Shroid Construction, Inc. v. DattomaShroid Construction, Inc. v. Dattoma
—In an action, inter alia, tо recover damages for breach of a collective bargaining agreement, the plaintiff appeals from an order of the Supreme Court, Queens County (Turret, J.H.O.), dated November 21, 1996, which, upon a decision and order of this Court dated March 4,
Ordered that the order is reversed, on the law, and the matter is remitted to the Supreme Court, Queens County, for a calculation of damages to which the plaintiff is entitled as the result of the work slowdown, and for the entry of an appropriate judgment.
This is the second appeal resulting from litigation involving a construction project which wаs governed by a collective bargaining agreement. The plaintiff commenced this action against Joseph Dattoma as president of the International Union of Bricklayers and Allied Craftsmen (hereinafter the Union) to recover damages allegedly sustained when he incited Union members to violate the terms of the collective bargaining agreement. The plaintiff alleged that the defendant’s conduct was intended to put economic pressure on the plaintiff to rehire a certain Union member who had been discharged from the project.
After a hearing, the Judicial Hearing Officer issued a “Decision, Findings of Fact and Conclusions of Law” dated February 22, 1994. In relevant part, that document read as follows (italicized portions had been inserted by hand):
“7. That on February 3, 1989, the [Union], through its constituent members, in retaliation for the discharge of [the Union member in question], commenced a work-stoppage at plaintiffs York College project site in contravention and breach of the Collective Bargaining Agreement in full force and effect between the parties hereto * * *
“9. That on February 8, 1989, [the Union’s] constituent members returned to work at plaintiffs York College project site.
“10. That from February 8, 1989 through and including June 13, 1989, [the Union’s] constituent members commenced a work slow-down at plaintiffs York College project site in retaliation for the discharge of [the Union member in question] by plaintiff.
“11. That the work slow-down by [the Union’s] constituent members was designed to put economic pressure on plaintiff.
“12. That [the] Union local sanctioned the actions оf its constituent members by refusing to direct them back to work
“13. That [the] Union local condoned the actions of its constituent members, and exhibited indifference to plaintiff’s plight, by failing and refusing to take any actions or steps to direct its constituent members back to work or to cease their work slow-down.
“14. That as a direct and proximate result of the actions of [the] Union local, its constituent members and agents, plaintiff incurred additional costs and has suffered monetary damages.
“15. That as a direct and proximate result of the actiоns of [the] Union local, its constituent members and agents, plaintiff has suffered actual damages on Feb 3, 6, and 7, 1989 in the amount of $15,000”
The Supreme Court issued an order dated April 5, 1994, directing the entry of a judgment awarding the рlaintiff $15,000 in damages. On appeal by the plaintiff, this Court modified the order by awarding the plaintiff an additional $414.12 in damages in accordance with the plaintiff’s prоof of actual damages resulting from the work stoppage (see, Shroid Constr. v Dattoma,
Upon remittitur, the Judical Hearing Officer issued an order dated November 21, 1996, which reads, in relevant part, as follows: “It was not my intention by these findings of fact to rule that [the] Union acted improperly in any respect to the work slowdown. To the extent that those findings of fact can be construed to so find, they are in the interest of justice amended. I find ho improper conduct by the union in connection with a work slowdown. It wаs my intention to find only improper conduct on the part of the union in respect to the three day work stoppage. Paragraph 15 of the findings of fact submitted by plaintiff was altered in my handwriting by striking damages proposed in the sum of $155,715.12 and inserting ‘actual’ damages ‘on February 3, 6, and 7, 1989’ in the amount of $15,000.00. It was for these damages only for work stoppage that I found Union liable.”
The plaintiff now appeals from the order of November 21, 1996, on the ground, inter alia, that the Judicial Hearing Officer was without power to make a substantive change in his findings, particularly in light of our determination on the prior appeal. The plaintiff is correct.
This rule applies with equal force to the amendment of the decision of a Referee upon which judgment may be entered (see, Corr v Hoffman,
Here, the Judicial Hearing Officer originally determined that the defendant had sanctioned a work slowdown in violation of the collective bargaining agreement. The amendment upon remittitur to vacate the findings of fact regarding the slowdown cannot be viewed as a сorrection of a mere clerical error as it clearly affected a substantive aspect of the dispute between the parties (see, Saleh v Karp, supra; Fudin v Fudin, supra).
Morе significantly, this Court previously determined that there was support in the record for the original determination, and directed the Supreme Court to calculаte the plaintiff’s damages occasioned by the slowdown. In doing so, this Court rejected the defendant’s argument that any damages flowing from the alleged slowdоwn were purely speculative. The defendant may not raise the same argument on this appeal. Our decision on the prior appeal constitutes the law of the case, and is thus binding not only on the Supreme Court but on this Court as well (see, Martin v City of Cohoes,
Under the circumstances, it was improper for the Judicial Hearing Officer to attempt to amend his findings after they