Lead Opinion
Plaintiff-Appellant Sierra Club filed this action on January 29, 2009 under the citizen suit provision of the Clean Air Act (“CAA”), 42 U.S.C. § 7604(a)(3), alleging that Defendant-Appellee Two Elk Generation Partners (“Two Elk”) is attempting to build a coal-fired power plant (“Power Plant”) with an invalid Prevention of Significant Deterioration (“PSD”) permit in violation of the CAA.
Background
Two Elk first proposed building the Power Plant in 1996, and the Wyoming Department of Environmental Quality (“DEQ”) issued a construction permit, CT-1352, in February 1998. Aplt.App. at 14. The DEQ administers and enforces the Wyoming Environmental Quality Act and is the primary regulatory authority for air quality in Wyoming. See Powder River Basin Res. Council v. Wyo. Dep’t of Envtl. Quality,
At some point, DEQ determined that Two Elk commenced construction prior to May 29, 2005, as required by the Permit. Id. at 88. Two Elk then filed an unopposed motion to dismiss the matter before the Council. Id. at 87. On July 18, 2005, after a hearing at which the parties were given an opportunity to be heard concerning the motion, the Council issued an order (“2005 Order”) finding that Two Elk had commenced construction on the Power Plant by pouring a foundation for the Power Plant’s exhaust stack and entering into a contract to purchase a main boiler. Id. at 87-88. The Council concluded that the Permit was valid, dismissed the matter, and terminated jurisdiction. Id.
On August 22, 2007, DEQ sent a letter to Two Elk stating that the Permit was no longer valid because construction had been discontinued for more than twenty-four months since first commenced. Id. at 208. On October 19, 2007, Two Elk filed a Petition for Review and Request for Immediate Stay with the Council, asking the Council to review the revocation of the Permit. Id. at 145. On November 21, 2007, after Two Elk disclosed confidential business information to DEQ, the two parties entered a Joint Stipulated Settlement
The Council conducted a hearing on November 28, 2007 where Council members expressed concern that the delay in construction meant that the Permit was outmoded and did not require the implementation of newer and more efficient emissions technologies, and also that Two Elk was tying up a portion of Wyoming’s allotted pollution. Id. at 104-06. Two Elk assured the Council that it was taking steps to complete construction, and a DEQ representative stated that the Settlement Agreement required Two Elk to apply newer technology, as required by DEQ-issued permits for other power plants. Id. at 97. On December 3, 2007, the Council issued an order approving the Settlement Agreement, approving the withdrawal of the DEQ’s August 22 letter, and dismissing Two Elk’s appeal (“2007 Order”). Id. at 114-15. The 2007 Order specifies that all the terms of the Settlement Agreement are adopted. Id. at 114.
At no point prior to the 2007 Order did Sierra Club attempt to intervene in the proceedings before the Council. Id. at 147. On December 20, 2007, however, Sierra Club filed a Motion to Intervene and for Reconsideration and Vacation of the Council’s 2007 Order. Id. The Council determined that it lacked jurisdiction over the dispute and dismissed the motion. Id.
On December 20, 2007, Sierra Club also filed a Petition for Review of Administrative Action in state district court pursuant to the Wyoming Administrative Procedures Act, Wyo. Stat. Ann. § 16-3-114. ApltApp. at 144. Sierra Club argued, among other things, that none of the facts in the Joint Stipulated Settlement Agreement supported the Council’s 2007 Order approving DEQ’s determination that Two Elk had engaged in continuous, on-site construction during the relevant twenty-four month period. Id. at 147-48. The state court rejected this argument and affirmed the Council’s 2007 Order on March 12, 2009. Id. at 160. On April 9, 2009, Sierra Club appealed to the Wyoming Supreme Court, but voluntarily dismissed that appeal. Id. at 313, 320.
On January 29, 2009, as the state court decision was pending, Sierra Club filed its citizen suit under the CAA in federal court, seeking a declaration that Two Elk lacked a valid permit to construct the Power Plant in violation of 42 U.S.C. § 7475(a), and penalties under 42 U.S.C. § 7604(g). Id. at 22. Specifically, Sierra Club asserted that the Permit is invalid because Two Elk failed to commence construction prior to May 29, 2005, and, even if it did commence construction, the Permit is still invalid because Two Elk discontinued construction for a period of twenty-four months after that time. Id. at 21-22. Two Elk filed a motion to dismiss under Fed.R.Civ.P. 12(b)(6), arguing that these issues were already decided by the Council and thus were barred by the doctrine of claim preclusion. Id. at 61-66. In addition, Two Elk argued that the court should abstain from exercising federal jurisdiction over the matter pursuant to the Burford abstention doctrine. Id. at 51-61.
