SIERRA CLUB, INC., Plaintiff-Appellee, v. UNITED STATES FISH AND WILDLIFE SERVICE; NATIONAL MARINE FISHERIES SERVICE, Defendants-Appellants.
No. 17-16560
UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT
December 21, 2018
Opinion by Judge Berg; Partial Concurrence and Partial Dissent by Judge Wallace
D.C. No. 3:15-cv-05872-EDL; Appeal from the United States District Court for the Northern District of California; Elizabeth D. Laporte, Magistrate Judge, Presiding; Argued and Submitted March 15, 2018 San Francisco, California
FOR PUBLICATION
Before: J. Clifford Wallace and Marsha S. Berzon, Circuit Judges, and Terrence Berg,* District Judge.
SUMMARY**
Freedom of Information Act
The panel affirmed in part and reversed in part the district court‘s decision that ordered the U.S. Department of Fish and Wildlife Services and the National Marine Fisheries Service to turn over 12 of 16 requested records in a Freedom of Information Act (“FOIA“) action brought by the Sierra Club challenging the Services’ denial of their request for records generated during the Environmental Protection Agency‘s rule-making process concerning cooling water intake structures.
Exemption 5 of FOIA shields documents subject to the “deliberative process privilege” from disclosure.
The panel held the December 2013 draft jeopardy biological opinions, the accompanying statistical table, the accompanying instructional documents, and the March 2014 reasonable and prudent alternative (RPA) were not both pre-decisional and deliberative. The panel therefore affirmed in part the district court‘s summary judgment order requiring the production of these records.
The panel held that there was sufficient support to conclude that the December 2013 RPAs and the April 2014 draft jeopardy opinion were pre-decisional and deliberative. Because these records satisfied the standard for non-disclosure under FOIA Exemption 5, the panel reversed the district court‘s order for their production.
The panel instructed the district court on remand to perform a segregability analysis.
Judge Wallace concurred in the result reached by the majority as to the April 2014 draft opinion and the December 2013 RPAs, and dissented from the result reached by the majority as to the rest of the documents because he disagreed with the majority that the deliberative process privilege did not protect the December draft opinions and other documents.
COUNSEL
Thomas Pulham (argued), Appellate Staff, Civil Division, United States Department of Justice, Washington, D.C., for Washington, D.C., for Defendants-Appellants.
Reed W. Super (argued) and Michael DiGuglio, Super Law Group LLC, New York, New York, for Plaintiff-Appellee.
Shaun A. Goho, Emmett Environmental Law & Policy Clinic, Harvard Law School, Cambridge, Massachusetts, for Amicus Curiae Union of Concerned Scientists.
OPINION
BERG, District Judge:
Across the United States, thousands of large industrial facilities, power plants, and other manufacturing and processing complexes draw billions of gallons of water each day from lakes, rivers, estuaries and oceans in order to cool their facilities through cooling water intake structures.1 These structures can harm fish, shellfish, and their eggs by pulling them into the factory‘s cooling system; they can injure or kill other aquatic life by generating heat or releasing chemicals during cleaning processes; and they can injure larger fish, reptiles and mammals by trapping them against the intake screens.2 Section 316(b) of the Clean Water Act,
In April 2011, the EPA proposed new regulations under Section 316(b) for cooling water intake structures. 76 Fed. Reg. 22,174 (April 20, 2011). The final rule was published in the Federal Register in August 2014. Final Regulations to Establish Requirements for Cooling Water Intake Structures, 79 Fed. Reg. 48,300 (Aug. 15, 2014) (to be codified at
Appellee, the Sierra Club, made a Freedom of Information Act (“FOIA“) request to the Services for records generated during the EPA‘s rule-making process concerning cooling water intake structures, including documents generated by the Services as part of an ESA Section 7 consultation about the rule. The Services withheld a number of the sought-after records under “Exemption 5” of FOIA, which shields documents subject to the “deliberative process privilege” from disclosure. See
I. BACKGROUND
a. Factual History
In 2012, the EPA began an informal consultation process with the Services about a proposed rule for regulating the requirements governing the operation of cooling water intake structures. The EPA requested a formal consultation on the proposed rule in 2013. On November 4, 2013, the Services received a revised version of the proposed rule from the Office of Management and Budget (OMB). On November 15, 2013, the Services sent a “Description of the Action” (i.e. a summary of what the Services thought the proposed rule set out to do) to the EPA. Finally, on November 26, 2013, the EPA responded with corrections to the Services’ description of the rule and the Services incorporated the EPA‘s corrections. The EPA and the Services tentatively agreed that the FWS and NMFS would each provide a draft biological opinion to the EPA by December 6, 2013, and a final opinion by December 20, 2013.
