These consolidated cases present two challenges to agency actions that provided necessary approvals for the Atlantic Coast Pipeline (ACP). The challenges were
The first petition, No. 18-1083, concerns the U.S. Fish and Wildlife Service (FWS). Pursuant to the Endangered Species Act, FWS issued an Incidental Take Statement (ITS) authorizing the pipeline to "take"-i.e., kill, harm, or harass-five species that are listed as threatened or endangered. Petitioners challenged the ITS as arbitrary and capricious under § 706 of the Administrative Procedure Act (APA) because the amount of take authorized in the ITS (known as the "take limit") cannot be enforced. Petitioners identify two flaws that make the take limits unenforceable: first, FWS failed to set numeric limits on take of the five threatened and endangered species, and second, FWS failed to comply with the requirements for using habitat as a surrogate for a numeric limit. Although FWS is not required to set a numeric limit, it can only use a habitat surrogate if it demonstrates a causal link between the species and the delineated habitat, shows that setting a numerical limit is not practical, and sets a clear standard for determining when incidental take is exceeded. Here, FWS failed some or all of these requirements for all five challenged species. As such, FWS's take limits are not enforceable and therefore arbitrary and capricious.
The second petition, No. 18-1082, concerns the U.S. National Park Service (NPS). The pipeline's proposed route intersects the Blue Ridge Parkway, a unit of the National Park System managed by NPS. Invoking the Blue Ridge Parkway Organic Act, NPS issued a right-of-way permit allowing the pipeline to drill and pass underneath the Parkway surface. The pipeline will also carve a path through a nearby forest, affecting views from the Parkway's scenic overlooks. Petitioners Sierra Club and the Virginia Wilderness Committee argue that NPS lacked the authority to grant a right-of-way to a gas pipeline and that doing so violated the statutory mandate that agency decisions not be inconsistent with the Parkway's conservation purpose. As detailed below, we assume for purposes of this case that NPS has the requisite statutory authority but because NPS does not explain how the pipeline crossing is not inconsistent with the purposes of the Parkway and the overall National Park System, the permit decision is arbitrary and capricious.
Part I of this opinion will provide a brief background and address a statute of limitations question common to both cases. Part II will provide the relevant background facts and legal analysis for No. 18-1083 (FWS), while Part III will provide the relevant background facts and legal analysis for No. 18-1082 (NPS). Finally, having concluded that the respective agencies erred, Part IV will address a question of remedy common to both cases.
I.
A.
The ACP is a 600-mile pipeline designed to transport natural gas from Harrison County, West Virginia, to the eastern portions of Virginia and North Carolina. J.A. 234. Constructing the pipeline would generally require a 125-foot right-of-way for most of the distance, which will disturb 11,776 acres of land. J.A. 553. Once completed, ACP would generally maintain a 50-foot permanent right-of-way along the length of the pipeline. J.A. 325.
Under the Natural Gas Act, the Federal Energy Regulatory Commission (FERC) is the agency responsible for giving final
On October 13, 2017, FERC issued ACP a certificate of public convenience and necessity that authorized the construction and operation of the pipeline. J.A. 234-389. As it has done in other cases, FERC conditioned its approval of the pipeline on ACP receiving all "state and other federal authorizations required for the proposed project."
Del. Riverkeeper Network v. Sec'y Pa. Dep't of Envtl. Prot.
,
B.
The first question we must resolve is whether the Petitioners filed their challenges within the applicable statute of limitations. Federal Rule of Appellate Procedure 15(a) provides that "[r]eview of an agency order is commenced by filing, within the time prescribed by law , a petition for review[.]" Fed. R. App. P. 15(a)(1) (emphasis added).
The Petitioners filed their challenges within 95 days (No. 18-1083) and 38 days (No. 18-1082) of the agency decisions, respectively. In their opening brief, Petitioners invoked the six-year statute of limitation created for claims "against the United States," which applies generally to challenges brought under the APA.
See
ACP argues that these challenges were actually brought under the Natural Gas Act, 15 U.S.C. § 717r(d)(1), which lacks a statute of limitations. Thus, ACP urges us to adopt the most closely analogous
state law
statute of limitations. ACP Resp. Br. 18-27 (citing
Reed v. United Transp. Union
,
The problem with ACP's argument is that the cases on which it relies predate Congress's establishment of a four-year default statute of limitations for any "civil action arising under an Act of Congress enacted after" December 1, 1990. Judicial Improvements Act of 1990, Pub. L. No. 101-650, § 313, 104 Stat 5089, 5114-15 (codified
As Petitioners point out, Congress added 15 U.S.C. § 717r(d) in 2005. Energy Policy Act of 2005, Pub. L. No. 109-58, § 313(b), 119 Stat 594, 689-90. If § 717r(d) is the source of Petitioners' cause of action, then § 1658(a) applies and the statute of limitations is four years. The only other federal court to consider this issue also looked to § 1658(a) in declining to apply a more restrictive state limitations period.
Del. Riverkeeper Network v. Sec'y of Pa. Dep't of Envtl. Prot.
,
We need not decide whether the Natural Gas Act, which ACP cites as the cause of action, or the APA, which Petitioners cite as theirs, provides the applicable statute of limitations. Petitioners filed their challenges to FWS and NPS after 95 and 38 days, respectively. By either measure, the petitions are timely.
II.
We turn first to petition No. 18-1083, in which Petitioners challenge the take limits set by FWS for five species that will be negatively impacted by the pipeline. We begin with the Endangered Species Act and the exception created for "incidental" take of threatened and endangered species. We next discuss how the Endangered Species Act obligated FWS to analyze how the pipeline would affect threatened and endangered species. We then summarize the statutory and regulatory requirements FWS must satisfy to issue a proper incidental take statement. Finally, we review in detail the agency's determinations about the five species at issue. We conclude that for each species, FWS failed to satisfy the requirements for a habitat surrogate and therefore failed to create enforceable take limits.
A.
1.
Congress enacted the Endangered Species Act in 1973 "to protect and conserve endangered and threatened species and their habitats."
Nat'l Ass'n of Home Builders v. Defs. of Wildlife
,
To protect threatened and endangered species, Endangered Species Act § 9 and FWS regulations prohibit their "take."
