delivered the opinion of the court:
It is insisted that the court erred in holding the propositions set forth in the statement and in refusing counter propositions asked by appéllant, its contention being that the contract is an entire one, and, the building in which the elevator was to be placed having been destroyed by fire before the time for final payment, without any fault of either party, no recovery for the work done or materials furnished could be had.
As will be seen from the plaintiff’s declaration, it proceeded on two theories: First, that the contract was not an entire one, so far as the payments were concerned; and second, even if it was, under the law plaintiff was entitled to recover the value of the work done and materials furnished prior to the destruction of the building. The judgment is upon this last theory, and is based upon the law as stated in the second of the above propositions.
The theory upon which the second proposition is based is, that under the contract requiring the elevator to be placed in a particular building it was the duty of defendant to furnish and provide that building, and therefore it is liable, even though the destruction was without its fault. The rule of law, as we understand it, is otherwise. Thus, in Addison on Contracts (sec. 554) it is said: “Where a man contracts to expend material and labor on buildings belonging to and in the occupation of the employer, to be paid for on completion of the whole, and before the completion the buildings are destroyed by accidental fire, the contractor is excused from the completion of the work, but is not entitled to any compensation for the work already done, which perished without any fault of the employer.” This doctrine is sustained by Brumby v. Smith,
It is insisted by counsel for appellee, and the decision of the Appellate Court is in conformity with that contention, that a different rule is announced in Cleary v. Sohier,
The case of Rawson v. Clark has no bearing whatever upon this case. There the plaintiff agreed to “manufacture and place in the building” certain iron work for a certain price, eighty-five per cent of which was to be paid on the certificate of the architect as the work progressed, and the balance, fifteen per cent, when the work was completed. The suit was for the iron work which had been manufactured. The evidence showed that the price agreed upon for manufacturing the iron was $206, and for putting it up about $75. Upon the completion of the manufacturing of the iron and the delivery of a small portion of it the defendant notified the plaintiff that the building was not ready for the work, and directed him to send no more until it should be ready, promising to notify him when that time arrived. A week later the building was destroyed by fire. The time required to put up the work would have been about two days, so that it clearly appeared in that case that the plaintiff was prevented from completing the work, not by the destruction of the building by fire, but because the defendant did not have it ready for the work when the plaintiff offered to complete it, and hence we said: “Appellees were no way in default. They were ready and offered to fully perform within the timé limited, but were prevented by appellant. The reason of their not entirely completing their contract by placing the iron work in the building was the default of the defendant in not having a building provided for the purpose.” This certainly does not mean that they were in default in not having a building because it was finally destroyed by fire, but because the building “was not then ready for the work,” etc.
We think the law is, that where a contract is entered into with reference to the existence of a particular thing, • and that thing is destroyed before the time for the performance of the contract, without the fault of either party, both parties are excused from performing the contract, but neither is entitled to recover anything for a part performance thereof. It remains, however, to be determined whether this contract is an entire contract within that rule. It will be seen that by its terms payment was to be made, not upon the completion of the work, but “as the work progresses, as follows: One-half when the engine is on foundation, and final payment to be due and payable when the elevator is put up in good running order,” thus clearly providing for payment by installments. Counsel insist, however, that this does not destroy the entirety of the contract, because, they say, the $1250 was a mere arbitrary sum, fixed without reference to the value of the work done at the time designated for its payment, and that the phrase “when the engine is on foundation,” merely named an arbitrary time at which a partial payment should be made, without reference to the value of the work and material furnished at that time, and that the payment of the installment in that manner was merely for the convenience of the con-' tractor and as an evidence of the good faith of Siegel, Cooper & Co. in completing its part of the contract. If all this were true we are unable to see why the contract is not severable, so far as the payments are concerned. But we do not think the contract is fairly susceptible of that construction. The $1250 is not a mere arbitrary sum fixed without reference to the value of the work done at the time of paying the installment. Payment was to be made as the work progressed,—one-half when the engine was on the foundation. The parties here fixed the sum, by agreement, which should be paid when the work had progressed thus far, and presumably with reference to the value of the material and labor then placed in the defendant’s building. That it served the convenience of the contractor and evidenced the good faith of the employer in no way affects the case.
Parsons in his work on Contracts, (vol. 2,—6th ed.— sec. 517,) speaking of the entirety of contracts, says: “If the part to be performed by one party consists of several distinct and separate items, and the price to be paid by the other is apportioned to each item to be performed or is left to be implied by law, such a contract will generally be held to be severable; and the same rule holds where the price to be paid is clearly and distinctly apportioned to different parts of what is to be performed, although the latter is iu its nature single and entire.” See note c to the same section.
In Schwartz v. Saunders,
We think the Appellate Court properly ruled that plaintiff was entitled to recover under the first count of the declaration, but we are unable to find authority or satisfactory reason upon which to sustain the second. The language, “payment to be made as the work progresses,” cannot, we think, be considered to mean more than that the §1250 should be paid as stated,—that is, it cannot be construed to mean that payments after the engine was on the foundation should be made as the work progressed, it being expressly stated, “final payment to be due and payable when the elevator is put up in good running order,”—that is, when the work was complete. Therefore, on a proper construction of the contract the second proposition should have been refused. There was, however, no error in the judgment of the trial court, because under the first proposition, which, as we have seen, was properly held, the plaintiff was entitled to recover the §1250, with five per cent interest thereon from August 1, 1891, to the date of the judgment, July 5, 1895, which amounted to considerably more than the $1390 recovered.
The judgment below will be affirmed.
Judgment affirmed.
Phillips and Cartwright, JJ., dissenting.