The district court declined to abstain under Burford, but granted Two Elk’s motion to dismiss because Sierra Club’s citizen suit was barred by the Council’s 2005 and 2007 Orders under the doctrine of issue preclusion. Id. at 330-32, 336-45.
On appeal, Sierra Club argues that the district court erred because the statutory language of the CAA establishes the circumstances in which a citizen suit may be precluded by a state action and those circumstances were not met here. In addition, Sierra Club contends that its citizen suit cannot be barred under the doctrine of issue preclusion because Sierra Club was not a party to the administrative proceedings and was not in privity with the DEQ, and the Council did not resolve disputed issues of fact in an adversarial proceeding. Aplt. Br. at ii-iii, 1-2. This court reviews a dismissal under Fed.R.Civ.P. 12(b)(6) de novo. Moss v. Kopp,
Discussion
A. Preclusion Under the CAA
Sierra Club first argues that the statutory language of the CAA establishes the only way in which a citizen suit may be precluded by a state action, and that those circumstances were not present here. Aplt. Br. at 31-32. Under the CAA, a citizen suit may not be commenced “if the Administrator or State has commenced and is diligently prosecuting a civil action in a court of the United States or a State to require compliance with the standard, limitation, or order, but in any such action in a court of the United States any person may intervene as a matter of right.” 42 U.S.C. § 7604(b)(1)(B).
Sierra Club’s argument that the CAA’s statutory language embodies Congress’s intent to displace the full faith and credit statute, 28 U.S.C. § 1738, and the common law doctrines of issue and claim preclusion is not persuasive. Numerous courts have applied § 1738 and the common law preclusion doctrines to citizen suits under the CAA or Clean Water Act (“CWA”) where, at the time the citizen suit was commenced, the State or Administrator was not “diligently prosecuting” an enforcement action. See, e.g., Ellis v. Gallatin Steel Co.,
To be sure, “an exception to § 1738 will not be recognized unless a later statute contains an express or implied partial repeal.” Kremer v. Chem. Constr. Corp.,
The CAA’s commencement bar to citizen suits applies only if the “Administrator or State has commenced and is diligently
Applying the doctrine of issue preclusion, the district court held that Sierra Club’s citizen suit is barred by the Council’s 2005 and 2007 Orders. Aplt.App. at 345. The court explained that it need not consider the Wyoming district court’s order in its preclusion analysis. Id. at 346. Under our preclusion analysis, we conclude that Sierra Club’s citizen suit is barred, but on a slightly different rationale than the district court’s. First, the issue of whether Two Elk engaged in continuous construction is precluded by the Wyoming district court’s March 12, 2009 Order. In addition, as the federal district court concluded, the issue of whether Two Elk commenced construction before May 29, 2005 is precluded by the Council’s 2005 Order.
B. Preclusive Effect of the Wyoming District Court’s March 12, 2009 Order
“ ‘The preclusive effect of a state court judgment in a subsequent federal lawsuit generally is determined by the full faith and credit statute,’ 28 U.S.C. § 1738, which ‘directs a federal court to refer to the preclusion law of the State in which judgment was rendered.’ ” Brady v. UBS Fin. Servs., Inc.,
In deciding whether the Wyoming district court’s affirmance of the Council’s 2007 Order precludes the current suit, we must determine whether the decision would be entitled to preclusive effect under Wyoming law and whether it satisfied the minimum standards of due process. Id. at 481-82,
Under Wyoming law, “[c]ollateral estoppel and res judicata are analogous, but not synonymous.” Erwin v. Wyo., Dep’t of Family Servs.,
Courts should consider the following factors to determine whether collateral estoppel applies under Wyoming law:
(1) whether the issue decided in the pri- or adjudication was identical with the issue presented in the present action; (2) whether the prior adjudication resulted in a judgment on the merits; (3) whether the party against whom collateral estoppel is asserted was a party or in privity with a party to the prior adjudication; and (4) whether the party against whom collateral estoppel is asserted had a full and fair opportunity to litigate the issue in the prior proceeding.