In 1982, Congress created a narrow exception to the prohibition against take: when "such taking is incidental to, and not the purpose of, the carrying out of an otherwise lawful activity."
2.
Building a natural gas pipeline implicates a number of federal laws, including the Endangered Species Act. J.A. 545-52. Pursuant to Endangered Species Act § 7, FERC must ensure that "any action authorized, funded, or carried out by such agency ... is not likely to jeopardize the continued existence of
2
any endangered species or threatened species or result in the destruction or adverse modification of habitat of such species."
In July 2017, FERC requested formal consultation with FWS about the ACP. J.A. 391. Three months later, FWS issued a Biological Opinion that addressed six threatened and endangered non-plant species: the Roanoke Logperch (a fish), the Clubshell (a mussel), the Rusty Patched Bumble Bee, the Madison Cave Isopod (a crustacean), the Indiana Bat, and the Northern Long-Eared Bat. J.A. 390-439. FWS concluded that the pipeline as a whole would not "jeopardize the continued existence of" the six species. J.A. 430-39. But because pipeline will adversely affect
Petitioners' sole challenge in this lawsuit is to the take limit set for five of the six species: the Clubshell, the Rusty Patched Bumble Bee, the Madison Cave Isopod, the Indiana Bat, and the Northern Long-Eared Bat.
B.
We have jurisdiction under the Natural Gas Act. 15 U.S.C. § 717r(d)(1). Because the Endangered Species Act does not specify a standard of review, "we apply the general standard of review of agency action established by" the APA.
Or. Nat. Res. Council v. Allen
,
C.
An ITS is a safe harbor: it allows an agency (here, FERC) to approve a project that takes threatened or endangered species without falling afoul of the Endangered Species Act.
For an ITS to function as a safe harbor, FWS must set an incidental take limit that can be monitored and enforced. FERC is required to "report the progress of the action and its impact on the species to [FWS] as specified in the incidental take statement."
Section 7 of the Endangered Species Act requires an ITS to "[s]pecif[y] the impact, i.e., the amount or extent, of such incidental taking on the species."
Wild Fish Conservancy v. Salazar
,
Here, FWS declined to set numeric limits on five of the six non-plant species that will be adversely affected by the pipeline. Instead, it set take limits as a "small percent," "majority" or "all" of the species within set geographic areas. As Petitioners point out, a "small percent" or a "majority" of a species is not an enforceable limit. FWS and ACP do not disagree. Instead, they claim that FWS used habitat surrogates.
A habitat surrogate is a way of defining take by the amount of adversely affected habitat rather than by the number of individuals harassed or killed. FWS has explained that habitat surrogates are "often more practical and meaningful to monitor project effects" because they can "provide a clear standard for determining when the amount or extent of anticipated take has been exceeded and consultation should be reinitiated."
Incidental Take Statements
,
FWS regulations list three elements necessary for a proper habitat surrogate. First, FWS must include a description of "the causal link between the surrogate and take of the listed species."
Second, FWS must explain "why it is not practical to express the amount or extent of anticipated take or to monitor take-related impacts in terms of individuals of the listed species."
Finally, FWS must set "a clear standard for determining when the level of anticipated take has been exceeded."
Turning to petition No. 18-1083, the only issue presented is whether FWS properly employed a habitat surrogate for five of the endangered and threatened species that will be adversely affected by the pipeline. Specifically, the Petitioners argue that: FWS did not establish that a numeric take limit was impractical, particularly because FWS had previously adopted numeric limits for some of the same species; FWS did not establish a causal link between the pipeline and the habitat selected for some of the species; and the surrogate limits adopted are unenforceable because they set the vague take limits of a "small percent" or a "majority" of individuals.
See
But first, we dispose of three overarching points. First, FWS claims that some numeric limits were not possible because either it lacked current survey information about many of the species or ACP had not completed the necessary surveys. This argument is "circular and unavailing."
Ctr. for Biological Diversity v. Bureau of Land Mgmt.
,
Second, the agency argues that there was insufficient time for the agency or ACP to develop reliable survey information regarding certain of the species because the agency "must complete formal consultation on a short, ninety-day time timetable based on the 'best scientific and commercial data'
then
available." Gov't Br. 21 (citing
Tellingly, neither the statute, nor the agency's implementing regulation, nor the agency's
Endangered Species Consultation Handbook
, identify lack of time as a proper basis for concluding that setting a numerical limit is impractical.
See
H.R. Rep. No. 97-567, at 27 (1982) ("For example, it may not be possible to determine the number of eggs of an endangered or threatened fish which will be sucked into a power plant when water is used as a cooling mechanism.");
Incidental Take Statements
,
Third, although FWS and ACP both argue that the ITS passes muster, they cannot agree about what the ITS actually did. ACP claims that FWS set pure habitat surrogates; therefore, the "small percent" and "majority" language "was not meant
FWS and ACP cannot rewrite the ITS on appeal.
Motor Vehicle Mfrs. Ass'n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co.
,
1. Roanoke Logperch ( Percina rex )
Before turning to the five challenged species, we take a moment to discuss briefly the sixth: the Roanoke Logperch, an endangered freshwater fish. Petitioners do not challenge the logperch take limit, but FWS's approach to the logperch is a useful comparator when evaluating its much different approach to the other five species.
The pipeline will cross four waterbodies known or with potential to support the logperch. J.A. 407. Neither ACP nor FWS conducted presence/absence surveys; instead, they assumed the presence of the logperch because the pipeline will affect potential habitat in areas known to support the logperch. J.A. 405. ACP threatens the logperch both indirectly due to increased sedimentation and directly where it crosses waterbodies with logperch present. J.A. 407, 418.
FWS estimated that a total of 150 logperch are expected to occur in the area affected by the pipeline. J.A. 406. It reached this number by using recent survey information for two of the four affected waterbodies. In the first waterbody, a 2017 survey observed 12 logperch. FWS multiplied that number by ten because "mark-recapture data indicates that only about 10% of [logperch] are actually detected during surveys." This resulted in an estimated 120 total logperch. In the second waterbody, a 2012 survey observed one logperch. Adjusting by the same multiple of ten, FWS estimated there were ten total logperch there. The third and fourth waterbodies lacked recent survey information, but FWS believed the fish to be present at a density comparable to the second waterbody (i.e., 10). And 120 plus ten plus ten plus ten equals 150.
