MEMORANDUM OPINION
Plaintiff Silo Point II, LLC, (“Silo Point”), a Maryland Limited Liability Company engaged in the business of real estate development, has filed a two-count Complaint in this Court against Defendant Suffolk Construction Company, Inc. (“Suffolk”), a general contractor incorporated in Massachusetts. At issue is the Guaranteed Maximum Price contract (the “Contract”) the parties entered into that sets forth the terms and risks attendant to the construction of a condominium project in Baltimore City (the “Project”). The crux of the dispute relates to the cаlculation of the Guaranteed Maximum Price (“GMP”), which largely determines liability for cost overruns on the Project. After the parties failed to negotiate a resolution, Silo Point brought this action seeking declaratory relief and specific performance.
Now pending before this Court is Defendant Suffolk’s Motion to Dismiss (Paper No. 4). Suffolk argues that the forum selection clause governing the Contract requires all disputes to be filed in a Mary- _ land state court. This matter has been briefed fully and no hearing is necessary. See Local Rule 105.6 (D.Md.2008). For the reasons set forth below, Suffolk’s Motion to Dismiss is GRANTED.
BACKGROUND
This action arises out of a dispute related to the construction of an approximately $100 million condominium project along Baltimore’s Inner Harbor. (Compl. ¶ 5.) On November 8, 2005, Silo Point issued its intent to award a prime contract to Suffolk for the construction of the Project that involved the conversion of a 1920s-era grain elevator and silo into a high end condominium building. (Id. ¶¶ 5, 8.) In late 2005 and early 2006, the parties engaged in Pre-Construction, wherein they identified the scoрe and intent of the work, determined construction feasibility, developed a construction schedule, and calculated a GMP. (Id. ¶ 9.) At the close of Pre-Construction, on April 20, 2006, the parties entered into the Contract that specified a GMP of $92,690,000 and a substantial completion date within twenty months from the commencement of construction. (Id. ¶¶ 10, 11; Def.’s Ex. 1A, Art. 4, § 4.3) The Contract provided that any costs exceeding the GMP would be borne by Suffolk without reimbursement by Silo Point. (Def.’s Ex. 1A, Art. 4 § 4.3) Finally, the Contract contains a forum selection clause which reads:
§ 4.4.3 Governing Law and Venue The substantive and procedural laws of Maryland shall apply in all respects to any and all disputes arising from or relating to interpretation of performance of this Contract, except as otherwise specifically рrovided herein. Any dispute between the parties shall be exclusively brought in the courts of the State of Maryland.
(Def.’s Ex. IB, Art. 4, § 4.4.3.)
During the construction process, several unforeseen conditions and difficulties developed. As a result, Suffolk began to incur costs well above the GMP and the Project’s projected completion date was extended. Suffolk thereupon petitioned Silo Point for both an upward adjustment *809 to the GMP to compensate for its cost overruns and for a time extension on the Project’s completiоn date. (Compl. ¶ 19.) A protracted dispute arose between the parties over the scope and nature of any adjustments to the Contract and the determination of the GMP and construction schedule.
In March of 2008, Suffolk indicated that it would file for a meсhanic’s lien against the property and would sue for breach of contract in the Circuit Court for Baltimore City. 1 (Id. ¶ 28.) On April 21, 2008, after the failure of the parties’ subsequent attempts to resolve their dispute, Silo Point filed this action. Silo Point seeks a declaratory judgment thаt determines “the GMP based on the respective rights, risks, and obligations each party undertook pursuant to their negotiated Contract, including the appropriate contract completion date, and a declaration regarding Suffolk’s claims that have been submitted and rejected, as contrary to the terms of the Contract.” (Id. ¶ 50.) In addition, Silo Point seeks a grant of specific performance requiring Suffolk to produce certain books and records previously sought by Silo Point. (Id. ¶¶ 52-55.) Suffolk has moved to dismiss, claiming, inter alia, that the forum selection сlause in the Contract forecloses either party from filing suit in this Court. 2
STANDARD OF REVIEW
The United States Court of Appeals for the Fourth Circuit has recently ruled that Fed.R.Civ.P. 12(b)(3) is the proper procedural vehicle for bringing a motion to dismiss based on improper venue when the issue turns on а forum selection clause.
3
Sucampo Pharms., Inc. v. Astellas Pharma, Inc.,
ANALYSIS
Because this is a diversity action, the substantive law of Maryland is applied in analyzing the forum selection clause.
