99 Wis. 437 | Wis. | 1898
The errors assigned and argued on this appeal, that require special mention, may be stated as, (1) granting plaintiff’s request to submit issues to the jury, though such request was not made till the close of the evidence;. (2) allowing a subcontractor’s lien for damages caused by the principal contractor’s negligence and breaches of contract, and for extra work not authorized by the principal contract;. (3) erroneous instructions in regard to the burden of proof.. Such alleged errors will be considered in their order.
1. Actions to enforce mechanics’ and materialmen’s liens, under the law of this state as it existed at the time of the trial, are suits in equity, with the added feature, under sec. 3323, R. S. 1878, giving to either party, on demand therefor, the right to have any issue of fact involved submitted, to a jury, whose verdict shall be conclusive. That section clearly contemplates that the demand for a jury shall be-made before the commencement of the trial and that it shall specify the particular issue or issues to be submitted, to the-end that proper questions, in the form of a special verdict,,
’ 2. There were some exceptions to rulings on objections to evidence, to instructions to the jury, and to findings and conclusions filed by the trial judge, all of which turn on Avhether a subcontractor is entitled to recover for work, labor, and material not authorized by the principal contract, ’ or for damages suffered by the subcontractor through the negligence and breaches of contract of the principal contractor. The trial court proceeded on the theory that the right of the subcontractor to a lien included charges for all Avork, labor, and material furnished to the principal contractor, without regard to the principal contract, and all damages to such subcontractor by reason of negligence of the principal contractor or breach of contract on his part. In regard to the questions covering extra work, the court instructed the jury, in effect, that it included all Avork done by plaintiff for defendant G-ross outside of their contract, without regard to the contract betAveen Gross and Hogan. Sec. 3315, R. S. 1878, as amended, upon which the right to the lien is based, provides that every person who, as subcontractor of a principal contractor, or employee of any contractor or subcontractor, performs any Avork or labor for, or furnishes any material to, a subcontractor, in or about the erection, construction, repair, or protection of any dwelling house or other building, shall be entitled to a lien thereon by complying with the provisions of such section. Manifestly, such right of lien is confined to Avork, labor, and material required by the principal contract. To that extent, by force of the statute, the owner makes the principal con
We do not feel called upon to cite authorities to support this construction of the statute, because its meaning in that regard is considered to be without reasonable question; but see Jones, Liens, § 1300; Tabor v. Armstrong, 9 Colo. 285.
It follows from what has preceded that, whether the alleged extra work and material were included in the original contract between plaintiff and Gross, was not the sole test of whether the same was allowable as against the appellant, Hogan. There was the further test of whether the claim therefor was lienable according to the contract between J-Iogan and Gross, either originally or as subsequently modified. That many of the items of such extra work and ma
A subcontractor cannot make any agreement or incur any liability, not authorized by the principal, contract, to the prejudice of the owner. McCrary Bros. v. Bristol B. & T. Co. 97 Tenn. 469. The contract between Hogan and Gross provided specifically for the manner of ordering extras as between them. Gross could not order any so as to bind appellant’s property, other than bj^ following such contract, unless the provisions in that regard were waived by appellant. The case on this subject does not appear to be covered by the evidence. So we are unable to determine the facts in accordance with the law as here laid down, and direct the proper judgment to be entered.
The $220 found by the jury for extra work in removing frozen dirt from the cellar, made necessary by the breach of contract or negligence of Gross, the $10 included, as appears from the evidence, for rebuilding a wall made necessary by the negligence of plumbers, the $15 for recutting jambs, and some other items caused bj1’ the negligence or mistakes of Gross or those employed by him, were clearly not proper charges against the appellant’s property. It appears from the evidence that the principal contract required Gross to remove a brick wall which was located on the premises; that he tipped such wall into the excavation plaintiff was making for the cellar, and that plaintiff then removed the débris. Whatever was the reasonable cost of removing the wall, as contemplated by the principal contract, may be properly considered as included in the charge made for removing the material of which the wall was composed after it Avas thrown by Gross into the excavation, but the balance of the plaintiff’s claim for removing such material cannot be considered as any part of the work contracted for by the
On a new trial the court can readily determine the facts with proper regard to the legal principles involved, and it is considered best to award a new trial for that purpose. All charges for damages for negligence on the part of the contractor Gross, or to remedy his mistakes and the mistakes or negligence of his employees, and all work, labor, and material not authorized by the contract between him and the appellant, as originally drawn or thereafter modified, all charges for work done for any other contractor than Gross, must be excluded from the amount chargeable to appellant’s property in this action.
3. The charge of the learned court on the subject of the burden of proof is subject to some criticism. He .said: “It is difficult to determine what the law is in regard to the burden ,of proof. The burden of proof is where the weight The general instruction concerning the burden of proof, that it is upon the plaintiff, is not applicable to this case.” It needs no discussion to show the prejudicial and misleading character of such language. The burden of proof is not synonymous with the weight of evidence. It is always on the party plaintiff affirming the existence of a fact in issue, where that fact is essential to his recovery. The weight of evidence may be in favor of one side of a controversy and the burden of proof on the other. If the true meaning of the learned court is that the general instruction ordinarily given, that the burden of proof is on the plaintiff, is not necessarily applicable where a special verdict is submitted, he was right, but we are unable to say that the jury so understood the -court’s instruction. No other instruction was given on the subject, and the jury may have understood that the burden of proof was not on the plaintiff to establish the existence of the facts in issue covered by the special verdict, which were essential to his right to recover. What
By the Court.— The judgment of the circuit court is reversed, and the cause remanded for a new trial.