Sierra Club, Plaintiff - Appellant, v. United States Army Corps of Engineers; Federal Emergency Management Agency; et al., Defendants - Appellees.
No. 04-3910
United States Court of Appeals, Eighth Circuit
April 4, 2006
Appeal from the United States District Court for the Western District of Missouri. Submitted: October 14, 2005. Filed: April 4, 2006. Before LOKEN, Chief Judge, LAY and BENTON, Circuit Judges.
Responding to a request by Jefferson City, Missouri, the U.S. Army Corps of Engineers (“the Corps”) proposes to construct a levee, known as L-142, to reduce the risk of future flooding along the banks of the Missouri River as it flows through Jefferson City. The project will include land previously acquired by Jefferson City under the Stafford Act,
On the government’s motion, the district court dismissed these claims for lack of jurisdiction, concluding that judicial review under the Administrative Procedure Act is barred by the lack of “final agency action,” see
I.
Following extensive flooding in the Midwest in 1993, Congress amended the Stafford Act to minimize the cost of future floods by authorizing FEMA to assist local governments in acquiring property in flood-prone areas. To obtain assistance under this hazard mitigation grant program (“HMGP”), an applicant must agree that:
(ii) no new structure will be erected on property acquired, accepted or from which a structure was removed under the acquisition or relocation program other than -
(I) a public facility that is open on all sides and functionally related to a designated open space;
(II) a rest room; or
(III) a structure that the [FEMA] Director approves in writing before
the commencement of the construction of the structure.
By early 1998, FEMA had adopted a policy that large flood control structures such as levees are not compatible with the non-structural emphasis of the HMGP program and therefore FEMA “will not grant an exception [under
On April 26, 2001, the Corps issued an environmental assessment (“EA”) for a proposed L-142 levee that would include 30.22 acres of deed-restricted land acquired with HMGP funds, 1.47 acres under the levee footprint, and 28.75 acres inside the levee. The Corps also issued a finding of no significant impact (“FONSI”) in lieu of an environmental impact statement. See
Sierra Club filed this suit in December 2003 alleging that the Corps violated NEPA and the APA by failing to adequately evaluate the environmental impacts of the project and by issuing a FONSI rather than an environmental impact statement. Sierra Club filed an amended complaint in February 2004 adding FEMA as a defendant and alleging that its Memorandum of Agreement with the Corps and approval of a levee including 30.22 acres of deed-restricted land were arbitrary and capricious agency actions within the meaning of the APA. See
The government moved to dismiss all claims for lack of jurisdiction, raising three inter-related issues. First, the government argued there is no final agency action by the Corps because it has not entered into a Project Cooperation Agreement with Jefferson City nor received necessary funding from Congress, and no final agency action by FEMA because it has not entered into an Agreement of Clarification with Jefferson City needed to modify the deed restrictions on HMGP-acquired properties. Second, the government argued that the claims are not ripe because the project’s future is uncertain and no construction work may begin until the Corps and FEMA take these additional actions. Third, the government argued that Sierra Club lacks standing because its alleged injury in fact is neither actual nor imminent.
The district court dismissed the amended complaint for lack of jurisdiction, concluding there has been no “final agency action” within the meaning of
II. Final Agency Action
Neither the Stafford Act, NEPA, nor the statutes governing the Corps expressly provide for judicial review of the agency actions at issue. Therefore, jurisdiction is limited to judicial review under the APA, which provides for review of “final agency action for which there is no other adequate remedy in a court.”
A. The Stafford Act Claim. For its claim against FEMA, Sierra Club first alleged that the agency’s March 2000 Memorandum of Agreement with the Corps permitting flood levees to be built on certain HMGP-acquired lands was an arbitrary and capricious application of
v. Spear. Therefore, it is not subject to immediate judicial review under the “final agency action” provision of
Sierra Club also alleged that FEMA’s “determination to allow construction of the [L-142] levee on 30.22 acres of deed-restricted land” was an arbitrary and capricious agency action. Surprisingly, although the Memorandum of Agreement provided for an “expeditious joint review” to make such determinations “on a case-by-case
In support of its motion to dismiss, the government submitted an affidavit by the Acting Director of FEMA’s Mitigation Division. The Acting Director first averred that a recipient of HMGP funds such as Jefferson City must apply for approval allowing a structure such as a levee to be built on HMGP-acquired lands, and FEMA’s approval must be reflected in an “Agreement of Clarification.” A Model Agreement of Clarification was attached to the affidavit. The Acting Director then averred that, although Jefferson City applied for approval in March 2000 and the April 2000 letter stated that FEMA “will provide an appropriate legal instrument,” no Agreement of Clarification has been signed and no deeds have been amended. “Furthermore,” the affidavit concluded, “given the amount of time that has lapsed . . . FEMA would require the City to resubmit their request to allow the construction of the levee on
HMGP lands.” Acknowledging that finality is a pragmatic and flexible concept, the government argues there is no final agency action under the Stafford Act until FEMA takes these additional steps.