After reviewing the November 2013 proposed rule, both Services prepared draft opinions finding that the rule in its then-current form was likely to cause jeopardy for ESA-protected species and negatively impact their designated critical habitats. The Services also proposed RPAs to accompany those jeopardy opinions. At the same time, NMFS discussed whether the jeopardy opinions should be sent to “the
NMFS completed its draft jeopardy opinion on December 6, 2013 and FWS completed its draft jeopardy opinion on December 9, 2013, both for transmission to the EPA. The ESA regulations require that the Services make draft opinions available to the Federal agency that initiated the formal consultation upon request.
On December 12, 2013, the FWS Deputy Solicitor called and emailed the EPA General Counsel to “touch base . . . about transmitting a document to EPA.” He also emailed “the current draft RPAs” to the EPA that same day. On December 17, 2013, the NMFS sent a “Revised Combined NMFS and USFWS RPA” to the EPA. The Services have further indicated in their briefing that they also provided other unspecified portions of the draft jeopardy opinions to the EPA.
After the transmission of these partial December 2013 jeopardy biological opinions and accompanying documents, the EPA issued a new version of the rule, the “final Rule and Preamble,” which it sent to the Services on March 14, 2014. On April 7, 2014, NMFS employees completed and internally circulated a draft of another jeopardy biological opinion. During this same time frame, the Services and the EPA discussed whether the EPA agreed with the Services’ interpretation and understanding of the March 2014 final rule: On March 31, 2014 the Services sent the EPA a document “seeking clarification on the Services’ understandings of key elements in EPA‘s proposed action.” On April 8, 2014, EPA “provided confirmation on the Services’ description and understanding of the key elements of EPA proposed action.” Finally, on May 19, 2014, the Services issued a joint final “no jeopardy” biological opinion regarding the March 2014 final rule. The EPA issued the regulation that same day, and it was published in the Federal Register on August 15, 2014. Final Regulations to Establish Requirements for Cooling Water Intake Structures, 79 Fed. Reg. 48,300.
On August 11, 2014, the Sierra Club submitted FOIA requests to the Services for records related to this ESA Section 7 consultation. In response, the Services produced a large quantity of documents (some of which were partially redacted). The Services withheld other documents under FOIA Exemption 5, which protects “inter-agency or intra-agency memorandums or letters that would not be available by law to a party other than an agency in litigation with the agency.”
In summary, the key chronological dates in this FOIA dispute are:
- June 18, 2013: EPA initiates formal consultation under ESA Section 7 with the Services regarding the proposed rule.
- November 4, 2013: The Services receive the most recent version of the EPA‘s proposed rule from OMB.
- November 15, 2013: The Services send the Description of the Action (i.e. a summary of their understanding of the proposed rule) to the EPA for review.
- November 26, 2013: EPA sends the Services its corrections and comments on the Description of the Action, which the EPA incorporated into the final description of the November 2013 proposed rule.
- December 3, 2013: The Services inform the EPA that their draft opinions
are “jeopardy opinions” and will be completed on or around December 6, 2013. - December 6, 2013: NMFS completes its draft jeopardy opinion.
- December 9, 2013: FWS completes its draft jeopardy opinion.
- December 12, 2013: FWS Deputy Solicitor calls the EPA General Counsel to “touch base . . . about transmitting a document to EPA.”
- December 12 & 17, 2013: The Services email two RPAs—written to accompany the draft jeopardy opinions—to the EPA.
- March 14, 2014: EPA sends the Services a new, final rule for review and Biological Opinion analysis.
- March 31, 2014: The Services send the EPA a document requesting clarification regarding their understanding of elements of the final rule.
- April 7, 2014: NMFS employees internally circulate a draft jeopardy biological opinion relating to the March 14, 2014 proposed rule; this draft is not sent to EPA.
- April 8, 2014: EPA confirms the Services’ interpretations and understanding of the final rule contained in the Services’ clarification document.
