Lead Opinion
Sierra Club brought a citizen suit seeking civil penalties against Oklahoma Gas and Electric . Company “(OG & E)” for alleged violations of the Clean Air Act. Sierra Club asserts that in March and April 'of 2008, OG & E, the owner and operator of a coal-fired power plant in Muskogee, modified a boiler at the plant without first obtaining an emission-regulating permit as required under the Act. Because Sierra Club filed its action more than five years after construction began on the plant, the district court dismissed its claim under Rule 12(b)(6) as barred by the statute of limitations. The court also dismissed Sierra Club’s claims for declaratory and injunctive relief because these remedies were predicated on the unavailable claim for civil penalties..
We agree with the district court and conclude that Sierra Club’s claim for civil penalties is statutorily time-barred under 28 U.S.C. § 2462 because it was brought more than five years after the date when the cause of action first accrued. In addition, Sierra Club’s claims for declaratory and injunctive relief are precluded because they are based on the same facts as the time-barred claim for civil penalties.
Accordingly, we AFFIRM.
I. Background
The. Clean Air Act (CAA) directs states to achieve and maintain air quality standards set by the EPA. Each state must adopt a state implementation plan (SIP) for meeting these goals, subject to EPA approval. See 42 U.S.C. §§ 7407(a), 7410(a), 7410(k). In “attainment” areas, where air quality 'is already up "to standards, see id. § 7407(d)(1)(A)(ii), SIPs must comply with the federal Prevention of Significant Deterioration (PSD) program, see id. §§ 7470-7492. The purpose of this program is to protect air quality from significant deterioration caused by new emissions. See id. § 7470. To further that aim, the PSD program provides that a “major emitting facility” cannot be constructed or modified without a permit that sets emission limitations. Id. § 7475(a)(1)
■According to the complaint, OG & E began modifying a boiler at its Muskogee power plant sometime in March 2008. The plant is a major emitting facility located in an attainment area and therefore was subject to the PSD permit requirement. OG & E did not obtain a PSD permit before commencing the project. Nor did the company secure one before the modification ended sometime in April 2008. Sierra Club alleges that the modification resulted in an increase in the emission of pollutants.
.Although the modification was completed in April 2008, Sierra Club took no legal action until 2013. At that time, it notified OG & E that it intended to bring suit under the CAA, which grants any person a cause of action against an entity that constructs or modifies a major emitting facility without a PSD permit. See 42 U.S.C. § 7604(a)(3). Sierra Club sought civil penalties under 42 U.S.C. § 7413(e)(2) for each day of unpermitted modification activity, as well as declaratory relief and an injunction requiring OG & E to obtain a PSD permit and upgrade its pollution controls so as to comply with Oklahoma regulations. The parties subsequently entered an agreement that tolled the statute of limitations effective April 1,2013.
Because the CAA does not specify a statute of limitations for bringing a citizen suit for civil penalties, the default five-year statute of limitations for civil penalties, fines, and forfeitures under federal law applies. See 28 U.S.C. § 2462. Thus, the parties agreed that any penalties originating before April 1, 2008—five years pri- or to the tolling agreement—were time-barred. The question was whether Sierra Club, could maintain a claim for penalties originating on April 1,2008 or later.
The district court dismissed Sierra Club’s claim for civil penalties, holding any failure on OG & E’s part to obtain a PSD permit would have- been a violation that accrued at the commencement of modification of the boiler, which was before April 1, 2008. The court also, dismissed Sierra Club’s equitable claims for injunctive and declaratory relief because they were predicated on the time-barred legal claim.
Sierra Club makes two arguments. First, it contends that the statute of limitations does not bar its claim for civil penalties because OG & E continued to violate the CAA until it completed the modification, which was sometime after April 1, 2008. Second, it asserts that its claims for equitable relief are not expired because they are separate from’its claim for civil penalties; Sierra Club seeks equitable relief as an alternative remedy, rather than as a means to enforce its civil penalties claim.