FWS set a take limit of 5 individual Roanoke Logperch through injury or death and 145 individuals through harm or harassment. J.A. 440. To arrive at this take limit, FWS divided the area of logperch habitat needed to actually build the crossing structures by the total area of logperch habitat at each pipeline crossing and determined that the crossings themselves will comprise 3.3 percent of the total affected habitat. Because FWS estimates
2. Clubshell ( Pleurobema clava )
The Clubshell is an endangered mussel that grows to be about three inches long. J.A. 692. In the Monongahela River system of West Virginia, which contains only one Clubshell population in Hackers Creek, the Clubshell is in severe decline and is not reproducing. J.A. 401, 432. A 2009 survey at a long-term monitoring site in Hackers Creek found 29 individuals; a 2014 survey found 19 individuals. J.A. 407. ACP will conduct construction in the upstream drainage area of Hackers Creek and will cross six of its tributaries. J.A. 407. The resulting sediment load will adversely impact the Clubshell population at Hackers Creek. J.A. 432.
FWS set the take limit as: killing a "[s]mall percent of individuals present within 585 m," and harming or harassing the "[m]ajority of individuals present within 585 m." J.A. 440-41. The agency explained that it "anticipates incidental take of clubshell will be difficult to detect for the following reason: up to 70% of a population can be distributed below the substrate surface." J.A. 440. Therefore, FWS concluded that the "level of take of this species can be anticipated by loss of habitat from 130 m downstream to 455 m upstream of Life's Run Bridge (County Route 14) (total of 585 m) because this area contains suitable clubshell habitat." J.A. 440. As part of the terms and conditions, FERC must collect all Clubshell in the 585-meter stretch of Hackers Creek. J.A. 444-45. The Clubshell will then be held at an approved facility for reintroduction after the pipeline is completed.
The incidental take authorized here is not a proper habitat surrogate because it lacks the three necessary elements. First, there is no clear and enforceable standard of take. Instead, take is limited to a "small percent" and a "majority" of Clubshell within a fixed geographic area. Although the geographic bounds are fixed, FWS authorized the pipeline to take only a subset of individuals located within those bounds . But it is impossible to know the size of the subset-i.e., how many individuals constitute a "small percent" or a "majority."
Second, FWS offered no explanation for why the habitat surrogate is limited to 130 meters downstream and 455 meters upstream of Life's Run Bridge. Although the Biological Opinion mentioned that the Hackers Creek Clubshell population is located at Life's Run Bridge, the geographic bounds of 130 meters downstream and 455 meters upstream are not explained anywhere else in the ITS or Biological Opinion. The arbitrariness of this range is particularly conspicuous considering that the pipeline will introduce sediment upstream of Life's Run Bridge, meaning that the sediment will flow through all of Hackers Creek, not just 585 meters of it.
Finally, FWS did not adequately explain why a numeric limit is not practical. The only proffered explanation is that Clubshell are difficult to detect because most of them live below the substrate surface. But FWS has been able to adequately survey Clubshell in the past; indeed, it knew there were 29 Clubshell in 2009 and 19 in 2014.
See
Miccosukee Tribe of Indians of Fla.
,
In sum, the take limit for the Clubshell fails all three habitat surrogate requirements: it lacks a causal link between the specific 585-meter stretch of Hackers Creek and the local Clubshell population, it lacks an explanation as to why a numerical limit is impractical, and it lacks a clear enforcement standard.
See
3. Rusty Patched Bumble Bee ( Bombus affinis )
The Rusty Patched Bumble Bee (RPBB) was listed as endangered in January 2017. J.A. 401, 809-11. A 2017 survey found one bee in Bath County, Virginia, about a mile from the pipeline route. J.A. 408. FWS concluded that the magnitude of the Rusty Patched Bumble Bee's population losses "has greatly reduced the likelihood that the species is present elsewhere" along the pipeline route. J.A. 408. As a result, "comprehensive RPBB surveys were not conducted throughout the action area" in Virginia. J.A. 408.
Based on this single bee, FWS estimated that the Rusty Patched Bumble Bee is most likely to occur in a 653-hectare "high potential zone" near the pipeline. J.A. 408-10. The pipeline will directly affect approximately 7.3 hectares of this zone, which could "crush individuals, crush a colony, expose RPBBs to noise/vibration, and render habitat temporarily and permanently unsuitable." J.A. 421. After making a number of assumptions about bee and bee colony density, FWS estimated that one colony-i.e., a cohesive biological unit of bees established every spring by a solitary queen and made up of her offspring, J.A. 807-is statistically likely to be present in the 7.3 hectares directly affected by the pipeline. J.A. 433.
FWS set the take limit as: killing "1 colony present within 7.3 [hectares]" and harming or harassing a "[s]mall percent of [queen bees] from 1 colony present within 7.3 [hectares]." J.A. 441. FWS explained that it "anticipates incidental take of RPBB will be difficult to detect for the following reasons: species has small body size, losses may be masked by seasonal fluctuations in numbers and other environmental factors, and species occurs in habitat
The incidental take authorized here is not a proper habitat surrogate because it lacks two of the three necessary elements. FWS has demonstrated a causal link between the bee and the geographic boundaries of the take limit: the pipeline will affect 7.3 hectares of high potential habitat for the Rusty Patched Bumble Bee, which
statistically
will affect only one Rusty Patched Bumble Bee colony. But FWS's incidental take limit is not a clear standard because it is not actually defined by the 7.3 hectares; instead, take is limited to exactly
one colony and a small percent of queen bees within the 7.3 hectares
. Neither one colony nor a small percent is an enforceable standard: There may be multiple colonies within the 7.3 hectares, FERC cannot know if taken bees are from the same colony or different colonies, and it is not clear what constitutes a "small percent" of queen bees. Moreover, FWS has not shown that a numeric limit is impractical.