Jurisdictional issues such as standing and ripeness are determined at the time the lawsuit was filed in December 2003. See McClain v. Am. Econ. Ins. Co., 424 F.3d 728, 733 (8th Cir. 2005). Therefore, we put aside as irrelevant the averment that FEMA would start the approval process over because time has now passed without construction of the L-142 levee. We are also inclined to disregard what may be the final step in the Stafford Act process, the modification of individual deeds to HMGP-acquired lands. The government has not established that deed modifications will be required, though real property filings will doubtless be prudent, if not required. But once FEMA has given the overall approval required by
The difficult question in this case is whether the specific FEMA determination described in the April 2000 letter was a final agency action before Jefferson City and FEMA entered into an Agreement of Clarification. The April 2000 letter appears to satisfy the first requirement of Bennett v. Spear; it reflects a final FEMA determination to approve a specific levee proposal. But to be a final agency action, this determination must be one that determines rights or obligations or from which legal consequences will flow. Neither party analyzed this issue in detail, as the Supreme Court’s precedents require, and the sparse record on appeal sheds inadequate light on an agency process that is not carefully prescribed by statute or regulation.
as the party invoking federal jurisdiction has the burden of proof. See Lujan v. Defenders of Wildlife, 504 U.S. 555, 561 (1992). Accordingly, we affirm the district court’s resolution of this issue.
B. The NEPA Claims. Sierra Club argues that the Corps’ issuance of an EA and a FONSI was a “final agency action.” The government responds that an EA and a FONSI are not a final agency action when, as here, “the federal agencies must take several more actions before their decision is final and [the major federal action] contemplated in the NEPA compliance documents could begin.” The district court did not specifically address this issue.2
NEPA prescribes a set of “action-forcing” measures that require federal agencies to take a “hard look” at the environmental consequences of major federal actions before they are taken. See
The Supreme Court has strongly signaled that an agency’s decision to issue either a FONSI or an environmental impact statement is a “final agency action” permitting immediate judicial review under NEPA:
NEPA . . . simply guarantees a particular procedure, not a particular result. . . . Hence a person with standing who is injured by a failure to comply with the NEPA procedure may complain of that failure at the time the failure takes place, for the claim can never get riper.
Ohio Forestry, 523 U.S. at 737 (citations omitted); cf. Marsh v. Oregon Natural Res. Council, 490 U.S. 360, 370-74 (1989). More than one of our sister circuits have held that the six-year statute of limitations for commencing a NEPA action under the APA begins to run when the agency issues a FONSI. See Jersey Heights Neighborhood Ass’n v. Glendening, 174 F.3d 180, 188 (4th Cir. 1999); Southwest Williamson County Cmty Ass’n v. Slater, 173 F.3d 1033, 1036 (6th Cir. 1999).
these reasons, we conclude that the Corps’ decision to issue a FONSI constituted a “final agency action” under NEPA that is subject to immediate judicial review under
III. Standing and Ripeness under NEPA
We likewise reject the district court’s conclusion that Sierra Club lacks standing because no injury is certain to occur until the Corps and FEMA take additional steps to finalize the levee project. Injury under NEPA occurs when an agency fails to comply with that statute, for example, by failing to issue a required environmental impact statement. The injury-in-fact is increased risk of environmental harm stemming from the agency’s allegedly uninformed decision-making. See Comm. to Save the Rio Hondo v. Lucero, 102 F.3d 445, 448-49 (10th Cir. 1996). The government does not challenge Sierra Club’s standing to assert that injury on behalf of its members. See Defenders of Wildlife, 504 U.S. at 572 n.7 (1992).
Finally, we have little difficulty concluding that this NEPA dispute was ripe for judicial review when the lawsuit was filed in December 2003. See Ohio Forestry, 523 U.S. at 737. However, that does not mean the district court must ignore the current posture of the dispute. An agency must continue to take a “hard look” at the environmental effects of a planned action after preliminary approval and may need to prepare a supplemental assessment or impact statement if environmentally significant new circumstances or information develop, and if as in this case major federal action is yet to occur. See Norton v. Southern Utah Wilderness Alliance, 542 U.S. 55, 72 (2004); Marsh, 490 U.S. at 372-74.
Substantial time has elapsed since FEMA approved the L-142 levee in April 2000 and the Corps issued a FONSI in April 2001. Both agencies have identified additional steps that must be taken before the levee may be built, steps that may require a new approval process before FEMA and may trigger supplemental
environmental analysis by the Corps, or by Jefferson City, see
The judgment of the district court is reversed and the case is remanded for further proceedings not inconsistent with this opinion.