We consider these arguments in turn, first holding the statute of limitations bars Sierra Club’s suit for civil penalties because the claim first accrued when modification commenced. We next hold Sierra Club’s actions for injunctive and declaratory relief are precluded by the concurrent remedy doctrine.
A. Statute of Limitations
We review de novo “a district court’s ruling regarding the applicability of a statute of limitations.” Plaza Speedway, Inc. v. United States,
An action seeking civil penalties for failure to obtain a PSD permit must be brought “within five years from the date when the claim first accrued.” 28 U.S.C. § 2462.- The parties agree that a PSD permit is a pre-construction or pre-modifi-cation requirement, but disagree as to whether the beginning of the -limitations period is delayed as long as the unpermit-ted construction or modification process continues. Sierra Club argues that the statute of limitations resets on each day of unpermitted construction or modification, which in this case included days after April 1,2008.
Sierra Club raises two distinct theories: (1) OG & E committed , a new, discrete violation on each day of unpermitted modification, which we refer to as a theory of “repeated violations”; or (2) OG & E committed a single violation when it began unpermitted construction, but that violation continued until construction was completed. We refer to the latter as a theory of “continuing violation.” In Sierra Club’s view, if either of these theories is correct, then the statute of limitations does not preclude civil penalties for days of modification beginning with April 1, 2008. In contrast, OG & E maintains that the failure to procure a PSD permit generated a single claim for one day’s penalty that accrued only on the first day of modification, which of course occurred before April 1,2008.
We need not consider whether OG & E’s position is correct because we conclude that Sierra Club’s claim for penalties is time-barred for other reasons. The statute of limitations begins to run as soon as a claim “first aecrue[s].” (emphasis added). Id. As explained below, if any form of violation exists beyond the first day of unpermitted modification, it is best characterized as a continuing violation rather than a series of repeated violations.
A single violation continues over ah extended period of time “when the plaintiffs claim seek's, redress for injuries resulting from a series of separate acts that collectively constitute one unlawful act,” as opposed to “conduct that is a discrete unlawful act.” Shomo v. City of New York,
That is the situation when an emissions facility is constructed or modified without a permit, as constructing or modifying a facility is best characterized as a single, ongoing act. To repeat, the CAA prohibits . unpermitted construction or modification of a “major emitting facility.” 42 U.S.C. § 7475(a)(1). It is the act of constructing itself that is unlawful, see Sierra Club, Inc. v. Sandy Creek Energy Assocs.,
Sierra Club argues that where a continuing violation exists, the limitations period under §. 2462 does not begin to run until the final day of the violation—here, the final day of unpermitted modification, which was sometime after April 1, 2008. Although we could consider this argument forfeited because it was not raised below, we reject it anyway.
In this case, it is clear that Sierra Club could have brought suit for the PSD permit violation on the first day of modification. Even one day of unpermitted modification would have presented a “complete and present” violation of the statute. See 40 C.F.R. § 51.166(a)(7)(iii) (“No new major stationary source or major modification to which the requirements [herein] apply shall begin actual construction without a permit that states that the major stationary source or major modification will meet those requirements.” (emphasis added)); United States v. Midwest Generation, LLC,
Sierra Club asserts that because “[a] penalty may be assessed for each day of violation,” 42 U.S.C. § 7413(e)(2), the claim reaccrues oh each day of a continuing violation. But whether the claim reaccrues does not answer or even-address when it first accrues. We see a difference between the availability of a statutory penalty and the initial accrual of the violation giving rise to penalties.
Next, Sierra Club cites four cases for the claim that a continuing violation extends' the deadline to file suit under § 2462. Three of them are easily distinguished. In the first, Havens Realty Corp. v. Coleman, the Supreme Court held “where a- plaintiff, pursuant to- the Fair Housing Act, challenges hot just one incident of conduct violative of the Act, but an unlawful practice that continues into-the limitations period,” the statutory clock begins upon “the last asserted occurrence of that practice.”
