Defendant assigns error to the denial of its motion to dismiss plaintiffs action on the ground that it was brought more than three years after the date of the consent judgment. The three-year period of the statute of limitations governing actions based on express contracts does not begin to run until the alleged breach occurs and the cause of action accrues.
Reidsville v. Burton,
Defendant also assigns error to the admission of testimony by plaintiffs expert witness Ray concerning the inability of the dam and pipe system to supply enough water to turn the water wheel at the mill and concerning the engineering modifications necessary to enable it to do so. In response to a question by plaintiffs counsel as to the reason that the system would never deliver enough water to the mill to turn the water wheel, Ray stated that “the total head that you have to work with is not enough with the present size pipe to deliver the amount of water that is necessary.” The rule is well-established that “[w]hen the language of a contract is clear and unambiguous, effect must be given to its terms, and the court, under the guise of construction, cannot reject what the parties inserted or what the parties elected to omit.”
Weyerhaeuser v. Light Co.,
Ray’s testimony which followed concerned proposed changes in the system which would increase the head of the water sufficiently to furnish water power to the mill. Defendant contends that such testimony concerning “improvements” was irrelevant in that it introduced matters beyond the scope of the parties’ contract. We agree.
The substance of Ray’s testimony was as follows: In order to provide sufficient water flow to operate the mill, the dam would have to be raised ten inches, and the entrance to the pipe at the top of the dam would need “a filtering system and a flow straightening system to arrange the *268 water and get the water directed into the entrance of the pipeline without any resistance from surface debris, leaves and that sort of thing.” At the point where the thirty-inch pipe built by the State now empties into the old raceway, a “sweeping radius pipe,” one with valve arrangements to sweep out silt gathering inside the pipe due to the higher elevation of the exit point, would be required to replace the open raceway area between the new pipe running from the dam and the pipe running under old Highway 213 towards the mill.
The admissibility of this evidence depends upon interpretation of the parties’ contract. The State’s obligation under the agreement, in essence, was to construct: (1) “a weir dam across Bull Creek in good operating condition at or near the site of the existing dam”, (2) “together with a 30" pipeline with a slide gate, for the conveyance of said water from said dam to Silver’s Mill,” and (3) “a grate or guard over or near the water entrance into the pipe so as to prevent foreign objects over three inches in diameter entering the pipe.” The object of contract construction is to ascertain the intention of the parties “from the expressions used, the subject matter, the end in view, the purpose sought, and the situation of the parties at the time.”
Electric Co. v. Insurance Co.,
Viewing the testimony offered by plaintiffs expert in light of this analysis, we conclude that it is necessary to distinguish those portions of the testimony which injected into the case matters beyond the scope of the contract from those which were relevant to the question of what would be required to conform the project to the terms of the contract. “The fundamental principle which underlies the decisions regarding the measure of damages for defects or omissions in the performance of a building or construction contract is that a party is entitled to have what he contracts for or its equivalent. What the equivalent is depends upon the circumstances of the case.”
Robbins v. Trading Post, Inc.,
Ray’s testimony concerning the necessity for a “filtering system and flow straightening system” at the entrance to the pipe at the dam, in contrast, was not only irrelevant to these issues, but actually contradicted the express terms of the contract, which contemplated a filtering system consisting only of a grate or guard that would prevent foreign objects over three inches in diameter from entering the pipeline. Its admission, therefore, was error.
*270
Ray’s testimony that a sweeping radius pipe was necessary to replace the open raceway area between the thirty-inch pipe installed by the State and the old thirty-inch pipe running towards the mill under old highway 213 was inadmissible for similar reasons. The agreement was ambiguous as to whether the parties intended that a pipeline be constructed the entire distance from the new dam to the mill, and it was for the jury to determine whether the contract so required.
Root v. Insurance Co.,
Defendant has also assigned error to the denial of its motion for a directed verdict at the close of all of the evidence on the grounds that the evidence established as a matter of law that defendant fully complied with the terms of the contract. We find no error. Viewed in the light most favorable to plaintiff, the nonmoving party, ample evidence was presented from which the jury could infer that the system as constructed did not substantially conform to the terms of the agreement contained in the consent judgment in that the exit end of the new pipeline was higher than the level of the dam, and a slide gate to the dam which was broken during construction was never properly repaired. In addition, the ambiguity of the contract as to the length of the pipe to be installed was for the jury to resolve.
That the incompetent evidence which was erroneously admitted impermissibly affected the verdict is confirmed by the trial court’s instructions to the jury. In those instructions the court referred to the testimony of the witness Ray concerning the complicated filtration and dispersal system and to his testimony concerning the cost of these items. Although the court later properly instructed the jury that “there is no duty on the Defendant to construct a dam sufficient to turn the mill wheel or to install any filter system,” it thereafter instructed them that they could award up to $13,000.00 in damages. That $13,000.00 figure to which the trial court referred and which the jury subsequently adopted was based not only on Ray’s compe *271 tent testimony concerning the cost of raising the dam, but also on his incompetent testimony concerning the cost of the filtering and flow straightening system and the sweeping radius pipe.
For errors in the admission of evidence, the defendant is entitled to a
New Trial.