5
It claimed that it has "no accurate way to assess the status of the local population," J.A. 409-but, only a few months earlier, FWS issued its own survey protocols for the Rusty Patched Bumble Bee, J.A. 854-89, and it had conducted a prior survey that identified the lone bee.
See
Miccosukee Tribe of Indians of Fla.
,
In sum, the take limit for the Rusty Patched Bumble Bee fails two of the habitat surrogate requirements: it lacks an explanation as to why a numerical limit is impractical, and it lacks a clear enforcement standard.
See
4. Madison Cave Isopod ( Antrolana lira )
The Madison Cave Isopod (MCI) is a threatened subterranean freshwater crustacean about a half-inch in size. "The species is endemic to underground karst aquifer habitats and is restricted to the Shenandoah Valley, from Lexington, Virginia to Harpers Ferry, West Virginia." J.A. 608. The pipeline right of way, additional temporary work space, and access roads will affect "approximately 1,974 surface acres (approximately 0.74%)" of the isopod's potential habitat in Augusta County, Virginia. J.A. 411. Included in this area are Cochran's Cave and five sinkholes, which FWS assumed are connected and which provide a conduit for sediment and contaminants to the isopod's habitat. J.A. 411-12. Because FWS lacked the ability to survey the presence or abundance of the isopods, it assumed that they will be found in the pipeline project area. J.A. 411.
The pipeline will threaten the isopods by crushing them or introducing sediment that smothers them or their habitat. J.A. 422. Although there are no "localities" in the pipeline construction area where Madison Cave Isopods have been sampled, FWS arbitrarily decided that Cochran's Cave would serve as an undocumented isopod "locality" and then chose to use "localities as a surrogate for a population." J.A. 434. It concluded that a total of 896.7 surface acres of isopod potential habitat is within 0.5 miles of the construction activities
FWS set the take limit as: killing a "[s]mall percent of individuals present within 11.2 acres" and harming or harassing "[a]ll individuals present within 896.7 acres." J.A. 441-42. The agency explained that "incidental take of the MCI will be difficult to detect for the following reasons: small body size, finding a dead or impaired specimen is unlikely, and species occurs in habitat (underground) that makes detection difficult." J.A. 441.
FWS has shown that a numeric limit is not practical here: the isopod is a half-inch crustacean that lives in underground aquifers. But the take limit fails as a habitat surrogate because it lacks the other two elements. First, FWS stated that the pipeline will affect 1,974 surface acres of MCI potential habitat, all of which it assumes contains isopods. But without providing a reasoned explanation, FWS arbitrarily limited the habitat surrogate to the 896.7 acres near Cochran's Cave. Second, the proffered take limits are not real surrogates: the authorized take limit is (in part) a "small percent" of isopods within the 11.2 acres that will be directly affected by the pipeline . But there is no precise way of measuring what a "small percent" of isopods would be, and thus no clear standard for enforcement.
In sum, the take limit for the Madison Cave Isopod fails to satisfy two of the habitat surrogate requirements: its causal link between the isopod and the geographic bounds of the take limit is arbitrary, and it lacks a clear enforcement standard.
See
5. Indiana Bat ( Myolis sodalis )
The Indiana Bat (Ibat) is an endangered migratory bat. FWS estimated that, as of 2017, there are only 425 in Virginia and 1,076 in West Virginia. J.A. 412. The pipeline crosses the Indiana Bat Appalachian Mountain Recovery Unit, an area of protected Indiana Bat habitat that covers all of West Virginia and part of western Virginia. 6 J.A. 412, 725. The pipeline will adversely affect Indiana Bats by temporarily or permanently removing 4,448 acres of suitable habitat in the Recovery Unit. J.A. 423-24. Based on survey data and seasonal movements, FWS defined four relevant categories of Indiana Bat habitat in the Recovery Unit: (1) suitable unoccupied summer habitat, i.e., habitat that is unoccupied during the summer; (2) known use summer habitat, i.e., habitat that is known to be used by the bats in the summer; (3) unknown use spring staging/fall swarming habitat, i.e., habitat near unsurveyed but potentially suitable winter hibernation quarters (known as "hibernacula"); and (4) known use spring staging/fall swarming habitat, i.e., habitat near known hibernacula. J.A. 412. The pipeline will affect these different habitats in the Recovery Unit as follows:
Habitat Category Total (acres) Suitable unoccupied summer habitat 3,275.382 Known use summer habitat 144.1 Unknown use spring staging/fall swarming habitat 178.1 Known use spring staging/fall swarming habitat 850.4 Total Acres of Recovery Unit 4,447.982
J.A. 413.
FWS set the take limit as:
Amount of Take Anticipated Type of Take Small percent of individuals present within Harm, Harass, 1,637.69 acres of suitable unoccupied summer Injure, or Kill habitat Small percent of individuals within 144.1 acres Harass of known use summer habitat Small percent of individuals present within 89.05 Harm, Harass, acres of unknown use spring staging/fall or Kill swarming habitat Small percent of individuals present within 850.4 Harm, Harass, acres known use spring staging/fall swarming or Kill habitat
J.A. 442. The agency explained that it "anticipates incidental take of the Ibat will be difficult to detect for the following reasons: species has small body size, finding a dead or impaired specimen is unlikely, and species occurs in habitat (forest and caves) that makes detection difficult." J.A. 442. FWS concluded that the "take of this species can be anticipated by loss of 4,447.982 acres because this area contains suitable Ibat habitat." J.A. 442. But FWS imposed a 0.5 multiplier on the affected acreage for two of the four habitat categories-suitable unoccupied summer habitat and unknown use spring staging/fall swarming habitat-purportedly "[t]o account for differences in Ibat use of the habitat categories." J.A. 442.
The incidental take authorized here is not a proper habitat surrogate because it lacks the three necessary elements. First and most significantly, it is not a true habitat surrogate: take is limited to a "small percent" of Indiana Bats within each geographic area. Although the geographic bounds are fixed, the pipeline can only take a subset of individuals located within those bounds . But it is impossible to know what a "small percent" of bats is. Therefore, there is no clear and enforceable standard of take.