Brockman v. Wyo. Dep’t of Family Servs.,
The Wyoming district court’s May 12, 2009 Order precludes the issue of whether Two Elk engaged in continuous construction of the Power Plant, as the four requirements of collateral estoppel under Wyoming law and the minimum requirements of due process are met. First, the issue — whether Two Elk engaged in continuous construction of the Power Plant— was identical. In state court, Sierra Club argued that “none of the facts described in the settlement agreement support [the Council’s] Order approving DEQ’s determination that [Two Elk] engaged in a continuous program of physical on-site construction of [the Power Plant] between 2005 and 2007.” Aplt.App. at 147. It makes the same argument here. The second and third elements are met because the court issued a judgment on the merits, and Sierra Club was a party to the proceeding. Finally, Sierra Club had a full and fair opportunity to litigate the issue before the court. A hearing was held on June 23, 2008 in which all parties were represented. Id. at 144. Although the arguments dealt primarily with the appropriateness of the Council as a party— Sierra Club initially named the Council as a respondent — both Two Elk and Sierra Club submitted briefs regarding the pertinent issues, and the court concluded that no further argument would be of assistance in determining the matter. Id. The court reviewed the entire record in making its ultimate decision. Id.
In its order, the court explained that “[a]s always, an agency’s conclusions of law are reviewed de novo, and are afforded no deference. The legal conclusions will be affirmed only if they are in accordance with the law.” Id. at 150 (citing Dale v. S & S Builders, LLC,
Sierra Club’s argument that preclusion is not appropriate because the Wyoming court reviewed only a closed record that Sierra Club never had the opportunity to develop is without merit. Aplt. Reply Br. at 32. Sierra Club did not attempt to intervene in the proceedings until after the Council issued its 2007 Order. Aplt.App. at 147. Indeed, during the federal district court’s hearing on Two Elk’s motion to dismiss, counsel for Sierra Club admitted that Sierra Club did not intervene at an earlier stage because it believed DEQ would adequately prosecute the matter. Id. at 338-39. Specifically, counsel stated that “the hope was that the state would enforce this issue of the permit becoming invalid. And as far as the Sierra Club could tell, that was happening until we got word of the settlement agreement between Two Elk and DEQ in 2007, about a week before that was approved by council.” Id. Further, Sierra Club never appeared at the Council hearing on November 28, 2007 to contest the Stipulated Settlement Agreement between Two Elk and DEQ, despite a week’s notice that the Council would be holding a hearing on the settlement. See Aplt. Br. at 55. As the state court observed, “[throughout the administrative process, [Sierra Club] remained mute and chose to speculate on the outcome of the dispute. When the dispute was concluded and [Sierra Club] determined that misfortune had come their way, they then chose to voice their displeasure. This conduct is contrary to the Wyoming supported policies of settlement and finality and will not be condoned.” Aplt.App. at 158. “The fact that [Sierra Club] failed to avail [itself] of the full procedures provided by state law does not constitute a sign of their inadequacy.” Kremer,
Accordingly, the Wyoming district court’s March 12, 2009 Order affirming the Council’s 2007 Order precludes the issue of whether Two Elk engaged in continuous construction. We now address whether the Council’s 2005 Order precludes the issue of whether Two Elk timely commenced construction on the Power Plant.
C. Preclusive Effect of the Council’s 2005 Order
“The United States Supreme Court has ‘long favored the application of the common-law doctrines of collateral estoppel (as to issues) and res judicata (as to claims) to those administrative bodies that have attained finality.’ ” Brockman,
1. Elements One, Tivo, and Four of Collateral Estoppel Under Wyoming Law are Satisfied
Elements one, two, and four of collateral estoppel under Wyoming law are met here. See Brockman,
2. DEQ and Sierra Club were in Privity During the Council’s 2005 Proceedings
Under Wyoming law, “[collateral estoppel may be applied to one who was a party to the prior proceeding or to one who was in privity with a party.” Worman v. Carver,
Sierra Club argues that we must look to the Supreme Court’s recent opinion in Taylor v. Sturgell,
It is not clear how Taylor will affect the Wyoming Supreme Court’s privity analysis. Some state courts, relying on the Supreme Court’s statement in Richards v. Jefferson County,
The doctrine of parens patriae “refers to the ‘right of a State to sue ... to prevent or repair harm to its “quasi-sovereign” interests.’ ” BP Am., Inc. v. Oklahoma,
In Satsky, we concluded that citizens of Colorado were in privity with the State of Colorado under the doctrine of parens patriae where the State filed suit against the defendant to protect its citizens against air pollution. Id. at 1469. Similarly, in EPA v. City of Green Forest, the Eighth Circuit decided that plaintiffs who filed suit under the CWA were in privity with the EPA— which is charged with enforcing the CWA on behalf of all citizens — where the EPA, acting as parens patriae, brought an action against a polluter that resulted in a consent decree.