- May 19, 2014: The Services issue a joint final no jeopardy biological opinion regarding the March 14, 2014 proposed rule.
b. Procedural History
On December 21, 2015, the Sierra Club filed suit against the Services, arguing that they had improperly withheld documents under FOIA Exemption 5. The parties filed cross-motions for summary judgment regarding their release. During and after that hearing the district court and the parties narrowed the list of contested documents to 16. The district court found that 4 of the disputed documents were fully protected under Exemption 5 but ordered that the Services produce one document in part and the other eleven in full.4 The Services timely appealed the district court‘s order to produce the documents, and the parties stipulated to stay of production pending appeal.5
The documents at issue on appeal—those that the district court found were not exempt from disclosure—were submitted to the panel under seal for in camera review. They are:
- Biological Opinions
- “NMFS 44516.1“: A 289-page NMFS draft jeopardy biological opinion dated December 6, 2013;
- “FWS 252“: A 72-page FWS draft jeopardy biological opinion dated December 9, 2013;
-
“NMFS 5427.1“: A 334-page NMFS draft jeopardy biological opinion dated April 7, 2014;6
- Reasonable and Prudent Alternatives (RPAs)
- “FWS 279“: A 4-page FWS RPA, dated December 17, 2013;
- “FWS 308“: A 3-page FWS RPA, dated December 18, 2013;
- “FWS 555“: A 2-page FWS RPA, dated March 6, 2014.
- Other Documents
- “NMFS 61721“: A 1-page statistical table showing estimated aggregate effects of cooling water intake structure facilities on protected species;
- “NMFS 5597.1“: A 2-page document that describes steps that facility owners/operators must take if abalone, an endangered species, is affected by their cooling water intake structures;
- “NMFS 7544.2“: A 15-page document on Anadromous Salmonid Requirements that provides criteria and guidelines to be utilized by owner/operators in the development of downstream migrant fish screen facilities for hydroelectric, irrigation, and other water withdrawal projects;
- “NMFS 37695“: A 2-page document that lists the steps that owner/operators must follow if a seal, sea lion, or fur seal, or their designated critical habitat, may be affected by a cooling water intake structure;
- “NMFS 37667“: A 3-page document that lists the steps that owner/operators must follow if sea turtles are affected by their cooling water intake structures;
- “NMFS 14973“: A 5-page document that lists the terms and conditions with which the EPA and an owner/operator must comply in order to be exempt from Section 9 of the ESA. These terms and conditions involve the protocols for dealing with sea turtles near cooling water intake structures. The district court held NMFS could redact one sentence but had to disclose the rest of the document.
II. STANDARD OF REVIEW
In FOIA cases, this court reviews summary judgment determinations de novo. Animal Legal Def. Fund v. U.S. Food & Drug Admin., 836 F.3d 987, 990 (9th Cir. 2016) (en banc).
III. DISCUSSION
Section 522 of Title 5, FOIA, “mandates a policy of broad disclosure of government documents.” Maricopa Audubon Soc. v. U.S. Forest Serv., 108 F.3d 1082, 1085 (9th Cir. 1997) (Maricopa I) (quoting Church of Scientology v. Dep‘t of the Army, 611 F.2d 738, 741 (9th Cir. 1979) (internal quotations omitted)). Agencies may withhold documents only pursuant to the exemptions listed in
Here, the Services argue that the 12 documents the district court ordered them to produce to the Sierra Club are protected under
This exemption has been interpreted as coextensive with all civil discovery privileges. NLRB v. Sears, Roebuck & Co., 421 U.S. 132, 149 (1975). The particular privilege the Services have claimed here is the “deliberative process privilege,” which permits agencies to withhold documents “to prevent injury to the quality of agency decisions by ensuring that the frank discussion of legal or policy matters in writing, within the agency, is not inhibited by public disclosure.” Maricopa Audubon Soc. v. U.S. Forest Serv., 108 F.3d 1089, 1092 (9th Cir. 1997) (Maricopa II) (quoting NLRB v. Sears, Roebuck & Co., 421 U.S. 132, 150–51 (1975) (internal quotations omitted)).
Because FOIA is meant to promote disclosure, its exemptions are interpreted narrowly. Assembly of Cal. v. U.S. Dep‘t of Commerce, 968 F.2d 920 (9th Cir. 1992) (citing Dep‘t of Justice v. Julian, 486 U.S. 1, 8 (1988)). The dissent argues that because the FOIA Exemption 5 privileges “inter-agency or intra-agency memorandums or letters” and because the documents at issue here were transmitted between agencies, they should be exempt from disclosure. We agree that the documents must be considered in the context in which they were produced, Sears, Roebuck & Co., 421 U.S. at 138. But a document‘s origins as part of the inter-agency consultation process between the EPA and the Services, see
This circuit has defined the ambit of the deliberative process privilege under Exemption 5 narrowly. It “applies only if disclosure of the materials would expose an agency‘s decision-making process in such a way as to discourage candid discussion within the agency and thereby undermine the agency‘s ability to perform its functions.” Kowack, 766 F.3d at 1135 (quoting Maricopa II, 108 F.3d at 1093) (internal quotations omitted) (finding the Forest Service had not sufficiently demonstrated that disclosure of redacted portions of an intra-agency investigative report regarding alleged employee misconduct contained more than factual, i.e., deliberative, content).