Second, Sierra Club’s reliance on United States v. Jaynes,
Lastly, Sierra Club points to a Fifth Circuit administrative appeal for the proposition that the beginning of the limitations period under § 2462 is extended as long as a violation continues. In Newell Recycling Co. v. EPA, the Fifth Circuit upheld an administrative determination that a claim against a recycling facility’s improper disposal of pollutants did not accrue until the facility properly disposed of the contaminated soil.
As a final note, we have observed that “the continuing violation doctrine is premised on the equitable notion that the statute” of limitations should not begin to run until a reasonable person would be aware that his or her rights have been violated.” Davidson v. Am. Online, Inc.,
In sum, § 2462 requires that a suit be filed within five years of when a claim first accrues, which in this case was when OG & E commenced modification of the boiler.
B. Concurrent Remedy Doctrine
Sierra Club also seeks declaratory relief and an injunction requiring OG & E to obtain a PSD permit and upgrade its pollution controls. But it relies on the same theory that underlies its claim for civil penalties: OG & E unlawfully modified a boiler at the Muskogee plant without a permit.
Although § 2462 bars ' Sierra Club’s suit for civil penalties, its language does not, in and of itself, limit actions for equitable relief. See United States v. Telluride Co.,
Relying on Russell,
We disagree. Sierra Club’s narrow reading of Russell contradicts our observation that an equitable claim is unavailable when it can be , brought on the same facts as an expired legal claim. Telluride,
Relying on the .same principles, the Eighth and Eleventh Circuits have
Finally, Sierra Club asserts that the concurrent remedy doctrine is inapplicable because it is acting as a “private attorney general” in place of the government. A suit brought by the government in its sovereign capacity “is not subject to "a time limitation unless Congress explicitly imposes one and any statute of limitations sought to be applied against the United States must receive a strict construction in favor of the Government.” Telluride,
III. Conclusion
For the foregoing reasons, we AFFIRM the district court’s Rule 12(b)(6) dismissal of Sierra Club’s claims.
Notes
. In relevant part, the statute reads:
(a) Major emitting facilities on which construction is commenced
No major emitting facility on which construction is commenced after August 7,*670 1977, may be constructed in’any area to which this part applies unless—
(1) a permit has been issued for such proposed facility in accordance with this part setting forth emission limitations for such facility which conform to the requirements of this part....
42 U.S.C. § 7475.
. In relevant part, the Oklahoma SIP reads:
No person shall cause or allow the construction or modification of any source without first obtaining an authority to construct or modify from the Commissioner as to comply with all applicable air pollution rules and" regulations, and not to exceed ambient air quality standards or applicable federal new source performance standards (NSPS) and national emission standards for hazardous air pollutants (NESHAPS), Sections 111 and 112 of the Federal Clean Air Act,
Oklahoma SIP Regulations § 1.4.2(a)(1),
, in a separate cause of action, Sierra Club also asserted that the plant had exceeded limits on opacity and particulate matter outlined in a 1978 permit that authorized the initial construction of the boiler. Sierra Club voluntarily dismissed this claim.
. As we explain below, the concurrent remedy doctrine bars claims that "could be brought on the same facts.” United States v, Telluride Co.,
. The distinction between a single, continuing violation and repeated, discrete violations is
. Sierra Club claims that it did raise this argument below, but the instances it cites appear to advance a repeated violations theory, rather than a continuing violation theory. “[V]ague, arguable references to a point in the district court proceedings do not preserve the issue on appeal.” Lyons v. Jefferson Bank
. We express no opinion on OG & E’s exposure to civil penalties had a timely suit been commenced. See 42 U.S.C. § 7413 (allowing civil penalties for each day of violation of the CAA). We only hold that Sierra Club knew it had a cause of- action when OG & E commenced construction.
. .Sierra Club concedes, “The only .claim at issue in this appeal is Sierra Club’s claim that by constructing a modification to its Muskogee coal-fired power plant without a permit, the Oklahoma Gas & Electric. Company violated 42 U.S.C. § 7475(a).” Aplt. Br. at 4.