Relying on Satsky, the district court concluded that DEQ was in privity with the citizens of Wyoming under the parens patriae doctrine. AplhApp. at 339. We agree. The Wyoming Supreme Court recently explained that “[a]s the administrative agency statutorily charged with carrying out the purposes of the Environmental Quality Act, including the promulgation, administration and enforcement of the Act’s provisions and any rules and regulations, DEQ represents the State’s legal interest ... before the [Council].” Wyo. Outdoor Council,
Our discussion of the CWA’s “diligent prosecution” standard in Karr v. Hefner,
DEQ was diligent in requiring compliance with the CAA before the Council in 2005. On October 23, 2002, Two Elk filed a petition with the Council contesting DEQ’s decision that Two Elk’s CT-1352A permit had terminated because Two Elk had failed to commence construction prior to August 20, 2002. Aplt.App. at 87. Two Elk and DEQ then entered into a Joint Stipulation and filed it with the Council on May 28, 2003. Id. The terms of the stipulation included an agreement to extend the deadline for commencing construction and to reduce certain emissions standards. Id. The Council approved the Joint Stipulation and retained jurisdiction over the matter to ensure compliance with the terms of the stipulation. Id. In accordance with the stipulation, DEQ issued the current Permit, which required Two Elk to commence construction before May 29, 2005. Id. at 88.
Two Elk submitted documentation showing that it commenced construction on the Power Plant to DEQ, and DEQ found as a matter of fact that “prior to May 29, 2005, [Two Elk] completed the construction of the foundation for the main stack, and entered into a binding written contract to purchase a site-specific boiler.” Id. Two Elk then moved to dismiss the matter before the Council. Id. at 87. On July 18, 2005, after a June 27, 2005 hearing at which the parties were given an opportunity to be heard concerning the motion, the Council found that “[Two Elk] has ... commenced construction as required by [the Permit],” and dismissed the matter. Id. at 87-88.
Even though Sierra Club disagrees with the position DEQ took and was not satisfied with the result of the Council’s 2005 Order, DEQ acted to ensure that Two Elk commenced construction before May 29, 2005, in accordance with the PSD Permit.
We conclude that DEQ was in privity with the citizens of Wyoming in the 2005 Council proceedings under the doc
3. The Council Resolved Disputed Issue of Fact in an Adversarial Proceeding
Sierra Club also argues that the Council’s 2005 Order does not preclude the issue of whether Two Elk commenced construction because the Council never resolved disputed issues of fact in an adversarial proceeding as required by Wyoming law. See Slavens,
Sierra Club’s argument that the Council’s 2005 Order should not be given preclusive effect because the Council did not make any findings of fact is without merit. Sierra Club cites Morgan v. City of Rawlins,
D. The Dissent
The dissent contends that privity between Sierra Club and DEQ cannot be established under Satsky, Green Forest, or Friends, stressing that privity is not appropriate where the DEQ never initiated an action in federal court. It also argues that the court expands the doctrine of parens patriae such that any suit in which a state appears as a party is a parens patriae proceeding. We disagree and note that citizen suits under the similarly worded CWA are “meant to supplement rather than to supplant governmental action.” Gwaltney,
The dissent identifies and places great weight on various “limitations” the Satsky court placed on parens patriae actions. But the court never imposed such limitations. In Satsky, the court of appeals mentioned that the district court had determined the State represented its citizens, and then explained that the critical question for maintaining a parens patriae
While “agency inaction,” Green Forest,
The dissent also misreads Friends. The court there never held that an action must take place in a court to establish privity under the doctrine of parens patriae. As the dissent observes, that question was never before the court. Rather, the court “look[ed] to” the CWA to determine whether a State’s action was “diligent” under the Restatement (Second) of Judgments § 41(l)(d). Friends,
We do not hold, as the dissent contends, that a state agency’s administrative adjudication of environmental regulations always creates privity. As we noted in Satsky, “[t]here is no definition of privity which can be automatically applied to all cases involving the doctrines of res judicata and collateral estoppel since privity depends upon the circumstances.”