Second, two of the chosen geographic bounds are arbitrary. FWS knew that the pipeline will directly affect 3,275.382 acres of suitable unoccupied summer habitat and 178.1 acres of unknown use spring staging/fall swarming habitat. Yet, without any explanation, the agency set the take limit for these two habitats at half of these acreages. In other words, FWS set the take limit at half the affected bat habitat that it knows the pipeline is going to affect.
Finally, FWS has not shown that a numeric limit is impractical. The bats may be small, but FWS has been able to survey them in the past. Indeed, FWS made precise estimates as recently as 2017, determining that there are 425 bats in Virginia and 1,076 in West Virginia.
See
Miccosukee Tribe of Indians of Fla.
,
In sum, the take limit for the Indiana Bat fails all three habitat surrogate requirements: its causal link between the Indiana bat and the geographic bounds of the take limit is arbitrary, it lacks an explanation as to why a numerical limit is impractical, and it lacks a clear enforcement standard.
See
The Northern Long-Eared Bat (NLEB) is a threatened migratory bat. Pipeline construction will remove 171 acres of trees within five miles of a Northern Long-Eared Bat hibernaculum identified as PH-S018. J.A. 425. In 2016, FWS promulgated a generally applicable final rule that governs most incidental take of the Northern Long-Eared Bat.
Endangered and Threatened Wildlife and Plants; 4(d) Rule for the Northern Long-Eared Bat
,
FWS set the take limit as: harming or harassing a "[s]mall percent of individuals present within 0.4 acres." J.A. 443. The agency explained that "incidental take of NLEB will be difficult to detect for the following reasons: species has small body size, finding a dead or impaired specimen is unlikely, and species occurs in habitat (forest and caves) that makes detection difficult." J.A. 443.
The incidental take authorized here is not a proper habitat surrogate because it lacks two of the three necessary elements. We find that FWS has demonstrated a causal link between the Northern Long-Eared Bat and the 0.4 acres listed in the take limit. But, as with the other species, the take limit is not a true habitat surrogate: take is limited to a "small percent" of Northern Long-Eared Bats within the 0.4 acres. Although the geographic bounds are fixed, the pipeline can only take a subset of individuals located within those bounds . And it is impossible to know how many bats constitute a "small percent." Therefore, there is no clear and enforceable standard of take. Moreover, FWS has not shown that a numeric take limit is impractical in such a small geographic area.
In sum, the take limit for the Northern Long-Eared Bat fails two of the habitat surrogate requirements: it lacks an explanation as to why a numerical limit is impractical, and it lacks a clear enforcement standard.
See
* * *
We find that FWS has failed to create proper habitat surrogates, failed to explain why numeric limits are not practical, and failed to create enforceable take limits for the Clubshell, the Rusty Patched Bumble Bee, the Madison Cave Isopod, the Indiana Bat, and the Northern Long-Eared Bat. Because FWS's vague and unenforceable take limits are arbitrary and capricious, we vacated the ITS pending the issuance of this opinion.
Sierra Club v. United States Dep't of the Interior
,
III.
We next address petition No. 18-1082, which challenges the National Park Service (NPS)'s decision to issue a permit allowing the ACP to cross the Blue Ridge Parkway. Petitioners Sierra Club and Virginia Wilderness Committee
8
argue that
A.
The Blue Ridge Parkway is a component of the National Park System, linking the Shenandoah National Park in Virginia to the Great Smoky Mountains National Park in North Carolina. 16 U.S.C. § 460a-2. Like the rest of the National Park System, the Parkway is managed by NPS. According to NPS's Management Plan, the Blue Ridge Parkway serves not only as a connector between destinations but also as a recreational and scenic site in itself. J.A. 623-24.
The ACP's proposed pathway intersects with the Blue Ridge Parkway. Accordingly, FERC's final approval of the pipeline hinges on NPS granting a right-of-way to cross the Parkway. As proposed, the pipeline would drill and pass underneath the Parkway without breaching the Parkway's surface. However, the proposed route would require removing all of the trees from a portion of a nearby forest, leaving a vertical clearing that would be visible from the Parkway. J.A. 1018. During initial construction of the pipeline, that clearing would be 125 feet wide. Once construction is complete, the clearing would be reduced to a permanent 50-foot wide corridor, reserved for pipeline maintenance purposes. J.A. 325, 1035.
A visual impact study conducted by ACP and overseen by NPS concluded that the corridor would be visible from at least one key observation point along the Parkway, thus significantly decreasing the park's scenic value. J.A. 1020. Specifically, the analysis concluded that "[v]iews of the ACP corridor from the Three Ridges overlook ... would likely be inconsistent with NPS management objectives, given the proximity to the viewer, the axial nature of the view, and the corridor's contrast with the surrounding forest." J.A. 1020.
On December 12, 2017, NPS issued a revocable permit granting right-of-way to ACP, subject to a list of terms and conditions. The permit cites only 16 U.S.C. § 460a-8 for its statutory authority. J.A. 897. The permit decision does not reference any harm to the Parkway's scenic or conservation value or the effectiveness of any mitigation strategies.
Petitioners now seek review of the right-of-way permit, arguing that NPS failed to comply with the Mineral Leasing Act and the Blue Ridge Parkway Organic Act.
B.
We first address standing. Petitioners Sierra Club and the Virginia Wilderness Committee are organizational plaintiffs that have associational standing to sue "on behalf of [their] members when [their] members would otherwise have standing to sue in their own right." 9
Members of the petitioning environmental groups aver that they regularly use and enjoy the Blue Ridge Parkway and its scenic views. Petitioners Opening Brief Addendum (Pet. Add.) 115, 126, 130, 171. One member avers that she and her husband have enjoyed using the Three Ridges Overlook for the past thirty-five years. Pet.
The affidavits provided by Petitioners' members sufficiently demonstrate injury in fact. "[E]nvironmental plaintiffs adequately allege injury in fact when they aver that they use the affected area and are persons for whom the aesthetic and recreational values of the area will be lessened by the challenged activity."
Laidlaw Envtl. Servs.
,
Petitioners have also shown that their members' injuries are fairly traceable to, or caused by, NPS's right-of-way decision. To establish traceability, Petitioners' members must show that the challenged action is "in part responsible for frustrating" their ability to enjoy the Blue Ridge Parkway.