. In its reply brief, Sierra Club asserts for the first time that its claim for injunctive relief is not based on the same facts as its claim for civil penalties because the former requires additional showings. These include irreparable injury, the inadequacy of legal remedies, that "the balance of hardships between the plaintiff and defendant” favors an equitable remedy, and "that the public interest would not be disserved by a permanent injunction.” eBay Inc. v. MercExchange, L.L.C.,
Dissenting Opinion
dissenting.
This case presents an issue of first impression in this and every other circuit: Is the statute of limitations for unpermitted construction or modification in violation of 42 U.S.C. § 7475(a) tolled so long as the construction or modification continues? The majority • concludes, that because this claim “first accrued” on the first day of construction, tolling for a continued violation is prohibited. Because this holding ignores the nature of tolling doctrines, as well as the text and purpose of the Glean Air Act’s Prevention of Significant Deterioration (PSD) program and the Oklahoma State Implementation Plan (SIP), I respectfully dissent.
I
The continuing violation doctrine
The continuing violation doctrine tolls the statute of limitations “for a claim that otherwise would be time-barred where the violation ... continues to occur within the limitations period.” Nat’l Parks & Conservation Ass’n, Inc. v. Tenn. Valley Auth.,
The Clean Air Act and Oklahoma SIP
Looking to the substantive statute for guidance on the nature of the PSD violation, the text of both the Clean Air Act and the EPA-approved Oklahoma SIP strongly support application of the continuing violation doctrine. The Clean Air, Act requires that “[n]o major emitting facility ... may be constructed [or modified] ... unless ... a permit has been issued.” 42 U.S.C. §§ .7475(a)(1), 7479(2)(c). (emphasis added). Additionally, the citizen- suit provision that
The majority is correct when it states: “It is the act of constructing itself that is unlawful,” and “[t]o ‘construct’ is an ongoing project.” Maj. Op. at 672.- While acknowledging that “constructing or modifying a facility is- best characterized as a single, ongoing act,” id., the majority ignores the statutory and regulatory language. Instead, the majority inserts narrowing terms which are not there, characterizing the’ violation as the act of commencing construction, rather than the whole act of construction. But 42 U.S.C. § 7475(a) indicates' that Congress considered and rejected limiting PSD violations .to the commencement of construction. In defining the jurisdiction of the PSD amendments, Congress stated that facilities “on which construction is commenced after” the date of enactment would be subject to the requirements. 42 U.S.C. § 7475(a). In contrast, Congress omitted any mention of “commencing” construction, in the text of the actual prohibition. Id. (“No major emitting facility ... may be constructed....”) (emphasis added). “[Wjhere Congress includes particular language in one section of a statute but omits it in another section of the same Act, it is generally presumed that -Congress acts intentionally and purposely in the disparate inclusion or exclusion.” Russello v. United States,
The majority’s reliance on an EPA Regulation that references the “begin[ning of] actual" construction” does not overcome this statutory language. See Maj. Op. at 673 (quoting 40 C.F.R. § 51.166(a)(7)(iii)). By relying on this regulation over the plain language of the Clean Air Act and the Oklahoma SIP, the majority ventures into administrative law and co-federalism issues far beyond the scope of this case. More importantly, the majority relies on this regulation merely for the accepted premise that the PSD claim “first accrued” when OG & E began its unpermitted modification. The majority again mistakes the date of first accrual with a bar on tolling doctrines, which permit otherwise time-barred claims.
Were" we to toll 28 U.S.C. § 2462 for a continuing violation based on a textual reading of the underlying statute, we would not be the first to do so. See Inter-americas Invs.,
Distinguishing continuing “operating” violations
The district court’s and majority’s reliance on cases from other circuits which purportedly address the issue at hand is misplaced. No other circuit has considered the continuing violation doctrine in the context of PSD violations where construction was ongoing within the limitations period. The majority’s citations to United States v. Midwest Generation, LLC,
The only views expressed by these sister circuits'on the issue presented are found in dicta in two cases, each pointing us‘in a different direction. In Otter Tail Power, the Eighth Circuit noted in its rejection of the continuing operations argument that “[i]t is ... clear that each of [the plaintiffs] PSD claims first accrued upon commencement of the relevant modification.”