The Services therefore bear the burden of proving that the documents they maintain should be exempt from disclosure are both “pre-decisional and deliberative.” Carter v. Dep‘t of Commerce, 307 F.3d 1084, 1089 (9th Cir. 2002) (internal quotations omitted).7
a. Pre-decisional
A document is pre-decisional if it is “prepared in order to assist an agency decision-maker in arriving at his decision, and may include recommendations, draft documents, proposals, suggestions, and other subjective documents which reflect the personal opinions of the writer rather than the policy of the agency.” Assembly of Cal., 968 F.2d at 920 (citation and internal quotations omitted). The agency requesting the exemption “must identify a specific decision to which the document is pre-decisional.” Maricopa II, 108 F.3d at 1094.
Here, the Services argue that the December 2013 and April 2014 jeopardy opinions, the three RPAs, and all of the other statistical and instructional documents pre-date the May 2014 “no jeopardy” opinion and are thus pre-decisional as to that final opinion.
1. April 2014 NMFS Draft Biological Opinion
We agree that the April 2014 draft jeopardy opinion (NMFS 542.71) was prepared as an internal agency document. It was only circulated between groups of NMFS employees, and there is nothing in the record that indicates that the jeopardy finding was communicated even informally to the EPA. Where one document reflects an earlier position of the agency—as the April 2014 draft jeopardy opinion does here when compared with the May 2014 final no jeopardy opinion—it is pre-decisional as to the issues addressed in both. See Nat. Wildlife Fed., 861 F.2d at 1120 (documents that were “working drafts” subject to revision are pre-decisional). In other words, it does not appear to represent the conclusion of the agency on the
2. RPAs
We also agree that the December 2013 RPAs (FWS 279, 308) are pre-decisional because they appear to be earlier drafts of the third, March 2014 RPA (FWS 555). In other words, the December 2013 RPAs do not reflect the FWS’ final position regarding the kinds of changes the November 2013 version of the rule needed in order to comply with the ESA. The December 2013 RPAs, but not the March 2014 RPA, are therefore pre-decisional.
3. 2013 Draft Biological Opinions
We disagree with the Services, however, that the December 2013 draft jeopardy opinions (NMFS 44516.1; FWS 252) are pre-decisional. These two jeopardy opinions represent the final view of the Services regarding the then-current November 2013 proposed rule; the May 2014 no jeopardy opinion represents the final view of Services regarding the later March 2014 revised, proposed rule.
Both the Supreme Court and this court have held that the issuance of a biological opinion is a final agency action. Bennet v. Spear, 520 U.S. 154, 178 (1997); Ctr. for Biological Diversity v. U.S. Fish & Wildlife Serv., 450 F.3d 930, 940 (9th Cir. 2006). So our focus is on whether each document at issue is pre-decisional as to a biological opinion, not whether it is pre-decisional as to the EPA‘s rulemaking. Although the December 2013 biological opinions in this case were not publicly issued, they nonetheless represent the Services’ final views and recommendations regarding the EPA‘s then-proposed regulation. The purpose of the December 2013 jeopardy biological opinions and their accompanying documents was not to advise another decision-maker higher up the chain about what the Service‘s position should be on the proposed rule. Instead, these opinions, created pursuant to an ESA Section 7 formal consultation, contain the final conclusions by the final decision-makers—the consulting Services—regarding whether a proposed regulation will harm protected species and habitat. See
Where, as here, a document is created by a final decision-maker and represents the final view of an entire agency as to a matter which, once concluded, is a final agency action independent of another agency‘s use of that document, it is not pre-decisional. Cf. Maricopa II, 108 F.3d at 1094 (Forest Service‘s internal investigative report was prepared to advise the Chief of the Forest Service on how the agency should respond to misconduct allegations and was thus pre-decisional); Kowack v. U.S. Forest Serv., 766 F.3d 1130, 1135 (9th Cir. 2014) (investigative reports prepared by the Forest Service‘s Misconduct Investigations program manager were meant to assist the agency in making a final decision regarding how to deal with an employee and were thus pre-decisional).
The record reflects the finality of the conclusions in the December 2013 draft jeopardy opinions. The documents had been approved by final decision-makers at each agency: the email correspondence in the record indicates Gary Frazer, the Assistant Director for Ecological Services at FWS who was responsible for overseeing and administering ESA consultations, made final edits to the FWS Service December 9, 2013 jeopardy opinion and that the document was awaiting his autopen signature. NMFS meanwhile was preparing “talking points” for its legislative affairs staff and preparing to release the drafts to the public.