Finally, policy factors weigh in favor of preclusion. First, Sierra Club’s failure to
In addition, implicit in the Wyoming district court’s holding that Two Elk did not cease construction is a subsidiary finding that Two Elk commenced construction in the first instance. As the court explained, the Permit required that “construction once commenced may not be discontinued for a period of twenty-four months or more.” Aplt.App. at 159 (emphasis added). In order to determine whether Two Elk ceased construction, Two Elk must have commenced construction.
The public policy of finality of judgments also supports our conclusion. The Wyoming Supreme Court has repeatedly recognized that the doctrines of res judicata and collateral estoppel are founded upon
the interest held by society in having differences conclusively resolved in a single action thereby avoiding the vexation and expense which are associated with piecemeal litigation. The necessity for sustaining this social interest is the justification for the doctrines of res judicata and collateral estoppel.... These doctrines ... promote the reliance by citizens of the state upon courts to settle their disputes and they conserve judicial resources.
Dowlin v. Dowlin,
AFFIRMED.
Notes
. The following acronyms are utilized:
CAA Clean Air Act
Council Wyoming Environmental Quality Council
CWA Clean Water Act
DEQ Wyoming Department of Environmental Quality
PSD Prevention of Significant Deterioration
WAQSR Wyoming Air Quality Standards and Regulations
. While it is true, as the dissent observes, that Wyoming courts review the factual determinations of an agency under a substantial evidence test, see Goodman,
. The Wyoming Environmental Quality Act “is intended to be compatible with, and at least as stringent as, the federal Clean Air Act.” Powder River Basin Res. Council,
. We note that our use of the phrase "diligent prosecution” is not an interpretation of the CAA's statutory language in 42 U.S.C. § 7604(b)(1)(B). Rather, we are using the diligence standard to determine whether privity existed between DEQ and Two Elk under the parens patriae doctrine for purposes of collateral estoppel.
. We reject Sierra Club’s argument that it was not in privity with DEQ because of its national membership. As the Ninth Circuit has pointed out in an unpublished opinion, while a state acting pursuant to its parens patriae authority typically acts on the behalf of its own citizens, privity can still exist between the state and an organization with out-of-state members where the public interest being represented by both parties is overwhelmingly that of the state. N. Cal. River Watch v. Humboldt Petroleum, Inc.,
Dissenting Opinion
dissenting.
Because my colleagues expand the well-defined principles of parens patriae to include preclusion based on state intra-agency proceedings and because they misapply the doctrine of collateral estoppel, I respectfully dissent.
The majority concludes that the common law applies to citizen suits under the Clean Air Act and thereby seeks to invoke par-ens patriae standing. But my colleagues ignore the Clean Air Act’s impact on common-law principles.
I
In determining whether the 2005 Order has collateral estoppel effect, the majority correctly observes that the Wyoming Supreme Court would look to federal law. (Majority Op. 1267.) I disagree, however, with my colleagues’ understanding of the manner in which federal law applies. My objection primarily concerns the third element of collateral estoppel: “whether the party against whom collateral estoppel is asserted was a party or in privity with a party to the prior adjudication.” Brock-man v. Wyo. Dep’t of Family Servs.,
Three analytical frameworks could guide an inquiry into whether Sierra Club was in privity with the DEQ as to the 2005 Order. Examples of these analyses are set forth in the case law. The first, articulated in Satsky v. Paramount Communications, Inc.,
A
I do not quarrel with the majority’s statement that a state is assumed to represent the.interests of its citizens if a state sues another party in a parens patriae suit. Thus, if a citizen were to sue to redress an identical injury, the citizen suit may be precluded. Cf. Satsky,
1
Parens patriae is a standing doctrine that allows states to vindicate their interests in federal court.
