This matter comes to us as a successive appeal. The original defendants wanted to build a power plant in southern Illinois. In the first appeal, we concluded that the defendants’ Prevention of Significant Deterioration (“PSD”) permit, which they needed in order to build the power plant, see 42 U.S.C. § 7475(a), had expired. We therefore held that it was proper for the district court to grant summary judgment in favor of plaintiff Sierra Club and to enjoin the defendants from engaging in further construction activities until they obtained a new permit.
After our ruling, the district court assessed a penalty of $100,000 on all of the defendants, jointly and severally, and awarded attorneys’ fees to Sierra Club. Defendant Khanjee Holding appeals that decision.
In this appeal, Khanjee contends that the district court lacked subject matter jurisdiction. But we already determined in the previous appeal that the district court had subject matter jurisdiction, and there is no reason to revisit that ruling.
Khanjee also argues that the district court assessed penalties and fees in violation of Khanjee’s constitutional rights. We find, however, that Khanjee waived its constitutional arguments by not raising them before the district court.
Lastly, Khanjee contends that the district court committed error when it weighed the requisite statutory factors. But we conclude that the district court did not abuse its discretion. The court considered all of the relevant statutory factors and did not make any clearly erroneous findings of fact in assessing a penalty and awarding fees. We affirm.
I. BACKGROUND
Franklin County Power (“FCP”), EnviroPower 1 , and Khanjee are experienced developers of electric power plants in the United States and in other countries, having successfully built about a dozen plants currently in operation. All three participated in the first appeal, but only Khanjee is a party to this appeal.
In 2000, FCP applied to the Illinois Environmental Protection Agency (“Illinois EPA”) for a PSD permit in order to build a coal power plant in southern Illinois. In 2001, the Illinois EPA issued the permit, which would become invalid if construction was not commenced within 18 months after receipt of approval, was discontinued for a period of 18 months or more, or was not commenced within a reasonable time.
In mid-2002, Khanjee began to serve as the lead developer for the project. Excavation on the site began in early 2003, but was abandoned shortly after due to an unrelated dispute. In March 2003, Khanjee and EnviroPower entered into a Development and Purchase Agreement, and in August of that year, Khanjee issued an offering memorandum seeking financial support for the project.
On May 20, 2005, Sierra Club filed suit, alleging that the defendants’ PSD permit had expired. Khanjee filed a motion to dismiss arguing that it was not a real party in interest in the lawsuit because it was not a party to the permit at issue and was a separate corporate entity from FCP and EnviroPower. The district court found that Sierra Club had alleged enough to state a claim against Khanjee, and added, “Whether the allegations of the underlying Clean Air Act violation prove true and whether the corporate relationship between Khanjee and the other defendants is sufficient to warrant imposing liability on Khanjee are matters to be determined later in the case.”
Sierra Club filed a motion for summary judgment against all defendants and requested an injunction to prevent construction of the plant until the defendants obtained a new PSD permit. The defendants, including Khanjee, filed a joint response and countered with their own motion for summary judgment. The defendants also filed a second motion to dismiss arguing that Sierra Club lacked standing to sue. Khanjee did not renew the arguments it made in its first motion to dismiss in any of these filings.
The district court granted Sierra Club’s motion for summary judgment and enjoined further construction of the power plant. The court also denied the defendants’ motions. The defendants appealed, and the court stayed the case pending resolution of the appeal.
In
Sierra Club v. Franklin County Power of Illinois, LLC,
Back before the district court, Sierra Club moved for penalties and attorneys’ fees. The court imposed a civil penalty of $100,000 on all defendants, jointly and severally, under 42 U.S.C. § 7604(a). The penalty was to be paid to various local chapters of the non-profit organization Habitat for Humanity. The court also awarded Sierra Club $375,985.70 in attorneys’ fees and costs. Khanjee appeals the imposition of penalties and fees.
II. ANALYSIS
A. Subject Matter Jurisdiction
Khanjee argues that the district court lacked subject matter jurisdiction to impose civil penalties under § 7604(a), relying on
CleanCOALition v. TXU Power,
We already decided the jurisdictional question in
Sierra Club I.
We held that the district court had jurisdiction because Sierra Club had alleged that the defendants (including Khanjee) were “in violation of [a] condition of a [PSD] permit” and § 7604(a)(3) expressly permits lawsuits against “any person ... who is alleged ...
Matters decided on appeal become the law of a case to be followed on a second appeal, unless there is plain error of law in the original decision.
Creek v. Vill. of Westhaven,
In
Christianson,
we explained that “there [was] authority for the proposition that the issue of subject matter jurisdiction is not constrained by law of the case principles,” citing the District of Columbia Circuit and the Fifth Circuit.
Moreover, in
Christianson,
we simply relied upon the established rule that the law of the case does not bar reconsideration and reversal of “even nonjurisdictional rulings that are manifestly incorrect.”
B. Constitutional Violation Claims
Khanjee contends that the district court’s imposition of civil penalties violates the separation of powers doctrine, the Appointments Clause, and the Excessive Fines Clause of the Eighth Amendment. But Khanjee did not develop its separation of powers or Appointments Clause arguments before the district court,
3
and it has therefore waived them.
Taubenfeld v. Aon Corp.,
Only Khanjee’s Excessive Fines argument warrants additional discussion. Khanjee admits in its reply that “this is the first time Khanjee has cited the Excessive Fines Clause,” but states that there “was no clear indication that the Clause would be relevant until the district court issued its decision.” There is authority for the proposition that an Excessive Fines challenge is not ripe “until the imposition, or immediately impending imposition, of a challenged punishment or fine.”