Moreover, the Services’ own account indicates that the EPA made changes to its proposed regulations after December 2013—that is, after both Services’ jeopardy opinions were completed and partially transmitted to the EPA—and that the “final” May 2014 Biological Opinion reflected the Services’ opinion concerning the EPA‘s later revised proposed regulation.
The fact that the December 2013 jeopardy opinions pre-dated the later no jeopardy opinion does not render them pre-decisional. “[M]aterial which predate[s] a decision chronologically, but did not contribute to that decision is not predecisional in any meaningful sense.” Assembly of Cal., 968 F.2d at 921 (census data prepared by the Department of Commerce “solely for the purpose of post-decision
dissemination” if the Secretary decided to adjust the census was not pre-decisional merely because it predated the Secretary‘s decision). The December 2013 jeopardy opinions pre-date the May 2014 no jeopardy opinion, but address and thus make final conclusions about a different version of the EPA‘s rule. These earlier opinions therefore were not pre-decisional with respect to the later opinion, which addressed a different proposed rule.
4. Other Documents
We disagree with the Services’ arguments that the remaining documents, which accompanied the December 2013 draft jeopardy opinions, were pre-decisional because they were either “modified” or excluded from the May 2014 final no jeopardy opinion. These documents—1) a statistical table showing estimated aggregate effects of cooling water intake structures on ESA-protected species (NMFS 61721); 2) several instructional documents for cooling water intake structure operators detailing how to abate the harmful impacts of those structures on specific species (NMFS 5597.1, “Abalone Measures“), (NMFS 7544.2, “Andromous Salmonid Measures“), (NMFS 37695, “Pinniped Measures“), and (NMFS 37667, “Sea Turtle Requirements“); and 3) “Terms and Conditions” that operators of cooling water intake structures must follow in implementing the RPAs (NMFS 14973.1)—were largely instructional, and intended to explain best practices for mitigating the projected, harmful effects of the November 2013 proposed rule. They were not early-stage recommendations for mitigating the impacts of the revised, March 2014 rule, and are thus not pre-decisional as to the May 2014 no jeopardy opinion the Services issued in response to that later rule.
b. Deliberative
To shield documents from disclosure under Exemption 5, the Services must not only show that they are pre-decisional, but also that they are deliberative. Maricopa II, 108 F.3d at 1093. Examples of “deliberative” materials include “recommendations, draft documents, proposals, suggestions, and other subjective documents which reflect the personal opinions of the writer rather than the policy of the agency” or that “inaccurately reflect or prematurely disclose the views of the agency.” Nat‘l Wildlife Fed‘n v. U.S. Forest Serv., 861 F.2d 1114, 1118–19 (9th Cir. 1988) (quoting Coastal States Gas Corp. v. Dep‘t of Energy, 617 F.2d 854, 866 (D.C. Cir. 1980)). With three exceptions noted below, the contested documents here are not “deliberative.”
The Supreme Court has cautioned against relying on a “wooden” facts-versus-opinions dichotomy for determining whether a document is deliberative. Assembly of Cal., 968 F.2d at 921 (citing EPA v. Mink, 410 U.S. 73, 91 (1973)). Accordingly, this circuit applies a “functional approach,” which considers whether the contents of the documents “reveal the mental processes of the decision-makers” and would “expose [the Services‘] decision-making process in such a way as to discourage candid discussion within the agency and thereby undermine [their] ability to perform [their] functions.” Id. at 920–21.
After conducting a de novo review of the documents, we conclude that only three—the December 2013 RPAs (FWS 279, 308) and April 2014 draft jeopardy opinion (NMFS 5427.1)—could reveal inter- or intra- agency deliberations and are thus exempt from disclosure.
The Services argue that all the documents at issue are deliberative because they were created as part of a “lengthy and complicated” consultation process between the Services and the EPA about the EPA‘s water cooling intake structures rule—a process during which many drafts of biological opinions and other documents were circulated intra-agency and inter-agency and “commented upon by others, revised, and recirculated for further discussion.” According to the Services, the Sierra Club‘s request is intended to “uncover any discrepancies between the findings, projection and recommendations” between jeopardy opinions created by “lower-level” Services personnel and the final joint no jeopardy opinion. (quoting Nat‘l Wildlife Fed‘n, 861 F.2d at 1122).