Properly applied, the parens patriae doctrine is utilized when a state purports to act for all of its citizens in litigation, generally before the federal courts. The core purpose of parens patriae is to extend “special solicitude” to states litigating in federal courts. Massachusetts v. EPA,
Moreover, mere enforcement of an agency’s organic statute is not a parens patriae suit. See United States v. Hooker Chems. & Plastics Corp.,
Satsky also articulates the requirement that a state plead an injury to one of its quasi-sovereign interests. Id. In 1907, the Supreme Court explained that one such quasi-sovereign interest is a state’s environment:
This is a suit by a state for an injury to it in its capacity of quasi-sovereign. In that capacity the State has an interest independent of and behind the titles of its citizens, in all the earth and air within its domain. It has the last word as to whether its mountains shall be stripped of their forests and its inhabitants shall breathe pure air.
Without the limitations articulated in Satsky, any suit whatsoever in which a state appears as a party, ipso facto, would be a parens patriae proceeding.
2
Satsky leaves no doubt that the Wyoming Department of Environmental Quality’s appearance before the Wyoming Environmental Council (both being under the same statutory umbrella
First, the suit was not brought in federal court. It was brought before a state administrative agency. Although federal courts sometimes grant preclusive effect to state agency proceedings, the parens patriae doctrine is not a matter of comity between the state and federal judiciaries. Rather it is a doctrine of standing which affords state officials a platform from which to vindicate their quasi-sovereign interests in federal court. The 2005 Order is not entitled to the same preclusive effect we afforded the consent decree in Satsky or the “special solicitude” the Court gave to the state in Massachusetts because it did not arise from federal litigation.
Second, the DEQ did not assert that it was suing on behalf of the citizens of Wyoming. Cf. Hooker,
Third, the DEQ’s exercise of sovereign authority was necessarily limited by the CAA. In expressly creating a federal right of action, the CAA minimizes a state’s need to assert “quasi-sovereign” interests apart from the federal scheme. Cf. Tenn. Copper Co.,
By intentionally overlooking the circumscribed view of parens patriae expressed in Satsky, the majority hopes to create a new rule that a state agency’s administrative adjudication of environmental regulations always creates privity. This expansion of the parens patriae doctrine would render citizen suit provisions a dead letter in spite of the Supreme Court’s admonition against “extraordinary application of the common law of preclusion” that undermines federal statutes. Taylor v. Sturgell,
B
Although Satsky strongly supports the conclusion that Sierra Club cannot be precluded based on a parens patriae rationale, Sierra Club would still prevail under the frameworks established by our sister circuits. The Seventh Circuit and the Eighth Circuit have grappled with the disconnect between the common law and the citizen suit provisions of the CAA and CWA. Each has adopted a test to determine whether a state has adequately represented the interests of its citizens and thus established privity. Compare Green Forest,
1
In Green Forest, the Eighth Circuit considered the estoppel effect of a consent decree entered into by the EPA and Tyson Foods. See
2
In Friends, the Seventh Circuit dealt directly with the interaction between the citizen suit provisions and common-law preclusion.
Focusing on this aspect of common-law preclusion, Friends determined that the common law and the statute dovetail neatly: the central question becomes whether a state diligently prosecuted a matter. Friends,
This approach balances our duties to give effect to state judgments under the Full Faith and Credit Statute, 28 U.S.C.
[the Friends approach] does not give the polluter a pass simply because it has reached a settlement with a government enforcement agency. On the other hand, it does not require a showing of immediate, perfect compliance when the polluter and a government enforcement agency have reached a settlement that puts into place a complex remediation plan.
St. Bernard Citizens,
3
A faithful application of Friends leads inexorably to the conclusion that Sierra Club was not in privity with the DEQ. The intra-agency action to which the majority would grant preclusive effect was initiated by Two Elk before the Wyoming Environmental Council, defended by the Wyoming Department of Environmental Quality, and settled through that same agency’s proceedings. My colleagues determine that, under Friends, the DEQ diligently prosecuted the action below and the 2005 Order is preclusive. But Friends adopted the statutory test in defining privity.
The Seventh Circuit did not have to consider the requirement in the CWA that the action be commenced in a court because the settlement at issue involved an adjudication before a Wisconsin state court. Friends,
Fidelity to Friends requires a determination of whether a “judicial action is capable of requiring compliance with the Act and is calculated to do so.”