See Cheffer v. Reno,
Khanjee contends that its relationship to the other defendants 'in the first appeal, FCP and EnviroPower, is too tenuous to warrant imposing penalties and fees on Khanjee. But Khanjee did not renew this argument on summary judgment after the district court rejected it in denying Khanjee’s motion to dismiss. And we already affirmed the district court’s grant of summary judgment against all of the defendants in
Sierra Club I. See Creek,
In any event, even if we were to consider Khanjee’s contention, it would fail. The citizen suit provision of the Clean Air Act allows any person to bring an action “against any person who proposes to construct or constructs any new or modified major emitting facility without a permit.” § 7604(a)(3). Khanjee argues that liability can only be imposed on owners or operators.
See United Steelworkers of Am. v. Or. Steel Mills, Inc.,
We need not resolve the dispute. As the district court found, the evidence reflects that Khanjee effectively controlled and led the efforts to build the power plant after the PSD permit expired in early 2003. Khanjee began to serve as the lead developer for the plant’s construction in mid 2002. And in March 2003, Khanjee entered into a Development and Purchase Agreement- with EnviroPower, which provided that, “In consideration of receiving the Development Funding ... [EnviroPower] agrees to
cede control over Development of the Projects
... to [Khanjee].” (emphasis added). The agreement further provided for the creation of a Management Committee of three members nominated by Khanjee, which was “responsible for ... assignment and management of manpower resources, contract negotiations and execution, funding procedures, budget compliance, status reports, schedule compliance and development, [and] implementation and adherence to the Financing Plan.” This agreement, which gave Khanjee control over the development of the plant, belies Khanjee’s claim that it was a mere financier. The district court also concluded, and we agree, that Khanjee and the other defendants, who are all sophisticated parties, had an intimate working relationship. Khanjee therefore exercised enough control over the project such that it can be held liable as an “owner or operator,” even if that were the test, along with the other defendants.
See B & W Inv. Props.,
1. Penalties
The Clean Air Act authorizes suits against entities who construct or propose to construct facilities without a permit.
See
§ 7604(a)(3). When a party prevails under § 7604(a)(3), as Sierra Club did here, the district court is authorized in its discretion to “apply any appropriate civil
In determining the amount of a civil penalty, the district court should consider, in addition to such other factors as justice may require, the size of the violator’s business, the economic impact of the penalty on the business, the violator’s full compliance history and good faith efforts to comply, the duration of the violation as established by any credible evidence, payment by the violator of penalties previously assessed for the same violation, the economic benefit of noncompliance, and the seriousness of the violation. § 7413(e)(1). The district court’s weighing of the statutory factors is reviewed for abuse of discretion.
B & W Inv. Props.,
Courts generally presume that the maximum penalty under the Clean Air Act should be imposed, and then consider the factors described in § 7413(e) to determine what degree of mitigation, if any, is proper.
B & W Inv. Props.,
Khanjee finds fault with the district court’s analysis because, Khanjee argues, the court erroneously concluded that Khanjee acted with bad faith and relied on that conclusion in imposing a penalty. We agree with Khanjee that in
Sierra Club I
we rejected Sierra Club’s contention that the defendants engaged in “willful misconduct” by persisting in their proposal to build the plant because the defendants were “simply defending the validity of [their] permit in court.”
Regardless, the Clean Air Act imposes strict liability from the first day of the offense.
See B & W Inv. Props.,
In this case, we are not confronted with a defendant who lacked knowledge of the circumstances surrounding the violation. The district court found that the evidence reflected an “intimate working relationship between the defendants ... regarding the construction of the Plant,” and that, “[i]t is inconceivable in light of this evidence that Khanjee was not aware of the PSD Permit’s expiration in early 2003.” As previously noted, the evidence reflects that Khanjee exercised significant control over the project. The court’s finding that Khanjee was aware of what was happening with the PSD permit is not clearly erroneous.
The district court considered all of the requisite factors under § 7413(e)(1). In light of the size of the project ($600 miltion) and of the potential maximum penalty of $41.7 million, we agree with the district court that a relatively small penalty of $100,000, imposed jointly and severally on all three defendants, was reasonable. 6
2. Fees
The district court has discretion to award costs of litigation, including reasonable attorneys’ fees, whenever appropriate in a Clean Air Act ease. § 7604(d). An award is appropriate if the party seeking fees obtained some success on the merits.
See Ruckelshaus v. Sierra Club,
Khanjee contends that Sierra Club should not get its fees because, it argues, fees should not be awarded to well-funded parties that would bring cases regardless of an award. But there is no support for this proposition in the case law. “[Congress], when it called for citizen-suits [to aid enforcement of the Clean Air Act], considered a fee recovery to be consonant with the public interest.”
Metro. Washington Coal, for Clean Air v. District of Columbia,
Western States Petroleum Ass’n v. E.P.A.,
III. CONCLUSION
The judgment of the district court is Affirmed.
Notes
. FCP is a wholly owned subsidiary of EnviroPower. The two entities share the same chief executive officer, Mr. Frank Rotondi.
. We also found that Sierra Club could seek an injunction: "[W]e agree that ‘a plain reading of the statute’ implies 'that the [injunctive remedies provision] applies to actions under [section 7604](a)(3).’ ” Id. at 935.
. The defendants briefly noted in their response to Sierra Club's motion for fees that the imposition of fines allegedly requires constitutional scrutiny, citing to Justice Kennedy’s concurrence in
Friends of the Earth, Inc. v. Laidlaw Envtl. Servs. (TOC), Inc.,
. We note that Khanjee and the other defendants argued in their previous appeal that a civil penalty was the only proper remedy in this case.
See Sierra Club I,
. Khanjee did not challenge this calculation before the district court in response to Sierra Club's motion seeking penalties.
See Kunz,
.
United States v. Cinergy Corp.,