The underlying concern in National Wildlife Federation was that releasing “working drafts” and comments on Forest Plans and Environmental Impact Statements (EISs) prepared by “lower-level” Forest Service employees would “reveal the mental processes” that went into choosing and publishing a final Forest Plan and EIS. Id. at 1119–22. In other words, a reader with access to both these working drafts and the final plan could “probe the editorial and policy judgment of the decision-makers” who selected and issued the final plan. Id.
The draft Forest Plans in National Wildlife Federation were a collection of “tentative opinions and recommendations of Forest Service employees“; the draft EISs compared these alternative Forest Plan proposals, thereby revealing the agency‘s deliberations in choosing a final plan. Id. at 1121–22. This understanding of “deliberative“—meaning reflecting the opinions of individuals or groups of employees rather than the position of an entire agency—is shared among the circuits. See, e.g., Moye, O‘Brien, Hogan & Pickert v. Nat‘l R.R. Passenger Corp., 376 F.3d 1270, 1279 (11th Cir. 2004) (Amtrak OIG
The dissent makes a similar point about the ongoing nature of the consultative process to argue that documents exchanged between the Services and the EPA during that process are protected inter-agency memoranda. It cites to the ESA Section 7 regulations to point out that the Services “shall make available to the Federal agency the draft biological opinion for the purpose of analyzing the reasonable and prudent alternatives.”
Nothing in the documents at issue here indicates whether the EPA sent these types of comments to the Services, how those comments impacted the Services’ jeopardy/no jeopardy conclusion, or anything else about what the substance of those comments might have been. Such documents would likely satisfy the two aforementioned conditions of 1) being an inter-agency memorandum that 2) fell within the ambit of deliberative process.
In the case before the court, we know that the draft opinion was transmitted piecemeal to the EPA, the Services and the EPA agreed to extend the time frame for the consultation, and that “[u]ltimately based on changes to the regulation, the Services’ final conclusion was that the regulation“—the final version—“was not likely to jeopardize the continued existence of listed species nor likely to destroy or adversely modify critical habitat.” (emphasis added). The fact that the decision to revise the rule after the jeopardy finding was the result of additional back-and-forth between the Services and the EPA—deliberative discussions that are not memorialized in the documents before us—does not render the December 2013 opinions or accompanying documents pre-decisional or deliberative as to the Services’ opinion about the November 2013 version of the EPA regulation or as to the Services’ later conclusion about a different version of the rule.
1. 2013 Draft Biological Opinions and Other Documents
After reviewing the documents in this case in camera to make a de novo determination, we conclude that neither the December 2013 draft jeopardy opinions (NMFS 44516.1; FWS 252), nor the accompanying statistical and instructional documents (NMFS 5597.1, NMFS 7544.2, NMFS 37695, NMFS 37667, NMFS 14973.1) were prepared by low-level officials, or contain merely tentative findings. These are final products that reflect the agencies’ findings on the jeopardy posed by the November 2013 proposed rule, and their recommendations for mitigating the harmful impacts of that rule.
We note that the documents do not contain line edits, marginal comments, or other written material that expose any internal agency discussion about the jeopardy finding. Nor do these documents contain any insertions or writings reflecting input
The only thing the December 2013 draft jeopardy opinions have in common with the draft Forest Plans and EISs in National Wildlife Federation is that they were referred to as “draft” documents. But to treat them similarly would ignore clear substantive distinctions. Unlike the documents in National Wildlife Federation, these opinions and accompanying documents represent the final view of the Services on the likely impact of the then-proposed regulation. These final jeopardy opinions from December 2013 pertain to a different rule and are not “earlier draft” versions of the no jeopardy opinion from May 2014; that later opinion addressed a new and different proposed rule.10
Moreover, taking seriously our obligation to consider the underlying purpose of the deliberative process privilege, these documents do not reveal more about the internal deliberative process that the Services went through before issuing their joint May 2014 no jeopardy opinion than what the Services themselves have already disclosed during this litigation: that the initial proposed regulation resulted in final drafts of jeopardy opinions in December 2013, that the EPA received portions of those opinions and proposed a revised regulation at some point after that, and that the Services ultimately issued a no jeopardy opinion for that revised, proposed regulation. Nor do the December 2013 jeopardy opinions reveal either the Services’ internal deliberative processes that lead to reaching those opinions or the EPA‘s internal deliberative process that resulted in revising the draft regulation. Cf. Assembly of Cal. v. U.S. Dep‘t of Comm., 968 F.2d 916, 922–23 (9th Cir. 1992) (disclosing final census figures would not reveal the deliberative process in reaching those figures, particularly when the method used to generate the data was already a matter of public record).