I agree with the Third Circuit’s view. The EME Homer court drew a well-principled line, based on the best reading of the Clean Air Act. Where construction or modification is ongoing without, a permit, the violation continues and the statute of limitations is reasonably tolled. When construction is complete, so is-the violation;
Finally, there are persuasive policy Reasons to conclude that the continuing violation doctrine tolls the statute of limitations here. The PSD program is the Clean Air Act’s principal tool to preserve areas that are in compliance with the National Ambient Air Quality Standards (NAAQSs). Failure to toll the statute of limitations to include the length of the construction process undermines the structure of this critical tool by upsetting the balance of the costs of noncompliance. If the law begins to characterize failure to get a PSD permit as a one-day violation, regulated parties will employ that authority to argue that they can only be subjected to one day of penalties (here, a maximum $32,500, or $37,500 for current violations). 42 U.S.C. § 7413; 40 C.F.R. § 19.4. Wasting no time, OG & E made that argument here as support for its statute of limitations theory. See Maj. Op. at 671. Thus, the majority’s ruling today may unknowingly place a low cap on available penalties on projects in violation of the PSD program, even where construction commences within five years of filing suit. Many of the emissions sources regulated by the PSD program generate a great deal of revenue, and enjoy lower costs in the absence of control measures which the permitting process would require.
Such a low cost of noncompliance undermines the balance Congress crafted when it designed the PSD program. This program allows state implementers like Oklahoma to allocate incremental increases in emissions among newly constructed and modified sources,- usually requiring control measures on the facility that the regulated entity would not otherwise install. This structure protects important interests-breathable, healthy air. See 1970 U.S.C.C.A.N. 5356, 5356. Without meaningful enforcement, emitters lose incentive to comply, and the program loses its principal tool to keep emissions at tolerable levels.
Unlike the integrity of the PSD program, policy concerns for the integrity of the statute of limitations are not implicated by this case. The principal purpose of a statute of limitations is to “promote justice by preventing surprises through the revival of claims that have been allowed to slumber until evidence has been lost, memories have faded, and witnesses have disappeared.” Gabelli v. S.E.C., — U.S. —,
II
In sum, I conclude that tolling the statute of limitations'-for a violation of 42 U.S.C. § 7475(a) is appropriate so long as the unpermitted construction or modification is ongoing. I would therefore not reach the issue of whether injunctive relief is barred under the concurrent remedies doctrine. Because the district court dismissed Sierra Club’s PSD claim as time-barred, I would reverse the judgment of the district court and remand for further proceedings.
. Contrary to the majority's conclusion, Sierra Club preserved its continuing violation argument. In its Response to OG & E’s Motion to Dismiss, Sierra Club made arguments identical to those niade on appeal regarding the text of the Clean Air Act, Oklahoma SIP, and case law. Sierra Club argued that the act of construction is an ongoing one, actionable as long as construction continues. App. at 74, 75, 77 n. 2, 78, Moreover, the cáses discussed in depth by both parties and the district court are the few authorities to speak to application of the continuing violation theory to PSD violations, so the issue was fairly raised. While Sierra Club failed to label their theory as a "continuing violation” theory before the district court, to call this argument forfeited ignores the substantive arguments for lack of a technical label.
. Sierra Club cites Havens merely as an example of the continuing violation theory generally. The majority’s attack on. Havens’s facts is therefore of little consequence to Sierra Club’s arguments specific to PSD violations.
. The title of 42’U.S.C. § 7475(a) is “Major emitting facilities on- which construction is commenced.” OG & E argued this title indicates that the violation is the commencement, rather than the whole act, of construction. Properly read, however, this title refers to the applicability of § 7475 to those facilities on which construction was commenced after the date of enactment, and further supports an inference that Congress intentionally declined to define PSD violations as the mere commencement of construction.