See
Libertarian Party of Va. v. Judd
,
To the contrary, NPS argues that the alleged injuries are not directly caused by the segment of the pipeline that crosses
Finally, and for similar reasons, Petitioners have demonstrated redressability. To satisfy this element of standing, Petitioners must show that "it is likely, as opposed to merely speculative, that the injury will be redressed by a favorable decision."
Laidlaw Envtl. Servs.
,
NPS nonetheless argues that the pipeline might be re-routed in a way that remains close to the Blue Ridge Parkway such that it could still disrupt views from the Parkway without intersecting it. However, this argument is mere speculation. NPS has not provided any support for its claim that the pipeline would materially affect views from the Parkway even if ACP were denied a right-of-way. The crossing of the Parkway necessitated the maintenance corridor that harms views from the Parkway, and we simply see no reason why the pipeline would clear and maintain a permanent corridor near the Parkway if no crossing is (or can be) permitted by NPS. Just as Petitioners cannot establish redressability via speculation, NPS cannot simply hypothesize as to possible future harm to overcome the fact that a favorable ruling would redress Petitioners' only injury at this time.
Even assuming that such a re-routing were possible or even likely, NPS's argument still fails. The removal of even one obstacle to the exercise of one's rights, even if other barriers remain, is sufficient to show redressability.
See
Larson
,
In sum, Petitioners have shown that their members will suffer an injury in fact that is at least partly caused by NPS's actions and that is likely to be redressed by a favorable ruling. Because their members have shown that they would have standing in their own right, Petitioners have associational standing to bring this suit.
C.
We now turn to the merits of the petition, which presents two lines of argument against NPS's issuance of the right-of-way permit. First, Petitioners argue that NPS lacks general statutory authority to grant rights-of-way for oil and gas pipelines. Second, assuming such general authority exists, they argue that issuing the permit in this case violates the authorizing statute because it is not consistent with parkway purposes. Answering these questions requires us to interpret three statutory provisions-the two general right-of-way provisions under the Blue Ridge Parkway Organic Act and the definitional provision of the Mineral Leasing Act, which purportedly constrains agency authority under the Organic Act. We first consider what deference we owe to the agency's interpretation of these statutes and then address the parties' arguments.
The parties seem to assume, without any analysis, that NPS's interpretation of the relevant statutes is eligible for
Chevron
review.
See
Chevron, U.S.A., Inc. v. Nat. Res. Def. Council, Inc.
,
As the Supreme Court held in
Mead
, only an agency interpretation that carries the force of law is
Chevron
-eligible.
This case concerns the scope of authority granted by 16 U.S.C. § 460a-3 and § 460a-8 and the effect, if any, of the Mineral Leasing Act,
We now turn to the only relevant interpretation that NPS has rendered-its invocation of 16 U.S.C. § 460a-8. In its permit decision, NPS concluded that " § 460a-8 authorizes the Secretary of the Interior to grant revocable licenses or permits for rights-of-way over, across, and upon Parkway lands, under such terms and conditions as he may determine to be consistent with the use of such lands for parkway purposes." J.A. 897. This near-verbatim recitation of § 460a-8 is not accompanied by any explanation or rationale. Nor does the boilerplate language specifically address authorizations concerning natural gas pipelines, the focus of this case.
Applying
Mead
to NPS's interpretation of § 460a-8, the first consideration is whether Congress has delegated power to the agency to make legislative-type determinations.
See
A.T. Massey Coal Co. v. Holland
,
Even assuming that Congress has delegated interpretative power to NPS,
Mead
requires that the agency actually exercise that delegated authority before it can receive deference for its interpretation.
A.T. Massey
,
In this case, the right-of-way permit lacks virtually all of the procedural hallmarks of a legislative-type determination. First, the permit has no precedential value because it does not bind third-parties or otherwise set forth a general rule that controls future cases.
See
High Sierra Hikers Ass'n v. Blackwell
,
Having determined that NPS's interpretation of § 460a-8 is not entitled to
Chevron
review, we next consider whether it is entitled to a lesser form of deference under
Skidmore
. "The weight of such a judgment ... depend[s] upon the thoroughness evident in its consideration, the validity of its reasoning, its consistency with earlier and later pronouncements, and all those factors which give it power to persuade, if lacking power to control."
Skidmore
,
Accordingly, we interpret the relevant statutory provisions de novo .
2.
We first turn to the Mineral Leasing Act (MLA), codified at
Because the MLA does not authorize rights-of-way across national parks, Petitioners draw the negative implication that Congress has forbidden oil and gas pipelines from crossing the National Park System. For support, Petitioners cite to
Food & Drug Admin. v. Brown & Williamson Tobacco Corp.
, where the Supreme Court held that "the meaning of one statute may be affected by other Acts, particularly where Congress has spoken subsequently and more specifically to the topic at hand."
However,
Brown & Williamson
is inapposite. There, the Supreme Court denied the Food and Drug Administration (FDA) the power to regulate tobacco because Congress had "enacted several statutes addressing the particular subject of tobacco and health, creating a distinct regulatory scheme for cigarettes and smokeless tobacco."
In an effort to show that the MLA is all-encompassing and precludes oil and gas pipelines in the National Park System, Petitioners cite the MLA's exclusivity and retroactivity provisions.
Petitioners also argue that a ruling in the agency's favor would allow NPS and ACP to evade the policy choice that Congress made in the MLA, which subjects oil and gas pipelines to stringent requirements. However, the MLA's requirements, by the statute's plain text, never applied to the National Park System. Thus, there is simply nothing to evade. That is not to say that NPS has unbridled discretion to grant oil and gas rights-of-way-the agency still has to comply with the requirements of whatever authorizing statute it properly invokes. And, although the MLA does not preclude NPS from granting such rights-of-way, the statute's exhaustive requirements shed light on the rigor and thoroughness that Congress expects to accompany such weighty decisions, particularly given the National Park System's conservation mission.
See
Accordingly, we hold that the MLA neither authorizes nor precludes grants of
3.