Nor would releasing these opinions and accompanying documents allow a reader to reconstruct the “mental processes” that lead to the production of the May 2014 no jeopardy opinion by allowing one to compare an early draft of that opinion to the final opinion. There is no later draft of the Services’ opinion regarding the November 2013 version of the rule that a discerning reader could compare to the two December 2013 opinions requested here.
Again, the statistical table (NMFS 61721) and the instructional documents and terms and conditions (NMFS 5597.1, NMFS 7544.2, NMFS 37695, NMFS 37667, NMFS 14973.1) summarize the Services’ best practices and recommendations for mitigating environmental harm to certain species, and effectively monitoring the welfare of certain protected species should they appear in the vicinity of a water
2. RPAs
Our analysis regarding the December 2013 RPAs (FWS 279, 308) is different from our analysis concerning the December 2013 Draft Biological Opinions and Other Documents because, as discussed above, they do appear to be successive drafts of the Services’ recommendations for the November 2013 proposed rule. And comparing these drafts would shed light on FWS’ internal vetting process. Thus, considering de novo whether the Services have carried their burden in showing that these documents are deliberative, we find that they have done so.
By comparison, disclosure of only the March 2014 RPA (FWS 555) will offer no insights into the agency‘s internal deliberations. It appears to be the final version in a progression of agency recommendations about how to amend the November 2013 proposed rule. The Services have offered no evidence that there were any subsequent versions of this RPA addressing the November 2013 proposed rule. The March 2014 RPA is therefore not deliberative.
3. April 2014 NMFS Draft Biological Opinion
Finally, we agree with the Services that the NMFS April 2014 draft jeopardy biological opinion is deliberative. As discussed above, it addresses the revised rule that the EPA proposed in March 2014. A reader could thus conceivably reconstruct some of the deliberations that occurred between the April 2014 and May 2014 opinions by comparing the two. Additionally, the Acting Assistant Administrator for NMFS testified in an affidavit provided to the district court that this draft of the jeopardy opinion was only circulated internally between one employee and a group of other lower-level employees. The April 2014 draft jeopardy opinion is therefore deliberative and subject to Exemption 5.
IV. CONCLUSION
For the foregoing reasons the district court‘s order to produce the December 2013 draft jeopardy biological opinions (NMFS 44516.1 and FWS 252), the March 2014 RPA (FWS 555), and the remaining statistical and instructional documents (NMFS 5597.1, NMFS 61721, NMFS 7544.2, NMFS 37695, NMFS 37667, NMFS 14973.1) is AFFIRMED because the record shows that these materials are not both pre-decisional and deliberative and therefore not exempt under
The district court‘s order to produce the December 2013 RPAs (FWS 279, 308) and the April 2014 draft jeopardy opinion (NMFS 5427.1) is REVERSED because these materials are both pre-decisional and deliberative and thus exempt from disclosure under FOIA Exemption 5. The parties agree that reversal would require the district court to perform a segregability analysis on remand. We instruct the district court to perform that analysis.
The case is REMANDED for further proceedings consistent with this opinion.
WALLACE, Circuit Judge, concurring in the result in part and dissenting in part:
I concur in the result reached by the majority as to the April 2014 draft opinion (NMFS 5427.1) and the December 2013 RPAs (FWS 279, 308). I dissent from the result reached by the majority as to the rest of the documents. I respectfully disagree with my colleagues that the deliberative
The majority overlooks the “context of the administrative process which generated” the December draft opinions. NLRB. v. Sears, Roebuck & Co., 421 U.S. 132, 138 (1975). They were part of an inter-agency consultation process.
Moreover, a formal consultation may involve not only the Services making a jeopardy decision, but also a decision about what alternative actions are reasonable and prudent, so-called RPAs. The Services and the agency “work[] closely” on the “development of [RPAs]” contained in a jeopardy opinion. Id. The “provision to review draft biological opinions” provides the necessary “exchange of information for the development of [RPAs].” Id. The Services “will, in most cases, defer to the Federal agency‘s expertise and judgment” as to whether a draft RPA is feasible, but if the Services disagree, the Services make the ultimate call. Id. Thus, even though the Services have discretion as to whether to accept the EPA‘s comments, the purpose of agency review is to seek the agency‘s advice on the draft opinion. Seeking comments on a document presupposes the ability to make changes to it, showing it is pre-decisional. It also shows the deliberative nature of the process. Accordingly, the administrative context shows that draft opinions are generally both pre-decisional and deliberative.
