs acquiesced in the taking from them of the- control of the work and the proceeding with it by the defendant, in such sense as to relieve the latter from the charge of
The learned counsel for the defendant urges upon our attention the question arising upon the refusal of'the court to charge “that if the jury find that up to June 29th was ample time to allow plaintiffs to finish the contract and further find the work was not then completed, and plaintiffs at that time did not supply a sufficiency of materials or men, then as the time when the work was to be finished ivas of the essence of the contract, the defendant was justified in doing what it did to complete the contract as soon as possible to prevent as far as' possible, loss and damage to all concerned.” If the rights and obligations of the parties were dependent solely upon the written provision of the contract, there would be no answer to such proposition. But, as has been observed, the delay of about twenty days in the commencement of the work was chargeable to the defendant, and the consequence was a right of the plaintiffs to a reasonable extension of time for its completion, which it appears by evidence was recognized by the defendant. The terms of the contract in that and no other respect were modified. In other words, the performance of the contract within the stipulated time was waived and extended for such time as was reasonable under the circumstances. And, in view of the situation thus presented, notice of a time within which the work should be completed was essential to put the plaintiffs in default in that respect. (Lawson v. Hogan, 93 N. Y. 39, 44; Thomson v. Poor, 147 id. 402; Sinclair v. Tallmadge, 35 Barb. 602; Darrow v. Cornell, 12 App. Div. 604.)
A different question would be presented if the plaintiffs, without any modification of the contract which operated as an extension of time, had by the mere indulgence of the defendant continued in the
The further stipulation of the contract, providing that if the plaintiffs refused or neglected to supply a sufficiency of materials or workmen, the defendant should have the power to furnish them and to finish the work and charge the expense to the plaintiffs, remained effectual. But three days’ notice in writing, was, by the terms of the contract, required to enable the defendant to so assume the control of the work pursuant to the contract. This provision was not observed in the notice of the twenty-ninth of J une, and for that reason it did not appear that the defendant was proceeding under the contract, but as for an assumed default on the part of the plaintiffs. The court, however, elsewhere in the charge to the jury¿ instructed them quite fully on the subject of the proposition so _refused andlsubstantially in accordance with it slightly modified.
The question is raised whether or not the defendant was entitled to have allowed to it, against the plaintiffs’ claim, the amount paid by the defendant to Murray and De Mott for the work done by them under their contract made with the plaintiffs prior to June twenty-ninth.
It is contended on the part of the defendant that it was in any event entitled to have such amount allowed in reduction of the plaintiffs’ claim, because the sub-contract was made by them with the consent of the defendant, and Murray and De Mott were to-receive payment directly from it. The contract, therefore, remained effectual notwithstanding the termination of the connection of the plaintiffs with the work. As the work which Murray and De Mott undertook to perform was a portion of that within the contract between the plaintiffs and defendant, the payment to them was apparently upon the latter contract for work performed pursuant to it. But the defendant had terminated the relation of the plaintiffs to the work with knowledge of the existence and effect of the contract with Murray and De Mott. And assuming, as we do, upon the finding of the jury, that such termination by the defendant of its contract
In the view taken of the subject of the cause of action and of the alleged defenses, counterclaims and setoffs relating to the causeway or road, as distinguished from the bridge, there was no error to the prejudice of the defendant in the rulings of the court at the trial.
The contract for the construction of the drawbridge was made subsequent to that for the causeway and was distinct from it, and the relief sought, founded upon the alleged breach of the ■bridge contract, is made the subject of a separate and distinct cause of action in the complaint. It may be observed that the notice of June twenty-ninth to the plaintiffs was that Smith (engineer) was instructed to “finish road” under the contract. It is insisted by the plaintiffs’ counsel that in the purpose and effect of this notice
This question was raised at the trial, and, although the point was not there distinctly taken that the bridge work was not included in the terminating notice given by the defendant to the plaintiffs, the question to that effect was fairly within the exception taken on the part of the defendant.
The claim of the plaintiffs, founded upon the alleged breach of the bridge contract and submitted for consideration upon the evidence, amounted to $572.40. Whether any or how much of it was allowed by the jury is not seen by the record, nor is it necessary to inquire in what manner they reached the conclusion represented by the verdict for $5,400.
In the view thus taken of the case, the $170 alleged as matter of defense to the plaintiffs’ second cause of action and found to have been paid by the defendant to procure from the war department of the United States permission to construct the bridge over the inlet, requires no consideration as that alleged cause of action is not supported by the evidence. (Smith v. Cowan, 3 App. Div. 230.)
The judgment and order should be reversed and a new trial granted, costs to abide the event, unless the plaintiffs stipulate to deduct from the recovery of damages $572.40, and in that event the judgment should be so modified, and as modified affirmed.
All concurred.
Judgment and order reversed and new trial granted, costs to abide the event, unless within twenty days the plaintiffs stipulate to deduct from the recovery of damages $572.40, and in that event the judgment is so modified and as modified affirmed, without co,sts of this appeal to either party.