But even assuming, arguendo, that Friends permits an agency’s decision to be given preclusive effect, the DEQ’s purported enforcement actions in this case were not “diligent prosecutions” as that phrase is generally understood. Proceedings were initiated by Two Elk upon the DEQ’s notification to the company that its permit expired. At a 2007 hearing, a representative of the DEQ explained that such letters are merely notifications and not any sort of “affirmative action in terms of repealing, revoking, renewing a permit.” The DEQ’s understanding of the role of its letter as non-prosecutorial is supported by the reasoning of the Seventh Circuit — as that court noted, “writing a letter would hardly be described as commencing or prosecuting an action.”
4
For similar reasons, Sierra Club is not precluded from bringing the present action even under the approach in Green Forest. In that case, the court squarely rejected the notion that declining to sue could curry preclusive effect. Green Forest,
Indeed, Sierra Club persuasively argues that the DEQ did not act in the citizen plaintiffs’ interests. There is no suggestion that Sierra Club shares any proprietary interest with Wyoming or the DEQ, which is generally required for a showing of privity. See Wyo. Med. Ctr. v. Wyo. Ins. Guar. Ass’n,
Thus, this case is unlike Karr, 475 F.3d 1192, in which the agency and the plaintiffs agreed the defendant was not compliant, but disagreed on the proper remedy to pursue. See id. at 1198. Sierra Club and the DEQ were at antipodes: one advocated prosecution and the other determined prosecution was not necessary. When courts have held a suit to be precluded by settlement or consent decree, the preclusive orders have contained “substantive provisions that on their face [were] directly designed to address” serious violations, St. Bernard Citizens,
II
Under Wyoming law, collateral estoppel does not apply when the proceedings sought to be estopped utilize a lower burden of proof than that utilized in the first proceeding. Elliott v. State,
In the state court proceeding, under a deferential substantial evidence standard, Sierra Club had the burden of showing “the agency’s conclusions were contrary to the overwhelming weight of the evidence in the record as a whole.” Goodman v. Foss,
Ill
Because I cannot concur with the majority’s understanding of federal or Wyoming law, I respectfully DISSENT.
. The majority rejects outright Sierra Club's argument that the CAA's plain language displaces common-law preclusion doctrines, relying on "[n]umerous courts” that have applied the doctrines in CAA or Clean Water Act ("CWA") cases. (Majority Op. 1263.) However, these cases assume without deciding that the common law controls the analysis. See Ellis v. Gallatin Steel Co.,
. The majority appears to interpret Satsky and Green Forest coterminously, but they are analytically distinct, as I explain below.
. The term may also refer to the common-law concept that the state has a duty to act as a guardian of children and the mentally disabled. This is the only way in which Wyoming courts have ever used the term. See, e.g., J.J.F. v. State,
. Although parens patriae generally refers to a state suing in federal court, some courts have loosely used the term “parens patriae” when referring more generally to the state's ability to sue on behalf of its citizens. See, e.g., Friends,
. The DEQ is an executive branch department, an agency under the Wyoming Administrative Procedure Act, empowered to enforce the Wyoming Environmental Quality Act. Wyo. Stat. §§ 16-3-101(b)(i), 35-11-104, -110(a). That act also establishes the Council to act as the adjudicative body for the DEQ. §§ 35-11-111,-112.
. And a later settlement discussed in the 2007 Order disclaimed any binding effect on non-parties (“[t]he rights, duties, and obligations contained in this Agreement shall operate only among [the DEQ and Two Elk]”).
. This was the basis for the DEQ’s argument that Sierra Club did not have state standing. The state court rejected this notion, concluding that Sierra Club had standing.
. Green Forest’s reliance on these precedents was questionable. For example, the court relied up on United States v. Olin Corp.,
. The Wyoming Supreme Court has favorably cited the Restatement (Second) of Judgments on matters of preclusion. See, e.g., Fuentes v. Jednat, 229 P.3d 949, 951-52 (Wyo.2010).
. The two outliers are Gardeski v. Colonial Sand & Stone, Co., Inc.,
. The majority points to the procedural history of this case as supporting a finding of estoppel. (Majority Op. 1269-70 (citing Slavens,
. The majority concludes that this argument was waived. This is a strained and harsh reading of the record. Sierra Club explicitly pled that it was a national organization with members outside Wyoming. It further argued that the DEQ did not represent its interests. Sierra Club demonstrably preserved the issue of whether it was in privity with the DEQ; our waiver rules do not require a party to raise every possible sub-argument supporting its principal objection in order to preserve that position.