A quick look at the record in this case dispels any doubt that the December draft opinions are pre-decisional and deliberative. The FWS draft opinion requests that the EPA “provide any comments” and states that the FWS would need about ten days after receiving comments, assuming they are not substantial, to issue the final opinion. Likewise, the government submitted declarations of two management-level Service employees stating that the drafts were subject to revision. Gary Frazer, assistant director of the FWS, stated that both draft opinions “were subject to internal review within FWS and the Department of the Interior and consultation with the EPA.” Samuel D. Rauch, an administrator at the NMFS, stated that by transmitting a draft opinion to the EPA, the “NMFS is not rendering a final decision” and the document “remains a draft and is subject to change until final signature.”
The majority and Sierra Club argue that because the December draft opinions were the Services’ “final” word on the November 2013 regulations, the opinions are not pre-decisional. I disagree. The Services’ decision would become final only “once the biological opinion is issued.” Ctr. for Biological Diversity v. U.S. Fish & Wildlife Serv., 450 F.3d 930, 940 (9th Cir. 2006); see also Bennett v. Spear, 520 U.S. 154, 177–78 (1997). The majority‘s observation that the December draft opinions did not contribute to the Services’ later decision about the March 2014 regulations is beside the point. The draft opinions are pre-decisional as to the November 2013 regulations, which the EPA changed before finalizing. That the Services never gave their final word as to those regulations does not strip the drafts of their privileged status. A draft that “die[s] on the vine . . . . is still a draft and thus still pre-decisional and deliberative.” Nat‘l Sec. Archive v. CIA, 752 F.3d 460, 463 (D.C. Cir. 2014); see also Sears, 421 U.S. at 151 n.18 (privilege may apply even if documents “do not ripen into agency decisions“).
The majority and Sierra Club contend that the December draft opinions are not deliberative because the Services’ management had vetted them and they represented the view of the “entire” Services. But even if true, those facts do not show that the drafts are not deliberative. It is well established that circulation of a draft opinion to another agency does not change its privileged status, any more than circulation within the agency. The Supreme Court has spoken decisively on this point: “By including inter-agency memoranda in Exemption 5, Congress plainly intended to permit one agency possessing decisional authority to obtain written recommendations and advice from a separate agency not possessing such decisional authority without requiring that the advice be any more disclosable than similar advice received from within the agency.” Renegotiation Bd. v. Grumman Aircraft Eng‘g Corp., 421 U.S. 168, 188 (1975). Here, the Services had decisional authority in preparing the opinions, but sought advice from the EPA about the decision. Grumman Aircraft teaches that is precisely the type of inter-agency process that Congress designed the privilege to protect.
The majority‘s decision sets out a categorical rule that the deliberative process privilege protects only documents “reflecting the opinions of individuals or groups of employees rather than the position of an entire agency.” This rule contravenes Grumman Aircraft, which acknowledged
Sierra Club makes much of the fact that “the Services typically include draft biological opinions in their administrative records.” Again, even if true, the government‘s waiver of privilege in some contexts does not waive the privilege here, see Assembly of Cal. v. U.S. Dep‘t of Commerce, 968 F.2d 916, 922 n.5 (9th Cir. 1992), a point that Sierra Club concedes.
Finally, Sierra Club argues that the Services’ draft opinions are “significant, legally-mandated drafts, apart from any number of internal or ‘working drafts.‘” It argues that they are “formal documents reflecting and conveying the Services’ conclusions at a prescribed point in the consultation process.” This argument reflects a misunderstanding of the governing regulation. It does not require draft opinions shared with the EPA to be “significant” or to constitute a formal statement of the Services’ conclusions. The regulation states that the Services must, upon the agency‘s request, “make available to the Federal agency the draft biological opinion for the purpose of analyzing the [RPAs].”
In conclusion, the administrative process that generated the draft opinions shows that they are pre-decisional and deliberative. They are pre-decisional because they do not reflect the Services’ final jeopardy and RPA decisions as to the November 2013 regulations. They are deliberative because they are “part of the deliberative process” by which the Services and the EPA consult on those decisions. Nat‘l Wildlife Fed‘n v. U.S. Forest Serv., 861 F.2d 1114, 1118 (9th Cir. 1988). I conclude that the Services may withhold them.
The deliberative process privilege also protects the other documents at issue in this case. Because the NMFS never finalized or adopted the April draft jeopardy opinion (NMFS 5427.1), my analysis above applies to it with equal force. The same is true for the three draft RPAs (FWS 279, FWS 308, FWS 555), which were part of never-finalized jeopardy opinions. In addition, the Services should be able to withhold
In conclusion, I would reverse the district court‘s judgment ordering production of all twelve documents and instruct it to perform a segregability analysis on remand.1