Having determined that the MLA leaves intact NPS's right-of-way authority, we now consider the scope of authority conferred by the Blue Ridge Parkway Organic Act and NPS's compliance with its requirements. At issue are two provisions containing substantially similar language, 16 U.S.C. § 460a-3 and § 460a-8. Petitioners argue that neither provision authorizes the right-of-way permit in this case, while NPS and ACP argue that both provisions are independently sufficient sources of authority. To harmonize and give effect to both provisions, we conclude below that § 460a-8 applies only to a specific extension of the Blue Ridge Parkway that is not at issue in this case. Even assuming that either § 460a-3 or § 460a-8 confers general authority on NPS to grant oil and gas rights-of-way through Blue Ridge Parkway property, we conclude that NPS has acted arbitrarily and capriciously by failing to explain why ACP's pipeline is not inconsistent with parkway purposes.
Our analysis begins with the text. Section 460a-3 provides that:
In the administration of the Blue Ridge Parkway, the Secretary of the Interior may issue revocable licenses or permits for rights-of-way over, across, and upon parkway lands, or for the use of parkway lands by the owners or lessees of adjacent lands, for such purposes and under such nondiscriminatory terms, regulations, and conditions as he may determine to be not inconsistent with the use of such lands for parkway purposes.
16 U.S.C. § 460a-3.
Section 460a-8 provides that:
The Secretary of the Interior may issue revocable licenses or permits for rights-of-way over, across, and upon parkway lands, or for the use of parkway lands by the owners or lessees of adjacent lands, or for such purposes and under such terms and conditions as he may determine to be consistent with the use of such lands for parkway purposes.
16 U.S.C. § 460a-8.
To discern the scope of these two virtually identical provisions, we must determine how they interact with one another. NPS and ACP argue that § 460a-8 is broader than § 460a-3 because the former places an "or" in front of "for such purposes and under such terms and conditions as he may determine to be consistent with ... parkway purposes." Thus, NPS and ACP read § 460a-8 as authorizing three types of permits: (1) permits for rights-of-way over, across, and upon parkway lands; (2) permits for the use of parkway lands by the owners or lessees of adjacent lands; and (3) permits for other purposes that the agency determines to be consistent with parkway objectives. Meanwhile, because § 460a-3 lacks the final disjunctive "or," it would only authorize two types of permits, both of which must be consistent with parkway purposes: (1) permits for rights-of-way over, across, and upon parkway lands and (2) permits for the use of parkway lands by the owners or lessees of adjacent lands.
We find NPS and ACP's reading of § 460a-8 unpersuasive. Were we to adopt it, § 460a-8 would completely swallow § 460a-3 and render it a nullity. Indeed, § 460a-8 would be an implied repeal of § 460a-3 because it would remove the consistency requirement that previously constrained NPS's discretion. This construction also flouts a fundamental principle that undergirds every aspect of NPS's management of the National Park System
Petitioners have provided a more than reasonable interpretation of § 460a-8 that also gives effect to § 460a-3. Petitioners correctly point out that § 460a-8 was a later-enacted provision passed within a larger bill authorizing the construction and management of an extension of the Blue Ridge Parkway, which would run from North Carolina into Georgia.
See
Pub. L. No. 90-555, § 3,
Ordinarily, that conclusion would end our inquiry because it is a "fundamental rule of administrative law" that "a reviewing court, in dealing with a determination or judgment which an administrative agency alone is authorized to make, must judge the propriety of such action solely by the grounds invoked by the agency."
See
Sec. & Exch. Comm'n v. Chenery Corp.
,
As to NPS's authority under § 460a-3, the parties dispute two possible limitations. First, Petitioners argue that § 460a-3 authorizes the grant of rights-of-way only to "owners or lessees of adjacent lands."
See
16 U.S.C. § 460a-3. NPS and ACP counter that the "owners or lessees" clause only modifies "for the use of parkway lands." In other words, they believe that NPS may authorize only the Parkway's neighbors to "use" the Parkway, but NPS can grant rights-of-way to both neighbors and non-neighbors. Second, the parties dispute whether § 460a-3 allows NPS to grant rights-of-way for oil and gas pipelines notwithstanding the neighbors clause. Petitioners argue that oil and gas pipelines are categorically inconsistent with parkway purposes and that NPS therefore has no authority to grant a right-of-way for any oil or gas pipeline, not just the ACP. The MLA (
To the extent § 460a-3 confers such authority, before NPS can properly issue a right-of-way permit, it must make a threshold determination that granting the right-of-way is "not inconsistent with the use of such lands for parkway purposes" and the overall National Park System to which it belongs. Critically, Congress has defined the National Park System's "purpose" as "conserv[ing] the scenery, natural and historic objects, and wild life in the System units and [ ] provid[ing] for the enjoyment of the scenery, natural and historic objects, and wild life in such manner and by such means as will leave them unimpaired for the enjoyment of future generations."
The Blue Ridge Parkway also has its own conservation and preservation purpose, according to NPS's General Management Plan for the Parkway. Under the Plan, the Parkway's specific purposes are
We review NPS's factbound determination that the pipeline right-of-way is consistent with the purposes of the Parkway and the Park System under the deferential "arbitrary and capricious" standard set forth in
State Farm
.
See
Here, the agency decision is not accompanied by any explanation, let alone a satisfactory one. Instead, the permit merely recites that "NPS has determined that the proposed use or occupancy of the NPS-administered lands or waters described herein for the operation and maintenance of the Project, is consistent with the use of these lands for Parkway purposes" and provides no further elaboration. J.A. 897.
We find this lack of explanation particularly troubling given the evidence in the record indicating that the presence of the pipeline is inconsistent with and in derogation of the purposes of the Parkway and the Park System. Indeed, a visual impact study that NPS oversaw specifically concluded that the effect of the pipeline on views from the Parkway "would likely be inconsistent with NPS management objectives." J.A. 1020. The permit neither mentions this detrimental effect nor the efficacy of any mitigating steps.
See, e.g.,
Fred Meyer Stores, Inc. v. Nat'l Labor Relations Bd.
