Appeal from a judgment of the Supreme Court (Hughes, J.), entered June 4, 1997, upon a decision of the court in favor of defendants.
In October 1985, defendant Mergentime Corporation/J.F. White, Inc., a joint venture (hereinafter defendant), entered into a subcontract with E.G. May Company, Inc. (hereinafter plaintiff) for the installation of certain electrical systems at the Croton Reservoir in Westchester County, as part of defendant’s contract with New York City for the renovation of two gate
As the project progressed, defendant needed an additional temporary power connection to the local utility company to run construction equipment. It issued change order No. 3 on May 12, 1987
Plaintiff commenced this breach of contract action to recover $313,000. Following a nonjury trial, Supreme Court, inter alia, determined that plaintiff breached the subcontract and had been fully compensated for work performed. Supreme Court awarded defendant judgment dismissing the complaint and plaintiff appeals.
At the outset, we note that while we possess broad review power in a nonjury trial, we do give deference to the trial court’s “assessment of the quality of the evidence and the credibility of the witnesses” (Callanan Indus. v Olympian Dev.,
There is support in this record for Supreme Court’s findings
Contrary to plaintiff’s first contention, our examination of the subcontract shows that the parties entered into a single agreement for the payment of a lump sum of $695,000, not two separate contracts of $313,000 and $382,000. While the performance of the subcontract was broken down into two phases, (1) gatehouse 1 and the pole line, and (2) existing gatehouse and the new substructure, the subcontract clearly obligated plaintiff to complete the entire project.
When it signed the subcontract, plaintiff became bound by its terms absent proof of fraud, duress or other wrongful act on defendant’s part (see, J & J Structures v Callarían Indus., supra, at 891). There is no such showing by plaintiff in this record. On the other hand, defendant offered proof that the subcontract specifically contemplated change orders, required prompt performance of any changes
Plaintiff seeks to excuse its failure to perform change order No. 3 by claiming that it was merely a proposal which did not provide adequate information to enable it to perform the work. However, there is no proof that plaintiff complained about inadequate information prior to suspending its performance on
In our view, the evidence supports Supreme Court’s finding that plaintiff’s unilateral suspension of the performance of change order No. 3 constituted an abandonment of the project and a breach of the “clear, complete and unambiguous” terms of the subcontract (Mazzaroli v Cook Bldrs.,
Finally, since defendant did not breach the subcontract, we find no merit in plaintiffs further contentions that it was entitled to an additional quantum meruit recovery (see, Tri-Mar Contrs. v Itco Drywall, supra, at 603; Farrell Heating, Plumbing, Air Conditioning Contrs. v Facilities Dev. & Improvement Corp.,
Mikoll, White, Carpinello and Graffeo, JJ., concur. Ordered that the judgment is affirmed, with costs.
Notes
. Notably, two earlier change orders were issued and paid for without incident.
. Section 4, entitled “Changes”, provides: “The Contractor may at any time by written order of Contractor’s authorized representative, and without notice to the Subcontractor’s sureties, make changes in, additions to or omissions from the work to be performed and materials to be furnished under this Subcontract, and the Subcontractor shall promptly proceed with the performance of this Subcontract as so changed.”
. Section 7, entitled “Labor”, provides in relevant part: “The Subcontractor, in connection with all work covered by the Subcontract, shall comply with and be bound by any labor agreements executed by the Contractor or on Contractor’s behalf to the extent that the provisions of such agreements apply to Subcontractors. Failure at any time to comply with any of the provisions of such agreements will, at the option of the Contractor, be cause for immediate termination of this Subcontract for default and the Contractor shall have all of the rights contained in Section 5 with regard to such termination.”