See Eisaman, et al. v. Cinema Grill Systems, Inc., et al.,
The forum selection clause contained in the Contract provides that “[a]ny dispute between the parties shall be exсlusively brought in the courts of the State of Maryland.” (Def.’s Ex. IB, Art. 4, § 4.43.) (emphasis added). Suffolk submits that the clause clearly identifies the state courts of Maryland as the exclusive fora selected by the parties. Suffolk contends 'that this interpretation is supported by a plain reаding of the clause and by the weight of authority interpreting identical or similar phrases. (Def.’s Mem. Supp. Mot. to Dismiss 14-15.) Silo Point counters by emphasizing the fact that in the clause “the parties agreed to submit to jurisdiction in the ‘courts’ of Maryland — not just one court — -but multiple ‘courts’ of Maryland.” (PL’s Mem. Opp’n Mot. to Dismiss 24.) Silo Point argues that because only one state court, the Circuit Court for Baltimore City, could serve as an appropriate venue for state actions between the parties, the plural use of “courts” must also refеr to the United States District Court for the District of Maryland. (Id.)
In analyzing forum selection clauses, courts begin by determining whether the limitation provided in the clause is one of sovereignty or geography.
See, e.g., American Soda, LLP v. U.S. Filter Wastewater Group, Inc.,
The forum selection clause in this case is unambiguously expressed in terms of sovereignty and therefore excludes federal courts. The term “of’ is commonly
*811
used in clauses to rеfer to sovereignty and has been defined as “denoting that from which anything proceeds; indicating origin, source, descent.”
Dixon v. TSE Int’l Inc.,
A very different result would be required if the forum selection clаuse in the Contract had used terms such as “in” or “within” instead of the term “of.”
See Pullman Inc.,
This Court recently held in
MTBR LLC v. D.R. Horton, Inc.,
No. 07-3363,
Applying the analysis and precedent cited above, this Court finds that the forum selection clаuse in the present case requires that any dispute arising from the Contract be brought in a Maryland state court. Silo Point does not cite any precedent that concerned the interpretation of forum selection clauses in support of its contrary position. Moreover, this Court finds unavailing Silo Point’s argument that by using the plural “courts” in the forum selection clause, the parties intended to include federal court because only one state court (the Circuit Court for Baltimore City) could properly hear state actions between the parties. (Pl.’s Mem. Opp’n Mot. to Dismiss 24.) As Suffolk points out, the latter contention is simply incorrect. For instance, the District Court for Baltimore City would properly decide any claims at issue between the parties that were below its $30,000 exсlusive jurisdictional threshold. (Def.’s Reply 3 (citing Md.Code, Cts. & Jud. Proc. § 4-401).) Finally, it is likely that the parties employed the plural “courts” to cover the possibility that after the completion of the Project, Silo Point could change its place of business, or Suffolk could stoр conducting business in Baltimore City but continue to do business in other parts of Maryland. (Def.’s Reply 4.)
CONCLUSION
For the reasons stated above, Defendant Suffolk’s Motion to Dismiss (Paper No. 4) is GRANTED. A separate Order follows.
ORDER
For the reasons stated in the foregoing Memorandum Opinion, it is this 25th day оf September 2008, ORDERED, that:
1. The Motion to Dismiss filed by Defendant Suffolk Construction Co., Inc. (Paper No. 4) is GRANTED.
2. The Clerk of the Court transmit copies of this Order and accompanying Memorandum Opinion to counsel for the parties and to CLOSE this case.
Notes
. Suffolk commenced its mechanic’s lien enforcement action and breach of contract claim in the Circuit Court for Baltimore City on April 28, 2008. (Def.'s Mem. Supp. Mot. to Dismiss 3.)
. Suffolk argued that dismissal is further warranted because Silo Point’s filing of this action is prohibited "procedural fencing.” Because there is sufficient cause to dismiss Silo Point's suit on the basis of the forum selection clause, this Court does not address the additional issue of "procedural fencing.”
.Suffolk mistakenly filed its motion to dismiss for improper venue under Fed.R.Civ.P. 12(b)(6). This Court will instead treat the motion for lack of jurisdiction based on the forum selection clause as a motion under Fed.R.Civ.P. 12(b)(3). Because Suffolk has contested venue in its first responsive pleading, it has not waived the issue under Fed. R.Civ.P. 12(h)(1). Therefore, Suffolk's failure to cite Rule 12(b)(3) was not material under the circumstances.
. In resolving this issue of contract interpretation, this Court does not find persuasive cases cited by the parties that deal exclusively with contract validity or enforceability.
See Koch v. Am. Online, Inc.,