,
Nor does the NPS decision address whether the drilling required to install the
Compounding these omissions are elemental errors in what NPS does say. In addition to invoking an inapplicable statutory provision ( 16 U.S.C. § 460a-8 ) as the source of its authority, the NPS decision also cites an inapplicable set of regulations. In the permit, NPS seems to take as a given that regulations codified at 36 C.F.R. Part 14 govern the issuance of the ACP permit and its conditions. J.A. 897. However, those regulations were promulgated under what is now
Accordingly, we hold that NPS's permit decision is arbitrary and capricious. NPS began by invoking inapplicable laws. Even if this Court overlooks that error and assumes that NPS correctly interpreted the Organic Act to authorize rights-of-way for gas pipelines, NPS has not fulfilled its statutory mandate of ensuring consistency with values and purposes of the Blue Ridge Parkway unit and the overall National Park System.
* * *
In sum, we hold that Petitioners have standing to bring this challenge, that this Court owes no deference to the statutory interpretation contained in NPS's permit decision, that the MLA does not strip NPS of authority to grant rights-of-way for gas pipelines, and that NPS's decision to grant ACP a right-of-way was arbitrary and capricious for failing to explain the pipeline's consistency with the purposes of the Blue Ridge Parkway and the National Park System.
Having concluded that both FWS and NPS erred in issuing their respective authorizations, we turn to the final question of remedy. Respondents argue that this Court lacks authority to vacate the agency actions under the Natural Gas Act. However, Respondents' position is contrary to the plain text of the Natural Gas Act. The judicial review provision at issue provides,
If the Court finds that such order or action is inconsistent with the Federal law governing such permit and would prevent the construction, expansion, or operation of the facility subject to section 717b of this title or section 717f of this title, the Court shall remand the proceeding to the agency to take appropriate action consistent with the order of the Court.
15 U.S.C. § 717r(d)(3).
On its face, § 717r(d)(3) only applies to an agency action that "would prevent the construction" of the natural gas facility.
See
Islander E. Pipeline Co., LLC v. McCarthy
,
Because FWS and NPS have both granted authorizations in contravention of their respective statutory requirements, we conclude that the correct remedy is to vacate the ITS and the right-of-way permit, respectively.
V.
For the reasons in Parts II and IV, we previously vacated the ITS pending the issuance of this opinion.
Sierra Club
,
For the reasons in Parts III and IV, we now VACATE the right-of-way permit that NPS issued to ACP.
IT IS SO ORDERED.
An endangered species is "any species which is in danger of extinction throughout all or a significant portion of its range."
"Jeopardize the continued existence of means to engage in an action that reasonably would be expected, directly or indirectly, to reduce appreciably the likelihood of both the survival and recovery of a listed species in the wild by reducing the reproduction, numbers, or distribution of that species."
Some eight years prior to this 2015 final rule, the Ninth Circuit expressed doubt about habitat surrogates that are coextensive with the project's own scope.
Allen
,
We take judicial notice of this FWS record, which is also available on FWS's website.
See
Goldfarb v. Mayor & City Council of Balt.
,
When evaluating a challenged habitat surrogate, other courts have looked to FWS's ability to set numeric limits in other circumstances.
E.g.
,
Ctr. for Biological Diversity v. Bureau of Land Mgmt.
,
Because a colony is a biological unit founded by a single queen and can vary in size, "one colony" cannot function as an enforceable numeric limit. FWS concedes as much by arguing that it used a habitat surrogate for the Rusty Patched Bumble Bee, Gov't Resp. Br. 25-26, since habitat surrogates cannot be used unless a numeric limit is impractical.
U.S. Fish & Wildlife Serv., Indiana Bat Range Map (Mar. 12, 2018), https://www.fws.gov/midwest/endangered/mammals/inba/rangemapinba.html (saved as ECF opinion attachment 2).
As explained in note 4,
supra
, we also take judicial notice of these FWS records, two of which are available on FWS's website.
See
Goldfarb
,
The Defenders of Wildlife is a petitioner in only No. 18-1083. For purposes of this section, we use "Petitioners" to refer to the Sierra Club and the Virginia Wilderness Committee.
Associational standing also requires that "the interests at stake [be] germane to the organization's purpose, and [and that] neither the claim asserted nor the relief requested requires the participation of individual members in the lawsuit."
Laidlaw Envtl. Servs.
,
We find it remarkable that counsel representing the National Park Service, which is charged with "provid[ing] for the enjoyment of the scenery, natural and historic objects, and wild life in such manner and by such means as will leave them unimpaired for the enjoyment of future generations," would seem to take a litigation position that regards the premier conservation agency's role as no more than highway maintenance.
See
As noted previously, FERC's authorization for ACP to begin construction is conditioned on the existence of valid authorizations from both FWS and NPS. Absent such authorizations, ACP, should it continue to proceed with construction, would violate FERC's certificate of public convenience and necessity. See J.A. 362-84.
As to the Mineral Leasing Act in particular, this Court also would not defer to any NPS interpretation because NPS is not the agency charged with implementing the statute.
See
Indeed,
Mead
noted that even precedential decisions may not always be
Chevron
-eligible.
The MLA's definitional provision contains two other exceptions not relevant to this case.
See
We note that even NPS's permit decision indicated that it only had authority under § 460a-8 to grant a right-of-way if it determined that such a grant is consistent with parkway purposes. J.A. 897. Therefore, NPS's litigation position is actually contrary to the agency decision that it purports to defend.
Compare J.A. 897 ("§ 460a-8 authorizes the Secretary of the Interior to grant revocable licenses or permits for rights-of-way over, across, and upon Parkway lands, under such terms and conditions as he may determine to be consistent with the use of such lands for parkway purposes.") with 16 U.S.C. § 460a-3 ("[T]he Secretary of the Interior may issue revocable licenses or permits for rights-of-way over, across, and upon parkway lands ... under such nondiscriminatory terms, regulations, and conditions as he may determine to be not inconsistent with the use of such lands for parkway purposes.").
National Park Service, Blue Ridge Management Plan, 9 (Jan. 2013), https://parkplanning.nps.gov/document.cfm?parkID=355 & projectID=10419 & documentID=51305 (saved as ECF opinion attachment 4).
